Section C - Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Redwood Sciences Laboratory Boiler Replacement, newest first.
File Type Posted
Amendment__2,_AG-9AD6-S-17-0002.pdf PDF
Amendment_1,_AG-9AD6-S-17-0002.pdf PDF
Arcata_100_DWG_Revised_binder.pdf PDF
SECTION_L_-__Arcata_Boiler_Replacement.docx DOCX document
SECTION_M_-__Arcata_Boiler_Replacement.docx DOCX document
SECTION_E._Arcata_Boiler_Replacement.docx DOCX document
SECTION_G._Arcata_Boiler_Replacement.docx DOCX document
Section_B_-_Schedule_of_Items,_Arcata_Boiler_Project.docx DOCX document
Section_J_-_Index_for_Arcata_Boiler_Project.docx DOCX document
PART_IV_Section_K-_Arcata_Boiler_Replacement.docx DOCX document
Section_J-1,_Arcata_Boiler_Project,_Davis_Bacon_Wages.pdf PDF
Part_II_Section_I._Arcata_Boiler_Project.docx DOCX document
Section_J-2,_Arcata_Boiler_Project_-_Drawings.pdf PDF
SECTION_F._Arcata_Boiler_Peplacement.docx DOCX document
Arcata_SF_1442.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture

Forest Service

Pacific Southwest Research Station

November 2016

Redwood Sciences Laboratory

Boiler Replacement Contract Documents

AUSD

BOILER REPLACMENT 001500 – 1

REDWOOD SCIENCES LABORATORY LIST OF DRAWINGS AND

SPECIFICTIONS

SECTION 001500

REDWOOD SCIENCES LABORATORY

BOILER REPLACEMENT

LIST OF DRAWINGS AND SPECIFICATIONS

PART 1 – GENERAL

1.1 DESCRIPTION

A. List of Contract Drawings:

1. Index of Sheets:

T1.0 Title Sheet M0.1 Photographs

M0.1A Revised Boiler Plan, Schematics, and Heating Hot Water Piping Diagram

M0.2 Schedules M2.1A First Floor Plan - North M2.1B First Floor Plan - South M2.2A Second Floor Plan - North M2.2B Second Floor Plan - South M4.1 Enlarged Floor Plans and Diagrams M5.1 Enlarged Floor Plans and Diagrams M6.1 Details

11 Total Plan Sheets in this Contract

B. List of Contract Specifications

1. Index of Specifications

DIVISION 1 - GENERAL REQUIREMENTS

Section 001500 List of Drawings and Specifications Section 010150 General Requirements

DIVISION 23 - MECHANICAL

Section 230500 Common Work Results for HVAC Section 230523 General-Duty Valves for HVAC Piping Section 230548 Vibration and Seismic Controls for HVAC Piping and

Equipment Section 230593 Testing, Adjusting, and Balancing for HVAC Section 230700 HVAC Insulation Section 232113 Hydronic Piping Section 23212 Natural-Gas Piping Section 232123 Hydronic Pumps

BOILER REPLACMENT 001500 – 2

REDWOOD SCIENCES LABORATORY LIST OF DRAWINGS AND

SPECIFICTIONS

Section 235200 Boilers

DIVISION 26 - ELECTRICAL

Section 260500 Electrical Material and Methods

BOILER REPLACEMENT 010150 – 1

REDWOOD SCIENCES LABORATORY GENERAL REQUIREMENTS

SECTION 010150

GENERAL REQUIREMENTS

PART 1 – SUMMARY OF WORK

1.1 DESCRIPTION

A. Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, miscellaneous items, freight and delivery and all necessary valid licenses and permits to remove and replace the heating hot water boiler; install an additional heating hot water boiler; modify the heating water piping system associated with the boilers; remove and replace heating hot water system pumps and associated piping and valves; and test, clean, and treat the existing hydronic heating water system.

B. This project is located at the Redwood Research Station located on the Humboldt State University campus in Arcata, California.

1.2 USE OF PREMISES

A. Use of Site: Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Full Government Occupancy: Government will occupy site and buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations.

