Atch_1_SOW.pdf
PDF 3 MB Posted
- Attached to
- Replace 34 Shutters-TIMU Federal contract opportunity
- Solicitation number
- 140P5423R0010
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5423R0010_Amd_0002.pdf | ||
| Atch_1_to_Amd_1_QandAs_0001.pdf | ||
| Sol_140P5423R0010_Amd_0001.pdf | ||
| Sol_140P5423R0010.pdf | ||
| Atch_3_Site_Visit_Info.pdf | ||
| Atch_2_DOL_DBA_WD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P5423R0010 Attachment 1
Page 1 of 9 Pages
TIMUCUAN ECOLOGICAL AND HISTORIC
PRESERVE
JACKSONVILLE, FL
STATEMENT OF WORK (SOW)
PMIS 320370
Remove and Replace with In-Kind Shutters on the Main House at Kingsley Plantation
DATED:
March 2023
NATIONAL PARK SERVICE
SOUTHEAST REGION
SOUTH MAJOR ACQUISITION BUYING OFFICE
Page 2 of 9 Pages
Statement of Work (SOW)
Removing and Replacing the Shutters on the Kingsley Plantation Main House
1. Description of Services:
This project entails the removal of thirty-four (34) sets of existing shutters, site preparation, fabrication of new shutters, purchasing new historic replica hardware, installing new wooden shutters and hardware, and repairing any damage from the removal and installation of shutters and hardware on the first and second story of the Main House at Kingsley Plantation. Shutters will be replaced with historically accurate replicas, constructed out of acetylated wood, and will match their corresponding shutter that is currently in place. The current shutters were fabricated and installed in mid-2000s and they have reached the end of their life. This first story contains windows #1-24 and the second story contains windows #25-#34. The style of the shutters will remain the same as they are currently, however the shutter hardware will be changed to be compatible with the historic construction. The structure requires new shutters and hardware that can better withstand the harsh environment of being situated on the North Florida coast.
This project requires an experienced contractor to design and execute the job. The Contractor shall provide all labor, material, tools, equipment, supervision, and other related items required to the complete the project as per scope of work, specifications. Contractors are advised to visit the site, verify the existing site conditions to develop their proposal.
From the time of its construction in 1797-98 until 1923 the Main House at Kingsley Plantation served as residence. John McQueen, who owned the property in 1797, lived there until 1804 when he sold the property to John McIntosh. John McIntosh eventually fled Florida in 1813 after the failed Patriot’s Rebellion. McIntosh subsequently leased his property to Zephaniah Kingsley in 1814 and moved his family and enslaved laborers shortly thereafter.
Kingsley purchased the property in 1817 and remained there until 1837 when he moved his family and slaves to Haiti. He sold the plantation to his nephews, Ralph King and Kingsley Beatty Gibbs. Kingsley Beatty Gibbs eventually moved to the property in 1841, but was only able to live there eleven years, when under significant financial strain he mortgaged the property and moved with his family to St.
Augustine. The Main House would not be lived in again until Charles Barnwell moved with his family to the island in 1860. At the end of the Civil War the Barnwells mortgaged the property and the house was empty again. It was not until 1869 that Rollins family moved into the house and a family member would live there until 1906, when Hannah Rollins passed away. Hannah and John Rollins’s daughter Gertrude Rollins Wilson purchased the house in 1906 and retained ownership until 1923 when she sold the property to the Fort George Club Corporation.
The property then became a club and the Main House became quarters for the club members when they visited the island. The Fort George Club sold the Main House to the State of Florida in 1955 and it has operated as a museum/historic house ever since. The state transferred ownership to the National Park Service 1991.
Page 3 of 9 Pages
The Kingsley Plantation, including the Main House, is a contributing property of the Kingsley Plantation Historic District, which is listed on the National Register of Historic Places. The Kingsley Plantation is associated with the early settlement of northeast Florida, antebellum Florida, antebellum plantation agriculture, postbellum farming adaptations to a new post-war economy, and finally to the twentieth-century transition to recreational use. It is also significant for its association with Zephaniah Kingsley.
