Questions_and_Answers_8-17.pdf
PDF 73 KB Posted
- Attached to
- Seiad Decommissioning, Phase I Federal contract opportunity
- Solicitation number
- AG-9AC7-S-16-0147
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1._Updated-SPECIAL_PROJECT_SPECS.pdf | ||
| 2._PLANS-SEIAD-DECOM-PHASE-1-2016.pdf | ||
| 3._PAL_Fire_Plan_030613.pdf | ||
| AG-9AC7-S-16-0147_Solicitation.pdf | ||
| 4._CA9._mod_8 _dated_07292016.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Seiad Decommissioning AG-9AC7-S-16-0147
Questions and Answers
As of 8/17/2016
1. The project calls for approximately 710 class 3 rip rap. The rock sources all seem to deal in river rock.
Will it be okay to use river rock for the rip rap?
In reading through Section 705.02 (Riprap Rock) of FP-03, it states that the rock shall be “hard, durable, angular rock….”
The idea being that angular rock will lock into place better than rounded rock. That being said, river rock might be suitable if it has some broken edges, and is still angular in nature.
2. Are there any quarry sources nearby or do you have any information on potential commercial suppliers nearby?
Hayes Construction on Indian Creek out of Happy Camp
Eddy Conners has a pit out of Horse Creek