C. Driveways and Entrances: Keep driveways, parking areas, loading areas and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

1.3 PROJECT SCHEDULING

A. Schedule work to minimize impacts to government and students.

1.4 WORK RESTRICTIONS

A. Nonsmoking Buildings: Smoking is not permitted within the buildings or within 25 feet (8 m) of entrances, operable windows, or outdoor air intakes.

BOILER REPLACEMENT 010150 – 2

1.5 CONTRACTOR’S RESPONSIBILITIES

A. Confine storage of materials to areas as approved by the CO.

B. Provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas.

1.6 FIELD VERIFICATION

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

1.7 PERMITS

A. State Electrical Inspection is required for this project. Obtain permits for electrical work if the State Electrical Inspector requires a permit to do the inspection.

B. Obtain permits for work required by County, State, or Federal laws or regulations.

PART 2 – DEFINITION OF ITEMS AND PAYMENT

2.1 DESCRIPTION

A. This section explains what is and what is not included in each pay item; the limits or cut-off points where one item ends and another begins; and basis of payment for work items listed in the Schedule of Items.

B. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, and as shown on the drawings.

2.2 SCHEDULE OF ITEMS

A. Schedule of Items: The project Schedule of Items includes several sections to organize the work into Base Items and Optional Items.

1. Provide pricing for all items listed in the Schedule of Items.

2. Contract award will be made for all Base Items.

3. Optional Items will be awarded based on available project funding.

B. Base Items (BI):

1. Base Item No. 1- Boiler Replacement

a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to remove and replace the heating hot water boiler with a smaller boiler; remove and replace

BOILER REPLACEMENT 010150 – 3

associated boiler pump, piping and valves; install an additional heating hot water boiler, boiler pump, piping, valves, and flue; make modifications and connection to the natural gas piping system, hydronic piping system, electrical system, and control system; and test and balance new equipment.

2. Base Item No. 2 – Hydronic System Cleaning and Treatment

a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to clean and treat the entire hydronic heating system.

C. Optional Items (OI):

1. Optional Item No. 1 – Pump Replacement

a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, demolition, labor and incidentals to remove and replace two heating water pumps; make modifications to hydronic piping and valves associated with the water pumps; make modifications associated with the pump electrical and control systems; and test and balance the new pumps.

PART 3 – ACCIDENT PREVENTION

3.1 DESCRIPTION

A. This section consists of establishing an effective accident prevention plan and providing a safe environment for personnel and visitors.

3.2 SUBMITTALS

A. Accident Prevention Plan: Before on-site work begins, submit a company approved accident prevention plan. This plan will be posted in the contract file. Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project. Notice to proceed will not be made until the plan is received. As a minimum the plan shall include:

1. Name, position title and contact information of company executive responsible for approving the Accident Prevention Plan.

2. Name and contact information of supervisor responsible to carry out the plan.

3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.

4. Contingency plans for emergency situations such as medical, fire, hazard material spills and other contract assessed hazard prevention and abatement requirement needs that apply to this project.

BOILER REPLACEMENT 010150 – 4

B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.

C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.

D. Submit a brief report of safety meetings and of inspections.

E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.

3.3 QUALITY ASSURANCE

A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions: In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

B. Qualifications of Employees: Ensure employees are physically qualified to perform assigned duties in a safe manner.

3.4 ACCIDENT REPORTING

A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 calendar days of a reportable accident, fill out and forward to the CO a CA-1 form, which may be obtained from CO.

B. All Other Accidents: Report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.

3.5 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the type of construction at the site.

3.6 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.

3.7 EMERGENCY INSTRUCTIONS

A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

3.8 PROTECTIVE EQUIPMENT

BOILER REPLACEMENT 010150 – 5

A. Inspect personal protective equipment daily and maintain in a serviceable condition.

Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.9 SAFETY MEETINGS

A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.