The Windows on the Main House
The house was originally constructed with two sizes of windows in the first and second stories. Several additional windows were installed throughout the house between 1878 and 1886. All the windows are divided light, double-hung types. The original windows have six-over-six sashes and measure approximately 2’-9” by 5’-4” on the first floor (Windows 1, 14, 17, 21 and 22) and 2’-3” by 3’-7” on the second floor (Windows 25 through 33). The windows added later have six-over-six and two-over-two sashes. All but one of the later six-over-six windows vary in size from 2’-6” by 5’-1” to 2’-9¾” by 5’-5” (Windows 18 through 20). Window 34, located on the second floor, was added circa 1886 and measures 2’-3” by 3’-7”. The two-over-two windows are larger, measuring 2’-9” by 7’-1” on the eastern bays (Windows 2 through 13) and 2’-9” by 8’-10½” on the North and South Porches (Windows 15, 16, 23 & 14).
2. General
Contractor shall restore all surfaces disturbed by construction to match with existing finish. Any deviation from the original contract/scope of work shall be informed to COR before work begins. No additional work or changes will be carried out without a contract modification.
3. Tasks
• #1-Assessment: This task consists of a site visit to provide recommendations and a detailed scope of work. This work consists of conducting a facility survey of the shutters of the Main House at Kingsley Plantation. The assessment will also identify alternatives to correct any weaknesses or deficiencies that may be found.
• #2-Shutter Removal: This item consists of the removal of the existing shutters and hardware, including shutter dogs with wood blocks. Note that shutters are currently missing at some windows, but replacement shutters will be required at all 34 windows, as described in the assessment. Contractor is responsible for the disconnection of the existing shutter, removal from the plantation, and proper disposal offsite.
• # 3-Fabrication of New : Task includes fabrication of wood shutters; fittings; hardware;
patching; coatings; protection of existing historic structure and/or fabric, and all other appurtenances.
o The contractor shall be required to complete a site visit where physical measurements of each identified opening shall be completed. A unit-by-unit shutter survey shall be completed and submitted for review and obtain written approval prior to ordering materials or starting any fabrication work. The purpose of this survey is to verify dimensions prior to fabrication. Submittal shall include the following:
Page 4 of 9 Pages
All shutters will be given a unique identification number, cross referenced to a building key plan.
Each shutter type must be identified separately on a minimum 8.5 by 11-sheet.
Shop drawings will be accepted. For this project, there may be multiple sizes of the same shutter type.
Each sheet must include an interior and exterior view of the shutters.
A tabular summary of each shutter unit describing the material, frame and casing trim material (as applicable), operating hardware, finish hardware, and other notes as needed.
Final completed schedules shall be submitted as a post award submittal, for review and approval prior to ordering materials or starting any fabrication work.
All dimensions shall be verified in the field.
Park COR and a NPS historical architect shall review the window schedule submittal and provide a final acceptance/revision for any proposed replacements.
• #4-Shutter Installation: This item consists of the installation of the shutters and hardware Kingsley Plantation. Payment shall cover the cost of labor, tools, equipment, and material, and performing all operations in connection with the installation of the door in accordance with the written specifications and applicable drawings. Includes the shutters, shutter hardware, lift (if needed), spare parts, spare hinges, and painting of window head, jambs, and sill. This item also includes mobilization, costs of preparatory work and operations, including but not limited to those necessary for the movement of personnel, equipment, supplies, materials and incidentals to the project site, site facilities necessary for the work on the project, traffic control, and all other work or costs necessary for the completion of the project, inspections, testing, system startup, project closeout, punchlists, final cleanup and demobilization from the project site upon completion of work. Also included are costs related to fees, permits, licenses, insurance, bonds, taxes and all other costs that the contractor is to obtain or pay to perform the work. Finally, it includes construction management and inspection.
