This is a Requirements Document for an Environmental Chamber solicited by the National Institute of Standards and Technology (NIST) Engineering Laboratory. The document seeks a single environmental chamber for the Materials and Structural Systems Division to conduct durability and accelerated aging research on infrastructure materials like concrete and polymers. Key technical specifications include an internal volume not exceeding 4 cubic feet, ability to hold 30 4-inch by 8-inch or 20 4-inch diameter by 2-inch tall concrete specimens, temperature range of -20°C to 180°C, humidity range of 10% to 95%, and dimensions fitting within 33x36x48 inches.
The solicitation (AMDTCRQ2501844) is a small business set-aside Request for Quotation (RFQ) using Lowest Price Technically Acceptable (LPTA) evaluation criteria. Delivery is required within 12 weeks after receipt of order, with payment contingent upon successful installation, testing, and acceptance. The contractor must provide a one-year warranty, and the equipment must be new, with no used, remanufactured, experimental, or prototype items accepted. Responses must be submitted electronically, and the final destination is NIST's Gaithersburg, Maryland campus.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Requirements_rvsd Amendment 002.pdf | ||
| Environmental Chamber-QA.pdf | ||
| RFQ attachment - FAR provisions.docx | DOCX document | |
| Requirements.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUIREMENTS DOCUMENT
Title: Environmental Chamber Requesting Lab: Engineering Lab; Materials and Structural Systems Division
I. BACKGROUND INFORMATION
The National Institute of Standards and Technology (NIST) Engineering Laboratory (EL) Materials and Structural Systems Division (MSSD) studies the durability and service life of infrastructure materials (polymers, concrete, engineered composites, etc.) for resilient infrastructure applications.
One of the key research focuses is to evaluate the durability of these materials when exposed to a wide range of environmental conditions. As such, accelerated aging of materials using elevated temperature and humidity is a common practice. The MSSD will benefit from an environmental chamber to condition and age concrete materials for the “Engineered Materials for Resilient Infrastructure” program in projects such as “Assessing Pyrrhotite in Concrete”, “Forward Looking Building Codes”, and “Additive Manufacturing with Cement Based Materials” as well as polymeric materials for the “Measurement Science for Service Life Prediction of Polymeric Components Used in PV Systems”.
Purpose/Objective: The purpose of this requirement is to obtain an Environmental Chamber to reliably condition materials for testing and perform accelerated aging tests. The environmental chamber shall be capable of conditioning infrastructure materials such as concrete specimens as well as cementitious and polymeric materials. The MSSD is anticipating an expansion of its infrastructure materials testing capabilities.
II. MINIMUM REQUIREMENTS
The Contractor shall provide an Environmental Chamber that meets all technical specifications identified below. All items must be new. Used or remanufactured equipment will not be considered for award. Experimental, prototype, or custom items will not be considered. The use of “gray market” components are not authorized for sale in the U.S. by the Contractor is not acceptable. All line items shall be shipped in the original manufacturer’s packaging and include all original documentation and software, when applicable.
Line Item 0001:
Description: Environmental Chamber Quantity: ONE (1)
A. Technical Specifications
a. Internal volume cannot exceed 4 cubic feet (113 L)
b. Chamber interior dimensions (working area) must be large enough to hold 30 4-inch by 8-inch cylindrical concrete specimens up to 20 4-inch diameter by 2-inch tall concrete specimens (approximately 2.5 lbs. each) where specimens are not touching one another allowing sufficient air flow between cylinders.
c. Must fit within the available laboratory space for the chamber of 33 inches wide, 36 inches deep, and 48 inches tall.
d. Stainless steel exterior and interior
e. Temperature range of -20 °C to 180 °C with an accuracy of ± 0.5 °C
f. Relative humidity range of 10 % to 95 % with an accuracy of ± 5 %
g. Ability to increase temperature at a rate of 1.5 °C per minute
h. Ability to decrease temperature at a rate of 1.2 °C per minute
i. Solid-state humidity measurement sensor
j. Ability to operate at less than 65 dBA
B. Electrical Specifications
a. Power supply of 115 V, 1 phase, 60 Hz, and 20 A
b. NEMA 5-20 plug
c. Detachable power cord with plug
C. User Interface/Data Acquisition Specifications
a. Touchscreen user interface to program and control temperature and humidity in chamber
b. Ability to program 40 different profiles with up to 50 steps each (e.g., ramp, soak, jump, auto-start, end, etc.)