3.10 HARD HATS AND PROTECTIVE EQUIPMENT AREAS

A. The CO will designate a hard hat area. Post the hard hat area in a manner satisfactory to the CO.

B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide two hard hats for use by visitors. Change liners before reissuing hats.

3.11 TRAINING

A. First Aid: Provide adequate training to ensure prompt and efficient first aid.

B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

PART 4 – SUBMITTAL PROCEDURES

4.1 DESCRIPTION

A. This section includes administrative and procedural requirements for submittals.

4.2 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Contracting Officer’s (CO's) responsive action.

B. Informational Submittals: Written information that does not require CO's approval.

Submittals may be rejected for not complying with requirements.

4.3 PROCEDURES

BOILER REPLACEMENT 010150 – 6

A. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 10 working days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 10 working days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

B. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space approximately 2 by 3 inches on label or beside title block to record

Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. Other necessary identification.

C. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

D. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

E. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

F. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

G. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

BOILER REPLACEMENT 010150 – 7

H. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

I. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

4.4 ACTION SUBMITTALS

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit four copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

4.5 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

B. Contractor's Construction Schedule: Provide a construction schedule.

C. Cost Breakdown: Following award provide a cost breakdown schedule listing main types of work with associated costs for each bid item.

BOILER REPLACEMENT 010150 – 8

PART 5 – TEMPORARY FACILITIES AND CONTROLS

5.1 DESCRIPTION

A. This section consists of requirements for temporary facilities and controls, including utilities, support facilities, and security and protection facilities.

5.2 UTILITIES

A. Water Service: Use of Government existing water service facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in a condition acceptable to CO. At Substantial Completion, restore these facilities to condition existing before initial use.

B. Sanitary Facilities: Use of Government sanitary facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to CO. At Substantial Completion, restore these facilities to condition existing before initial use.

C. Electric Power and Lighting Service: Use of Government's existing electric power and lighting service will be permitted without metering and without payment of use charges, as long as equipment is maintained in a condition acceptable to CO.

D. Telephone Service: The Contractor is responsible for providing telephone service deemed necessary for the duration of the construction.

5.3 STORAGE AREAS

A. Coordinate on-site storage requirements with the Contracting Officer.

5.4 CONSTRUCTION WASTE DISPOSAL FACILITIES

A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste.

5.5 SUPPORT FACILITIES INSTALLATION

A. Locate temporary construction and support facilities for easy access.

5.6 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects. Restrict use of noisemaking tools and equipment to hours that will minimize complaints from persons or firms near Project site.

BOILER REPLACEMENT 010150 – 9

B. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erecting structurally adequate barricades. Paint with appropriate colors, graphics, and warning signs to inform personnel and public of possible hazard. Where appropriate and needed, provide lighting, including flashing red or amber lights.

C. Fire Protection:

1. Store combustible materials in containers in fire-safe locations.

2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.

3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.

PART 6 – EXECUTION REQUIREMENTS

6.1 DESCRIPTION

A. This section consists of general procedural requirements governing execution of the Work including, but not limited to, the following:

1. General installation of products.

2. Progress cleaning.

3. Protection of installed construction.

4. Correction of the Work.

6.2 EXAMINATION

A. Existing Conditions: Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work.

B. Acceptance of Conditions: Examine areas, and conditions, with Installer. Record observations.

1. Examine roughing-in for electrical systems to verify actual locations of connections before equipment and fixture installation.

2. Proceed with installation only after unsatisfactory conditions have been corrected.

Proceeding with the Work indicates acceptance of surfaces and conditions.

6.3 PREPARATION

A. Field Measurements: Take field measurements as required to fit the Work properly.

B. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO.

Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

BOILER REPLACEMENT 010150 – 10

6.4 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

B. Comply with manufacturer's written instructions and recommendations for installing products.

C. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

6.5 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

B. Site: Maintain Project site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

D. Waste Disposal: Burying or burning waste materials on-site will not be permitted.

Washing waste materials down sewers or into waterways will not be permitted.