4. Specifications
a) Work under this contract shall be carried out strictly in accordance with specifications attached and will meet US and Local codes.
b) Work includes all finish Carpentry required for the shutters on the Main House at Kingsley
Plantation.
c) Shutters will be constructed to fit their corresponding window. Total of 34 shutters.
d) The shutters shall be of high quality wood and finished to have a smooth finish.
e) Replacement wood for damaged wood at siding, window frames, and exterior trim:
a. Contractor is to submit a replacement material for all wood for the project, which is to have the characteristics of the original, old-growth wood. Replacement wood is to be dimensionally stable and long-lasting. Wood shall be highly rot-resistant and still workable for the specified repairs.
b. Shutters to be manufactured from acetylated wood.
Page 5 of 9 Pages
f) Shutters will be replaced with historically accurate replicas. Wood and other materials used will be consistent with the colonial style of the historic site, to prevent an impact to the historic integrity of the house.
g) Current hardware will be replaced with period-appropriate hardware, to be powder coated black:
i. Shutter hardware to match ACME Style Mortise Shutter Hinges in the correct size for the existing window openings.
ii. Shutter hardware may be from a manufacturer of period-replica hardware, if they meet specifications, or may be custom fabricated to fit the project.
iii. Hardware must allow for proper clearance away from window opening so that the shutter will sit against the exterior wall correctly and close securely.
h) All hardware and fasteners shall be made and cast from C95400 aluminum-bronze, or similar casting grade of aluminum bronze such as Mil-B-16033, QQ-C-390 G5, QQ-B-671, Class 3, SAE J461 or J462, ASTM B505 or B505M for strength and maximum corrosion resistance. Chemical Composition: Cu - 83.0% minimum; Fe – 3to5%; Ni(including Co) – 1.5%; Al – 10to11.5%; Mn – 0.5%. Density: 0.269 lbs/cubic inch.
i. Contractor to submit shop drawings for all hardware prior to fabrication. Once shop drawings have been approved, a minimum of 6 samples are to be fabricated and submitted for approval.
ii. Complete the application of primer and paint at all bronze hardware:
1) The proposed paint system for bronze is to be submitted and must be appropriate for adhesion to bronze.
2) Metal elements shall be painted to match the existing color.
i) All metal in contact with wood, including attachment hardware, hinges, latches, etc., must be C95400 aluminum-bronze, or similar casting grade of aluminum bronze such as Mil-B- 16033, QQ-C-390 G5, QQ-B-671, Class 3, SAE J461 or J462, ASTM B505 or B505M for strength and maximum corrosion resistance. Chemical Composition: Cu - 83.0% minimum;
Fe – 3to5%; Ni(including Co) – 1.5%; Al – 10to11.5%; Mn – 0.5%. Density: 0.269 lbs/cubic inch . Metal must be a type compatible with the wood and must not corrode when in contact with other metals.
j) The new shutters will have the same sized louvres as the existing shutters which shall have the same orientation and be operable.
k) The contractor shall fill holes, cracks, gaps with compatible patching material; finish patch to match surrounding surface shape, texture and color. Larger repairs should be completed with replacement or a dutchman repair using a compatible wood match.
l) Touch up paint at surrounding trim, window sashes, wood siding, etc. due to any damage arising from installation of shutters.
m) Clean, sand and remove dust from all surfaces to be finished. All finish carpentry to be sanded smooth, and all blemishes filled so that no graining, knots, dents, etc., show thru painted finish. Shutters to be shop painted and touched up in field.
n) Apply as needed coats of smooth, even coat/layer of sanding primer and Benjamin Moore Aura Paint for exterior use needed for finish coats to achieve the smooth finish.
a. Paint color of shutters to match existing shutter color at all locations.
Page 6 of 9 Pages
b. Primer shall be compatible with finish coat. All sides are to be primed prior to painting. Two finish coats are required.
c. Paint system and paint drawdowns shall be submitted for review prior to proceeding with work.
o) The layout, location, style and finish appearance of ALL materials used in shutter painting will be approved by Contracting Officer Representative (COR), before any work begins.
p) All wood trim (head, jambs, and sill) to be repainted with coordinating colors after installation.
q) No clean up residue will be left on adjacent finished surfaces, trim plates, or fixtures.
r) The finish will have uniform color depth and appearance in all lighting conditions.The surface finish will be free of surface defects, irregularities and any physical damage.
s) Paint Schedule: Provide color samples from manufacturer’s line of colors for approval by
COR. All paint colors to match existing at all locations.
t) Any damage to existing materials, such as floor, walls, siding, or other, will be the contractor’s responsibility to repair to match existing materials.
u) Area of work will be closed off to the public for safety.
v) Entrance will be closed at the end of day, if the job is not completed contractor will install a temporary zero visibility door for security.