D. Accessory Specifications
a. TWO (2) wire shelves with a load capacity of 15 lbs. per shelf
b. Purifying, de-ionizing filter for humidity from water source (i.e., municipal water)
III. DELIVERY REQUIREMENTS
Delivery shall be F.O.B Destination and shall occur in accordance with the manufacturer’s or vendor’s standard commercial lead time not to exceed 12 weeks after receipt of an order.
FOB Destination means: The contractor shall pack and mark the shipment in conformance with carrier requirements, deliver the shipment in good order and condition to the point of delivery specified in the purchase order, be responsible for any loss of and/or damage to the goods occurring before receipt and acceptance of the shipment by the consignee at the delivery point specified in the purchase order; and pay all charges to the specified point of delivery.
Delivery shall be made to the NIST Shipping and Receiving address identified below. The delivery will then be directed to the equipment’s final destination, also identified below.
NIST Shipping & Receiving 100 Bureau Drive Building 301 Gaithersburg, MD 20899-0001
NIST Final Equipment Destination:
The National Institute of Standards and Technology 100 Bureau Drive, Building 226, Room B363 Gaithersburg, MD 20899-1640
No installation or training shall be required by the Contractor.
IV. INSPECTION & ACCEPTANCE
In addition to the inspection and acceptance terms articulated in 52.212-4, the Government reserves the right to perform such performance tests and evaluations as defined below to verify specified system performance. Such tests and evaluations, if performed, shall be conducted within the environment that the system is to be operated. The Contractor has the right to be present during the tests and evaluations, if performed, at the Contractor’s expense. Inspection and Acceptance shall take place on the NIST Gaithersburg campus in building 226.
Performance Tests:
1. Ensure that the equipment is operational and has no defects or missing parts.
NIST may choose at its discretion to forego this part of acceptance testing.
A visual inspection of the equipment will be performed by the NIST Subject Matter Expert (SME) to identify surface defects or any form of indication that any equipment was damaged during transport to NIST. The Government shall have sole discretion to require repair or replacement of damaged and/or nonconforming supplies at no cost to the Government. The Government at any time prior to acceptance shall reject the equipment due to defects and/or nonconformance. The vendor is responsible for latent defects discovered any time after final inspection. However, the extent of its liability shall be prorated over the useful life of the equipment.
Ownership of the equipment shall transfer to NIST upon acceptance by the Government.
The Government will test, inspect, and accept or reject the equipment within 10 business days after delivery to ensure that it conforms to the requirements identified in this Requirements document. If all performance testing, as described below, is approved and all other requirements are met and the equipment is operational, the product shall be accepted. of the receipt of the equipment unless otherwise indicated above. The Government reserves the right to conduct quality assurance testing to confirm that a given instrument(s) meets the manufacturer’s and/or the Government’s performance specifications. It is anticipated that the equipment will meet all manufacturer’s specifications and/or the Government’s performance specifications identified in the most recent operations and maintenance manual for each piece of equipment and/or in this document.
V. WARRANTY
The contractor shall warranty the entire system for a period of a minimum of 1 YEAR after receipt of the equipment and shall be in accordance with terms in FAR 52.212-4. Warranty at a minimum shall include the following:
To be free of defects in materials and workmanship for a period of ONE (1) year from the date of the original shipment.
VI. PAYMENT SCHEDULE
Advance payment is not authorized. The Contractor must invoice in arrears according to the payment schedule. The Contractor shall be paid, in accordance with Net 30-day payment terms, upon receipt and acceptance of a proper invoice, in accordance with the following schedule:
1. 100% after installation and acceptance by the SME of fully installed system, AND
2. After the successful completion of the testing requirements set forth in this document under section set forth in this document, AND
3. After successful demonstration by the instrumentation that it performs IAW the technical requirements set forth in this document AND
4. After receiving an invoice submitted properly, IAW the purchase order terms and conditions.
NOTE: Partial shipments and partial invoices will not be accepted, unless otherwise requested and accepted by the Contracting Officer prior to award offer. Proposed payment schedules shall be submitted with vendor’s response to the RFQ for consideration.