6.6 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

6.7 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

BOILER REPLACEMENT 010150 – 11

PART 7 – OPERATIONS AND MAINTENANCE MANUALS

7.1 DESCRIPTION

A. This Section consists of administrative and procedural requirements for operation and maintenance manuals.

7.2 SUBMITTALS

A. Submit two manuals in final form at least 15 working days before final inspection.

7.3 OPERATION AND MAINTENANCE MANUALS

A. Assemble a complete set of operation and maintenance data indicating the operation and maintenance of each system, subsystem, and piece of equipment not part of a system.

Include operation and maintenance data required in individual Specification Sections and as follows:

1. Operation Data: Include emergency instructions and procedures, system and equipment descriptions, operating procedures, and sequence of operations.

2. Maintenance Data: Include manufacturer's information, list of spare parts, maintenance procedures, maintenance and service schedules for preventive and routine maintenance, and copies of warranties and bonds.

B. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain a title page, table of contents, and manual contents.

C. Title Page: Enclose title page in transparent plastic sleeve. Include the following information:

1. Subject matter included in manual.

2. Name and address of Project.

3. Name and address of Job Corps.

4. Date of submittal.

5. Name, address, and telephone number of Contractor.

6. Cross-reference to related systems in other operation and maintenance manuals.

D. Table of Contents: List each product included in manual, identified by product name, indexed to content of volume, and cross-referenced to Specification Section.

E. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.

1. Binders: Heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with

BOILER REPLACEMENT 010150 – 12

clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.

a. Identify each binder on front and spine, with printed title "OPERATION

AND MAINTENANCE MANUAL," Project title or name, and subject matter of contents. Indicate volume number for multiple-volume sets.

2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section. Mark each tab to indicate contents. Include typed list of products and major components of equipment included in the section on each divider, cross-referenced to Specification Section number and title of Project Manual.

3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic software diskettes for computerized electronic equipment.

4. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.

a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts.

b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten pages indicating drawing titles, descriptions of contents, and drawing locations.

F. Content: Include operation and maintenance data required in individual Specification Sections and equipment descriptions, operating standards, operating procedures, operating logs, wiring and control diagrams, and license requirements.

G. Descriptions: Include the following:

1. Product name and model number.

2. Manufacturer's name.

3. Equipment identification with serial number of each component.

4. Equipment function.

5. Operating characteristics.

6. Performance curves.

7. Engineering data and tests.

8. Complete nomenclature and number of replacement parts.

H. Source Information: For each product, list name, address, and telephone number of Installer or supplier.

I. Operating Procedures: Include startup, break-in, and control procedures; stopping and normal shutdown instructions; routine, normal, seasonal, and weekend operating instructions; and required sequences for electric or electronic systems.

J. Systems and Equipment Controls: Describe sequence of operation, and diagram controls as installed.

BOILER REPLACEMENT 010150 – 13

K. Maintenance Procedures: For each system, subsystem, and piece of equipment not part of a system, include manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, drawings and diagrams for maintenance, nomenclature of parts and components, and recommended spare parts for each component part or piece of equipment.

L. Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment.

M. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.

1. Provide heavy paper dividers with plastic-covered tabs for each separate warranty.

Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

PART 8 – CLOSEOUT PROCEDURES

8.1 DESCRIPTION

A. This section consists of administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Inspection procedures.

2. Project Record Documents.

3. Final cleaning.

8.2 SUBSTANTIAL COMPLETION

A. Definition of Substantial Completion: The Date certified by the Contracting Officer when construction is sufficiently complete, in accordance with the Contract Documents, so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.

B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise Contracting Officer (CO) of pending insurance changeover requirements.

3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.

BOILER REPLACEMENT 010150 – 14

4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.

5. Prepare and submit Project Record Documents, operation and maintenance manuals, Final Completion construction photographs and photographic negatives, and similar final record information.

6. Complete startup testing of systems.

7. Complete final cleaning requirements, including touchup painting.

8. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final Completion.

8.3 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.

B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

8.4 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

BOILER REPLACEMENT 010150 – 15

A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

8.5 PROJECT RECORD DOCUMENTS

A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.