5. Submittals
a) Submit product data for all paint products, wood, and metal hardware.
b) Samples for Initial Selection Purposes: Submit manufacturer’s standard size samples of colors and finishes.
c) Samples for Verification: Submit samples of all hardware. Shop drawings.
6. Product handling:
a) Place materials in area protected from weather immediately upon delivery to project.
b) Store above ground on blocking and cover with waterproof covering and provide adequate ventilation.
c) Do not store seasoned materials in damp or wet area of building.
d) Protect sheet materials from corner breakage and surface damage while handling.
e) Protect treated materials from high humidity.
f) The contractor shall maintain existing utilities indicated to remain and protect them against damage during the works.
g) Damages caused by demolition and renovation operations, shall be repaired by the contractor at no additional cost to the Government.
h) The contractor shall transport from site all debris, rubbish, and materials resulting from demolition operations and dispose offsite on a daily basis in accordance with local regulations.
Page 7 of 9 Pages
7. Execution of Work:
a) Do not disturb portions of project site beyond areas in which the Work is indicated.
Construction zones shall be fenced, barricaded, and/or marked with COR approved construction barrier fencing, plastic, chalked, and/or portable fencing before any construction activity. The fencing and/or markings shall define the construction zone and confine activity to the minimum area required for construction. All protection measures shall be clearly stated in the construction documents, and workers will be instructed to avoid conducting activities beyond the construction zone as defined by the construction zone fencing or markings.
b) The Contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with MUTCD-2003.
c) Parking of vehicles shall be limited to existing roads, in legally designated areas, and within approved staging area(s).
d) Coordinate construction efforts with the COR such that there is minimal impact to the work of NPS personnel, other contractors and the visiting public.
e) The Contractor shall allow for Government occupancy of project site, and keep roadways clear and available to the Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
f) The Contractors are advised to review the material specifications and scope of work. The Contractor should visit and walk through the site to familiarize themselves with the site conditions to understand the exact quantum of work.
8. Site Clearance and Cleanup
a) The Contractor shall clear away all debris and excess materials accumulated at the site and dispose of it away from Embassy premises, maintaining a neat site condition. On completion of project, Contractor shall remove all surplus materials and leave the site in a broom clean condition.
9. Workmanship
a) Workers working on the site shall be skilled in their job and have related job experience.
b) The quality of all work shall be the responsibility of the Contractor. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings. Quality Control Daily Reports shall be completed by the Quality Control Supervisor. Test reports shall be completed by person performing the test.
Page 8 of 9 Pages
10. Working Hours:
a) Working hours shall be from 7:00 A.M. to 2:30P.M Monday thru Friday. No work shall be done Saturdays, Sundays and holidays without the prior approval of the COR.
11. Safety Measures
a) While on Park Property Provide the following:
i. First aid supplies
ii. Personal protective equipment that meets the requirements of NIOSH and MSHA
iii. Emergency instructions, including telephone numbers and reporting instruction for ambulance, physician, hospital, fire department and park police. Place in conspicuous locations at the worksite
iv. Adequate egress at all times in accordance with the Life Safety Code (NFPA 241)
v. Hard hats for all employees and for up to 6 visitors
vi. Designate and post signs in all hard hat areas
b) Provide training for first aid and lift safety.
c) Performing tasks that create hazards for workers. The requirements listed below are minimum requirements.
d) Safety glasses will be worn while performing the following
i. Drilling
ii. Chiseling, chipping
iii. Wood working, metal working
iv. Hearing protection will be worn for all those who operate loud power tools and equipment.
