Appendix F - Certification Test Plan.pdf

PDF 439 KB Posted

Attached to
B3907 Remote Pump Module Upgrade Federal contract opportunity
Solicitation number
FA812522Q0089
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

This certification test plan outlines requirements for validating repairs and upgrades to a Remote Pump Module System at Tinker Air Force Base. Initial certification requires verifying flow, pressure, and temperature specifications across boost and main pumps at maximum output. Full certification involves simultaneously running three test units across four test stations while maintaining supply parameters and recording pressure, flow, and temperature measurements at regular intervals. Test results must be compiled in a spreadsheet and provided to the government for evaluation.

The related solicitation seeks quotes for a B3907 Remote Pump Module Upgrade set aside for small businesses. Responses are due by the closing date on page one and must include company information, pricing on page three, and a written statement explaining how the offeror will meet technical requirements. The solicitation is issued by the Air Force Sustainment Center for the Department of the Air Force Materiel Command.

View the file

Other files for this federal contract opportunity

Other files attached to B3907 Remote Pump Module Upgrade, newest first.
File Type Posted
Solicitation Amendment FA812522Q00890001 SF 30.pdf PDF
Appendix J - Design Guideline 450.pdf PDF
Appendix E - Environmental Language.pdf PDF
Appendix B - RCM and Vib Sev Chart.pdf PDF
Appendix I - UUT TOs_note.pdf PDF
Appendix D - Glossary and Definitions.pdf PDF
Appendix G - Pump Module Operations Manual_note.pdf PDF
SOW_B3907 Pump Module.pdf PDF
Appendix A - Equipment List.pdf PDF
Appendix C - Safety Specifications.pdf PDF
Appendix H -Drawings_note.pdf PDF
Solicitation - FA812522Q0089.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW-H2WC10 25 April 2022

Page | 1

Appendix F – Certification Test Plan Remote Pump Module System

1. Introduction This document describes the certification test plan to validate the repairs & upgrades to the Remote Pump Module System (RPMS), pump rack located in Building 3907 Room 115, and control cabinets located remotely in Room 118 are successful. The full certification process is to verify the RPMS will supply adequate MIL-PRF-7024 Type II Calibration Fluid to test stands as required. During certification the contractor shall perform a particle count of RPMS fluid, as identified below, to insure no contamination to the system or attached test stands has occurred.

2. Initial Certification

2.1 Initial certification procedure is as follows:

2.1.1 Use the newly installed and calibrated pressure and flow supply header measurement device.

2.1.2 Turn on successive boost pumps and main pumps to provide maximum output flow and maintaining within pressure limits.

2.1.3 As each main and boost pump is open record the flow and pressure measurements and note which pumps are running.

2.1.4 At maximum output flow, take and record three (3) pressure, flow, and temperature measurements spaced at 20 minute intervals.

2.1.4.1 Flow accuracy shall be ± 20 GPM (Gallons per Minute) and pressure accuracy shall be ± 20 PSIG (Pounds per Square Inch, Gauge Pressure) per Appendix H inlet flow requirements.

2.1.4.2 Temperature shall be controlled to 85 ± 10°F (Degrees Fahrenheit) per SOW Appendix G and H.

2.1.5 Perform a particle count test per manual 1TL32-6718-2 (SOW Appendix G) and record results. Maximum Allowable contamination per 50 ml sample is listed below.

Contaminate Particle Size Maximum Allowable

Metal > 5 Micron 40,000

> 25 Micron 2,000

> 101 Micron 0

Fiber 7

2.1.6 Compile and document all results in spreadsheet form using Microsoft Excel.

3. Full Certification Process

3.1 Full Certification procedure is as follows:

3.1.1 Government operator will simultaneously run UUT Final Test on 3 of the 4 test stations supplied by the RPMS.

3.1.1.1 UUTs ran will be qty. one (1) Augmentor Fuel Control (AFC) and qty. two (2) Main Fuel Controls (MFC) in accordance with their applicable USAF Technical Order (T.O.).

