Amend1_AG-9AC7-S-16-0086.pdf
PDF 453 KB Posted
- Attached to
- Canyon Tree Planting Federal contract opportunity
- Solicitation number
- AG-9AC7-S-16-0086
About this file
Amendment 1 - Change in Schedule of Items
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 77-0727.txt | TXT text file | |
| Appendix_B_Canyon_Research_Plot_Planting_Diagram.pdf | ||
| Appendix_A_Canyon_Planting_2016_Maps.pdf | ||
| AG-9AC7-S-16-0086_Solicitation.pdf | ||
| Appendix_D_Fire_Plan.pdf | ||
| Appendix_E_Field_Medical_Evac_Plan.pdf | ||
| Appendix_C_Slope_Correction_FactorTable.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
AG-9AC7-S-16-0086
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
9AC7
REDDING CA 96002
3644 AVTECH PARKWAY SUITE 180
R5 NO-CAL ACQ SERVICE AREA NCASA
USDA FOREST SERVICE
04/11/2016000001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/11/2016
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Canyon Tree Planting
Lassen National Forest
The purpose of this amendment is to correct errors in quantities on the Schedule of Items.
Remove and Replace the Schedule of Items (page 6) with the new document. The corrections are on items 3 and 4. No other changes are made to the terms, conditions or specifications.
The due date for receipt of quotes remains the same.
Period of Performance: 04/21/2016 to 06/30/2016
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
MARILYN LADD
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
4/13/2016
AG-9AC7-S-16-0086 Canyon Tree Planting, Lassen NF
Amendment 1 Page 6
SERVICES & PRICES SCHEDULE OF
ITEMS
CANYON TREE PLANTING
LASSEN NATIONAL FOREST
Almanor Ranger District
Item # Description Pay Unit Est. Qty Unit Price
Total Price
Tree Planting: Canyon Project 2016 – Canyon Dam Area – Full Plant
Acre 33
Tree Planting: Canyon Project 2016 – Storrie Fire Area – Full Plant
Acre 67
Tree Planting: Canyon Project 2016 – Storrie Fire Area – Interplant
Acre 65 $_________ $__________
Tree Planting: Canyon Project 2016 – Storrie Fire Area –Research Plots - Interplant
Acre
TOTAL
File details come from the government source that posted it. Updated .