B. Record Drawings: Maintain and submit one set of blue- or black-line white prints of Contract Drawings and Shop Drawings.

1. Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.

a. Give particular attention to information on concealed elements that cannot be readily identified and recorded later.

b. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

2. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.

3. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable.

4. Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. Organize into manageable sets;

bind each set with durable paper cover sheets. Include identification on cover sheets.

8.6 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

BOILER REPLACEMENT 010150 – 16

1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

2. Remove tools, construction equipment, machinery, and surplus material from Project site.

3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.

Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

D. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.

END OF SECTION 010150

BOILER REPLACEMENT 230500 - 1

REDWOOD SCIENCES LABORATORY COMMON WORK RESULTS FOR HVAC

SECTION 230500

COMMON WORK RESULTS FOR HVAC

PART 1 – GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Piping materials and installation instructions common to most piping systems.

2. Identification.

3. HVAC demolition.

4. Equipment installation.

1.2 SUBMITTALS

A. As specified in Division 1 Section, “Submittal Procedures.”

1. Submit manufacturer's literature for each type of identification products speci-fied.

2. Welding Certificates.

1.3 CLOSEOUT SUBMITTALS

A. As specified in Division 1 Section “Closeout Procedures.”

1. Furnish valve schedule for each piping system, type written on 8-1/2-inch x 11-inch bond paper. In tabular format include valve identification number, piping system, location of valve (room name and number), function, and normal posi-tion.

1.4 QUALITY ASSURANCE

A. Electrical Characteristics for HVAC Equipment: Equipment of higher electrical char-acteristics may be furnished provided such proposed equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes are appropriately modified. If minimum energy ratings or efficiencies are specified, equipment shall comply with requirements.

B. Steel Support Welding: Qualify processes and operators according to AWS D1.1, "Structural Welding Code--Steel."

C. Steel Pipe Welding: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications."

D. Comply with provisions in ASME B31 Series, "Code for Pressure Piping."

BOILER REPLACEMENT 230500 - 2

E. Certify that each welder has passed AWS qualification tests for welding processes in-volved and that certification is current.

PART 2 – PRODUCTS

2.1 IDENTIFICATION

A. Valve tags: Engraved anodized aluminum or engraved plastic tag.

1. Size: 2-inch diameter.

2. Fasteners: Metal chain.

B. Pipe Labels: General Requirements for Manufactured Pipe Labels: Preprinted, color-coded, with lettering indicating service, and showing flow direction.

1. Pretensioned Pipe Labels: Precoiled, semirigid plastic formed to cover full cir-cumference of pipe and to attach to pipe without fasteners or adhesive.

2. Self-Adhesive Pipe Labels: Printed plastic with contact-type, permanent-adhesive backing.

3. Pipe Label Contents: Include identification of piping service using same desig-nations or abbreviations as used on Drawings, pipe size, and an arrow indicating flow direction.

a. Flow-Direction Arrows: Integral with piping system service lettering to accommodate both directions, or as separate unit on each pipe label to in-dicate flow direction.

b. Lettering Size: At least 1-1/2 inches (38 mm) high.

PART 3 – EXECUTION

3.1 HVAC DEMOLITION

A. Disconnect, demolish, and remove HVAC systems, equipment, piping, and compo-nents indicated to be removed.

1. Piping to Be Removed: Remove portion of piping or ducts indicated to be re-moved and cap remaining piping or duct with same or compatible material.

2. Equipment to Be Removed: Disconnect and cap services. Remove equipment.

3. Equipment to Be Removed and Reinstalled: Disconnect and cap services. Re-move, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

B. If piping insulation, or equipment to remain is damaged in appearance or is unservice-able, remove damaged or unserviceable portions and replace with new products of equal capacity and quality.