3.1.1.2 UUTs will be serviceable (A-condition) assets, selection will be determined by availability.

SOW-H2WC10 25 April 2022

Page | 2

UUT Part number Technical Order

F100-220 AFC 441422-7 6J3-2-34-2-2

F100-220 MFC 441610-21 6J3-4-118-2-2

F100-220 MFC 441396-21 6J3-4-118-2-2

F100-220 MFC 442645-23 6J3-4-118-2-2

F100-229 MFC 441721-10 6J3-4-118-2-2

3.1.2 Before stands are run simultaneously first verify each stand is receiving flow as requested from the RPMS. Verify RPMS supplied flow and pressure remain in limits.

3.1.3 For the simultaneous test stand run, UUTs will be set at high flow and constant rate, Test point 11.090 (Resolver Calibration) or equivalent, to obtain calibration fluid inlet readings.

3.1.3.1 Take and record three (3) pressure, flow, and temperature measurements spaced at 20 minute intervals for each test stand (9 readings per stand, 27 total readings).

3.1.3.2 Record the UUT part numbers and test stand OC numbers ran.

3.1.3.3 Perform a particle count test per manual 1TL32-6718-2 (SOW Appendix G) and record results.

3.1.4 Repeat steps 3.1.3 through 3.1.3.3 twice more.

3.1.5 Compile and document all results in spreadsheet form using Microsoft Excel

4. Test Report Provide initial and full certification results (2.1.6 and 3.1.4) to Government POC for evaluation of SOW compliance.

1. Introduction
2. Initial Certification
2.1 Initial certification procedure is as follows:
2.1.1 Use the newly installed and calibrated pressure and flow supply header measurement device.
2.1.2 Turn on successive boost pumps and main pumps to provide maximum output flow and maintaining within pressure limits.
2.1.3 As each main and boost pump is open record the flow and pressure measurements and note which pumps are running.
2.1.4 At maximum output flow, take and record three (3) pressure, flow, and temperature measurements spaced at 20 minute intervals.
2.1.4.1 Flow accuracy shall be ± 20 GPM (Gallons per Minute) and pressure accuracy shall be ± 20 PSIG (Pounds per Square Inch, Gauge Pressure) per Appendix H inlet flow requirements.
2.1.4.2 Temperature shall be controlled to 85 ± 10 F (Degrees Fahrenheit) per SOW Appendix G and H.
2.1.5 Perform a particle count test per manual 1TL32-6718-2 (SOW Appendix G) and record results. Maximum Allowable contamination per 50 ml sample is listed below.
2.1.6 Compile and document all results in spreadsheet form using Microsoft Excel.
3. Full Certification Process
3.1 Full Certification procedure is as follows:
3.1.1 Government operator will simultaneously run UUT Final Test on 3 of the 4 test stations supplied by the RPMS.
3.1.1.1 UUTs ran will be qty. one (1) Augmentor Fuel Control (AFC) and qty. two (2) Main Fuel Controls (MFC) in accordance with their applicable USAF Technical Order (T.O.).
3.1.1.2 UUTs will be serviceable (A-condition) assets, selection will be determined by availability.
3.1.2 Before stands are run simultaneously first verify each stand is receiving flow as requested from the RPMS. Verify RPMS supplied flow and pressure remain in limits.
3.1.3 For the simultaneous test stand run, UUTs will be set at high flow and constant rate, Test point 11.090 (Resolver Calibration) or equivalent, to obtain calibration fluid inlet readings.
3.1.3.1 Take and record three (3) pressure, flow, and temperature measurements spaced at 20 minute intervals for each test stand (9 readings per stand, 27 total readings).
3.1.3.2 Record the UUT part numbers and test stand OC numbers ran.
3.1.3.3 Perform a particle count test per manual 1TL32-6718-2 (SOW Appendix G) and record results.
3.1.4 Repeat steps 3.1.3 through 3.1.3.3 twice more.
3.1.5 Compile and document all results in spreadsheet form using Microsoft Excel

4. Test Report