v. Hard hats will be worn in areas where falling objects are a hazard.
vi. Gloves will be worn for cleanup and removal of work area waste and materials.
vii. Proper footwear will be worn by all workers, including safety shoes.
e) The contractor will identify a safety officer for each project responsible for the following:
i. Use of Signs and Barriers
ii. Barriers and signs shall identify workplace hazards and special instructions.
iii. Minimum space required to perform work shall be identified.
f) Waste cleanup and removal
i. All excess or waste materials will be removed from the site at the close of each work day.
ii. Debris will be removed to include food bags and containers. Staging of materials shall be in an agreed upon location.
iii. Ribbon, tape, fencing or portable barriers will create a controlled area around work site.
g) Electrical issues
i. All power cords and power taps will be wired appropriately, leaving no exposed wires that are live or could come in contact with staff.
Page 9 of 9 Pages
ii. While working on electrical systems proper lockout/tag-out procedures will be followed, and the circuit being worked on will be de-energized (turned off at the main breaker).
iii. Power cords and temporary power will be GFCI protected and shall not be placed in areas that are prone to flooding or are wet, (i.e. running through puddles on the floor).
iv. Equipment will be plugged into a standard GFCI-protected receptacle and not wired directly into power taps.
12. Warranty
a) The contractor shall guarantee that all work performed will be free from all defects in workmanship and materials and that all installation will provide the capacities and characteristics specified. The contract further guarantees that if, during a period of three years from the date of the certificate of completion and acceptance of the work, any such defects will be repaired by the contractor at his expenses.
b) A warranty of 12 months will be provided for all workmanship and hardware.
c) Accetylated wood will have a warranty of 50 years.
Attachments:
Appendix A-Drawings of Structure
Appendix B-Photographs of Elevations of Structure and Windows
Appendix C-Example of Hardware to be used
Appendix A
Drawings
Page 1 of 2 Pages
Appendix A
Page 2 of 2 Pages
Appendix A (cont’d)
Appendix B
Page 1 of 14 Pages
Appendix B
Photographs
Appendix B
Page 2 of 14 Pages
Photograph 1: South Elevation; Going from left to right on first story Window 23, 24, and 1; on second story Window 33, 34, and 25; looking north
Appendix B
Page 3 of 14 Pages
Photograph 2: South Elevation; first story going left to right Window 22 and 23; second story Window 33, 34, and 25; looking North
Appendix B
Page 4 of 14 Pages
Photograph 3: West Elevation; First Story going from left to right Window 18, 19, 20, and 21;
second story Window 31 and 32; looking East
Appendix B
Page 5 of 14 Pages
Photograph 4: West Elevation; First story looking left to right Window 18, 19, and 21; Second story Window 31 and 32; looking East
Appendix B
Page 6 of 14 Pages
Photograph 5: West Elevation; First story Window 18; Second story Window 31 and 32; looking East
Appendix B
Page 7 of 14 Pages
Photograph 6: North Elevation: First story looking left to right Window 14, 15, 16, and 17; Second story Window 28, 29, and 30; looking South
Appendix B
Page 8 of 14 Pages
Photograph 7: East Elevation; First story left to right Window 3, 4, 7, 8, 9, 10, 11, 12, and 13; second story 26 and 27; looking West
Appendix B
Page 9 of 14 Pages
Photograph 8: East Elevation; First story left to right Window 4, 6, 7, 8, 9, 10, 11, 12, 13; Second story 27
Appendix B
Page 10 of 14 Pages
Photograph 9: East Elevation; First story left to right Window 2. 3. 4. 5. 6, 7, and 8; Second story Window 26; looking West
Appendix B
Page 11 of 14 Pages
Photograph 10: South Elevation; Window 1
Appendix B
Page 12 of 14 Pages
Photograph 11: South Elevation; Window 23
Appendix B
Page 13 of 14 Pages
Photograph 12: West Elevation; Window 21
Appendix B
Page 14 of 14 Pages
Photograph 13: East Elevation; Window 4
Page 1 of 1 Page
Appendix C Example of Hardware