BOILER REPLACEMENT 230500 - 3

C. Repair adjacent construction and finishes damaged during demolition and extension work.

D. Extend existing installations using materials and methods as specified.

E. Removed piping equipment, etc. become the property of the Contractor unless otherwise noted.

F. Remove, relocate, and extend existing installations to accommodate new construction.

3.2 PIPING SYSTEMS - COMMON REQUIREMENTS

A. Install piping according to the following requirements and Division 23 Sections speci-fying piping systems.

B. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems. Indicated locations and arrangements were used to size pipe and cal-culate friction loss, expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on Coordination Draw-ings.

C. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless spe-cifically indicated otherwise.

D. Install piping to permit valve servicing.

E. Install piping at indicated slopes.

F. Install piping free of sags and bends.

G. Install fittings for changes in direction and branch connections.

H. Install piping to allow application of insulation.

I. Select system components with pressure rating equal to or greater than system operat-ing pressure.

3.3 PIPING JOINT CONSTRUCTION

A. Join pipe and fittings according to the following requirements and Division 23 Sec-tions specifying piping systems.

B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.

C. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

BOILER REPLACEMENT 230500 - 4

D. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise indicat-ed, to tube end. Construct joints according to ASTM B 828 or CDA's "Copper Tube Handbook," using lead-free solder alloy complying with ASTM B 32.

E. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1.

Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:

1. Apply appropriate tape or thread compound to external pipe threads unless dry seal threading is specified.

2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corrod-ed or damaged. Do not use pipe sections that have cracked or open welds.

F. Welded Joints: Construct joints according to AWS D10.12, using qualified processes and welding operators according to Part 1 "Quality Assurance" Article.

G. Flanged Joints: Select appropriate gasket material, size, type, and thickness for ser-vice application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.

3.4 PIPING CONNECTIONS

A. Make connections according to the following, unless otherwise indicated:

1. Install unions, in piping NPS 2 and smaller, adjacent to each valve and at final connection to each piece of equipment.

2. Wet Piping Systems: Install dielectric coupling and nipple fittings to connect piping materials of dissimilar metals.

3.5 IDENTIFICATION

A. Clean piping surfaces of substances that could impair bond of identification devices, including dirt, oil, grease, release agents, and incompatible primers, paints, and encap-sulants.

B. Valve Label Installation: Label valves, cocks, and control devices in new piping sys-tems. Exclude check valves and valves within factory fabricated equipment. List each tagged valve in valve schedule.

C. Pipe Label Installation: Install pipe labels on new piping. Locate pipe labels in equipment rooms as follows:

1. Near each valve and control device.

2. Near each branch connection, excluding short takeoffs for fixtures and terminal units. Where flow pattern is not obvious, mark each pipe at branch.

3. Near penetrations through walls, floors, ceilings, and inaccessible enclosures.

4. At access doors and similar access points that permit view of concealed piping.

5. Near major equipment items and other points of origination and termination.

BOILER REPLACEMENT 230500 - 5

6. Spaced at maximum intervals of 50 feet along each run.

7. Pipe Label Color Schedule:

a. Heating Water Piping:

1) Background Color: Green.

2) Letter Color: White.

b. Natural Gas:

1) Background Color: Yellow.

2) Letter Color Black.

3.6 EQUIPMENT INSTALLATION - COMMON REQUIREMENTS

A. Install equipment to allow maximum possible headroom unless specific mounting heights are not indicated.

B. Install equipment level and plumb, parallel and perpendicular to other building sys-tems and components in exposed interior spaces, unless otherwise indicated.

C. Install HVAC equipment to facilitate service, maintenance, and repair or replacement of components. Connect equipment for ease of disconnecting, with minimum interfer-ence to other installations.

D. Install equipment to allow right of way for piping installed at required slope.

END OF SECTION 230500

BOILER REPLACEMENT 230500 - 6

This page intentionally left blank.

BOILER REPLACEMENT 230523 - 1

REDWOODS SCIENCES LABORATORY GENERAL-DUTY VALVES FOR

HVAC PIPING

SECTION 230523

GENERAL-DUTY VALVES FOR HVAC PIPING

PART 1 – GENERAL

1.1 SUMMARY

A. This Section includes general-duty valves for modifications to the heating water sys-tem to replace the boiler and hydronic pumps.

1.2 SUBMITTALS

A. As specified in Division 1 Section, “Submittal Procedures.”

1. Submit manufacturer's literature for each type of valve.

1.3 CLOSEOUT SUBMITTALS

A. As specified in Division 1 Section “Closeout Procedures.”

1. Operation and Maintenance Data: Furnish for each type of valve.

PART 2 – PRODUCTS

2.1 VALVE END CONNECTIONS

A. Valve-End Connections:

1. Solder Joint: Sockets according to ASME B16.18.

2. Threaded: Threads according to ASME B1.20.1.

3. Flanged: With flanges according to ASME B16.1 for iron valves.

2.2 BRONZE BALL VALVES

A. Manufacturers: Subject to compliance with requirements, available manufacturers of-fering products that may be incorporated into the Work include, but are not limited to, the following:

1. American Valve, Inc.

2. Hammond Valve.

3. Milwaukee Valve Company.

4. NIBCO INC.

B. Two-Piece, Bronze Ball Valves with Bronze Trim:

1. Standard: MSS SP-110.

BOILER REPLACEMENT 230523 - 2

HVAC PIPING

2. SWP Rating: 150 psig.

3. CWP Rating: 600 psig.

4. Body Design: Two piece.

5. Body Material: Bronze.

6. Ends: Threaded.

7. Seats: PTFE or TFE.

8. Stem: Bronze.

9. Ball: Chrome-plated brass.

10. Port: Regular or full port depending on service.

2.3 BRONZE SWING CHECK VALVES

A. Manufacturers: Subject to compliance with requirements, available manufacturers of-fering products that may be incorporated into the Work include, but are not limited to, the following:

1. Conbraco Industries, Inc.; Apollo Valves.

2. Crane Co.; Crane Valve Group; Jenkins Valves.

3. Crane Co.; Crane Valve Group; Stockham Division.

4. Hammond Valve.

5. Milwaukee Valve Company.

6. NIBCO INC.

B. Class 125, Bronze Swing Check Valves with Bronze Disc:

1. Description:

a. Standard: MSS SP-80, Type 3.

b. CWP Rating: 200 psig (1380 kPa).

c. Body Design: Horizontal flow.

d. Body Material: ASTM B 62, bronze.

e. Ends: Threaded.

f. Disc: Bronze.

2.4 IRON, SINGLE-FLANGE BUTTERFLY VALVES

A. 150 CWP, Iron, Single-Flange Butterfly Valves with EPDM Seat and Aluminum- Bronze Disc:

B. Manufacturers: Subject to compliance with requirements, available manufacturers of-fering products that may be incorporated into the Work include, but are not limited to, the following:

1. Conbraco Industries, Inc.; Apollo Valves.

2. Crane Co.; Crane Valve Group; Jenkins Valves.

3. Crane Co.; Crane Valve Group; Stockham Division.

BOILER REPLACEMENT 230523 - 3

HVAC PIPING

4. Hammond Valve.

5. Milwaukee Valve Company.

6. NIBCO INC.

C. Description:

1. Standard: MSS SP-67, Type I.

2. CWP Rating: 150 psig.

3. Body Design: Lug type; suitable for bidirectional dead-end service at rated pressure without use of downstream flange.

4. Body Material: ASTM A 126, cast iron or ASTM A 536, ductile iron.

5. Seat: EPDM.

6. Stem: One- or two-piece stainless steel.

7. Disc: Aluminum bronze.

PART 3 – EXECUTION

3.1 VALVE INSTALLATION

A. Install valves with unions or flanges at each piece of equipment arranged to allow ser-vice, maintenance, and equipment removal without system shutdown.

B. Locate valves for easy access and provide separate support where necessary.

C. Install valves in horizontal piping with stem at or above center of pipe.

D. Install valves in position to allow full stem movement.

E. Install swing check valves for proper direction of flow and in horizontal position with hinge pin level.

3.2 ADJUSTING

A. Adjust or replace valve packing after piping systems have been tested and put into service but before final adjusting and balancing. Replace valves if persistent leaking occurs.

3.3 GENERAL REQUIREMENTS FOR VALVES

A. Valve Pressure and Temperature Ratings: Not less than indicated and as required for system pressures and temperatures.

B. Valve Sizes: Same as upstream piping unless otherwise indicated.

C. Valves in Insulated Piping: Provide with 2-inch stem extensions and the following features:

BOILER REPLACEMENT 230523 - 4

HVAC PIPING

1. Ball Valves: With extended operating handle of non-thermal-conductive mate-rial, and protective sleeve that allows operation of valve without breaking the vapor seal or disturbing insulation.

D. If valve applications are not indicated, use the following:

1. Shutoff Service: Ball valves.

2. Throttling Service: Ball or butterfly valves.

3. Pump-Discharge Check Valves: Bronze swing check valves.

E. If valves with specified SWP classes or CWP ratings are not available, the same types of valves with higher SWP classes or CWP ratings may be substituted.

F. Select valves, except wafer types, with the following end connections:

1. For Copper Tubing, NPS 2 (DN 50) and Smaller: Threaded ends except where solder-joint valve-end option is indicated in valve schedules below.

2. For Copper Tubing, NPS 2-1/2 to NPS 4 (DN 65 to DN 100): Flanged ends ex-cept where threaded valve-end option is indicated in valve schedules below.

3. For Steel Piping, NPS 2 (DN 50) and Smaller: Threaded ends.

3.4 VALVE SCHEDULE

A. Copper Pipe NPS 2-1/2 and Smaller:

1. Provide bronze ball valves with solder-joint or threaded ends.

B. Iron Pipe NPS 2-1/2 and Larger:

1. Provide iron, single-flange butterfly valves with threaded or flanged ends.

END OF SECTION 230523

BOILER REPLACEMENT 230548 - 1

REDWOOD SCIENCES LABORATORY VIBRATION AND SEISMIC CONTROLS FOR

HVAC PIPING AND EQUIPMENT

SECTION 230548

VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT

PART 1 – GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Elastomeric hangers.

2. Restraining braces and cables.

1.2 PERFORMANCE REQUIREMENTS

A. Seismic-Restraint Loading:

1. Site Class as Defined in IBC: D.

2. Assigned Seismic Use Group or Building Category as Defined in the IBC: D.

a. Component Importance Factor:

1) Boilers: 1.0.

2) Piping Distribution System: 2.5.

b. Component Response Modification Factor:

1) Boilers: 2.5.

2) Piping Distribution System: 6.

3. Design Spectral Response Acceleration at Short Periods (0.2 Second): 1.0

4. Design Spectral Response Acceleration at 1-Second Period: 1.5.

1.3 SUBMITTALS

A. As specified in Division 1 Section, “Submittal Procedures.”

1. Product Data: Include data for each specified item.

1.4 CLOSEOUT SUBMITTALS

A. Closeout Submittals: As specified in Division 1 Section, “Closeout Procedures.”

1. Field quality test reports.

1.5 QUALITY ASSURANCE

BOILER REPLACEMENT 230548 - 2

HVAC PIPING AND EQUIPMENT

A. Comply with seismic-restraint requirements in the IBC unless requirements in this Section are more stringent.

PART 2 – PRODUCTS

2.1 VIBRATION ISOLATORS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers of-fering products that may be incorporated into the Work include, but are not limited to, the following:

1. Ace Mountings Co., Inc.

2. Mason Industries.

3. Vibration Mountings & Controls, Inc.

B. Elastomeric Hangers: Single or double deflection type, fitted with molded, oil-resistant elastomeric isolator elements bonded to steel housings with threaded connec-tions for hanger rods. Color-code or otherwise identify to indicate capacity range.

2.2 SEISMIC-RESTRAINT DEVICES

A. Available Manufacturers: Subject to compliance with requirements, manufacturers of-fering products that may be incorporated into the Work include, but are not limited…