Road Logs General Notes

View the file

Other files for this federal contract opportunity

Other files attached to Sims Culvert Replacement Project, newest first.
File Type Posted
Amendment_002_Signed.pdf PDF
AG-9AC7-S-16-0044_Amend_001.pdf PDF
SF_24_BID_BOND.pdf PDF
A5_CA9 _mod_5_Dated_030416.pdf PDF
A3_Sims_Drawings.pdf PDF
A1_Supplimental_Specs.pdf PDF
AG-9AC7-S-16-0044_Solicitation.pdf PDF
A4_Sims_PAL_Fire_Plan_030613.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sims Culvert Replacement Project

Road Logs

AG-9AC7-S-16-0044

Forest Road 6N20

MP 0.44 Remove 18” CMP and replace with 24” CMP, 50 feet long.

MP 0.58 Remove 24” CMP and replace with 36” CMP, 65 feet long.

MP 0.75 Remove 18” CMP and replace with 24” CMP, 50 feet long.

MP 1.49 Remove 18” CMP and replace with 24” CMP, 60 feet long.

MP 1.55 Remove 18: CMP and replace with 24” CMP, 50 feet long.

MP 2.10 Remove 18” CMP and replace with 24” CMP, 55 feet long.

MP 3.14 Remove 18” CMP and replace with 24” CMP, 55 feet long.

Forest Road 5N20

MP 0.26 Remove 24” CMP and replace with 30” CMP, 30 feet long.

MP 0.66 Remove 24” CMP and replace with 36” CMP, 40 feet long.

MP 0.73 Remove 18” CMP and replace with 24” CMP, 40 feet long.

MP 0.84 Remove 24” CMP and replace with 24” CMP, 60 feet long.

Forest Road 5N34

MP 1.25 Remove 36” CMP and replace with 48” CMP, 95 feet long.

Forest Road 5N13

MP 0.97 Remove 18” CMP and replace with 24” CMP, 80 feet long.

Sims Culvert Replacement [1] AG-9AC7-S-16-0044

2016 Culvert Replacement Project General Notes & Road Log

General Notes

Information given for specific culverts is approximate and intended only to give the contractor a general idea of the degree of effort required for excavation. Field visits are recommended. Linear dimensions listed are from the edges of the road along the ground slope to the end of the culvert. Fill estimations are approximately the amount of embankment associated with each site, and are not the estimated excavation quantities to replace the pipe.

The Pay Items for culvert installations are divided up into two categories to clarify amount of effort/degree of difficulty in excavation and embankment.

Type 1 excavation: culverts are at a depth 7 feet or less at the outside edge of road, measured straight down into the embankment.

Type 2 excavation: culverts are at a depth between 7 feet and 14 feet at the outside edge of road, measured straight down into the embankment.

Construct a rocked rolling dip at each site. On flat roads, the dip should be placed on top, or nearly on top the new culvert. On sloped roads, the dip should be placed a few feet downslope from the new culvert location.

Place 36 tons of surface aggregate on the road surface over disturbed area of each culvert installation.

Spread government furnished seed evenly on disturbed areas, at approximately 25 pounds per acre, prior to mulching with straw. Use a hand-held spreading machine.

Sites with flowing water need to be dewatered before the old culvert is removed and until the new culvert is installed.

Existing culverts to be replaced are not designated for salvage and shall be disposed of according to 203.05-Disposing of Material, Section a) Remove from project and off government lands.

At least 14 days prior to beginning work, the contractor shall provide an erosion control plan in accordance with Section 157, Erosion Control.

As noted in Specification 602.03-General, the contractor shall measure each culvert and submit the list to the contracting officer prior to ordering pipe.

Sims Culvert Replacement [2] AG-9AC7-S-16-0044

Road Logs

Type 1 Culverts

Road 6N20 - MP 0.44: Replace 18-inch diameter culvert with 24-inch culvert by 50 feet long.

Fill 94 CY Distance from edge road to inlet is 4 feet Distance to outlet from edge of road is 17 feet

Road 6N20 - MP 1.55: Replace 18-inch diameter culvert with 24-inch culvert by 50 feet long.

Fill 279 CY Distance from edge road to inlet is 6 feet Distance to outlet from edge of road is 16 feet

Road 6N20 - MP 2.10: Replace 18-inch diameter culvert with 24-inch culvert 55 feet long.

Fill 173 CY Distance from edge road to inlet is 10 feet Distance to outlet from edge of road is 16 feet

Road 5N20 - MP 0.26: Replace 24-inch diameter culvert with 30-inch culvert 30 feet long. New culvert shall extend to the bottom of the existing scour hole at outlet.

Fill 128 CY Distance from edge road to inlet is 5 feet Distance to outlet from edge of road is 8 feet

Road 5N20 - MP 0.66: Replace 24-inch diameter culvert with 36-inch culvert 40 feet long. New culvert shall extend to the bottom of the existing scour hole at outlet.

Fill 833 CY Distance from edge road to inlet is 6 feet Distance to outlet from edge of road is 18 feet

Road 5N20 – MP 0.73: Replace 18-inch diameter culvert with 24-inch culvert 40 feet long. New culvert shall extend to the bottom of the existing scour hole at outlet.

Fill 209 CY Distance from edge road to inlet is 3 feet Distance to outlet from edge of road is 18 feet

Road 5N20 – MP 0.84: Replace 24-inch diameter culvert with 24-inch culvert 60 feet long. New culvert shall extend to the bottom of the existing scour hole at outlet.

Fill 917 CY Distance from road edge to inlet is 2 feet Distance to outlet from road edge is 16 feet

Sims Culvert Replacement [3] AG-9AC7-S-16-0044

Type 2 Culverts

Road 6N20 - MP 0.58: Replace 24-inch diameter culvert with 36-inch culvert 65 feet long.

Fill 441 CY Distance from edge road to inlet is 17 feet Distance to outlet from edge of road is 17 feet

Road 6N20 - MP 0.75: Replace 18-inch diameter culvert with 24-inch culvert 50 feet long.

Fill 156 CY Distance from edge road to inlet is 7 feet Distance to outlet from edge of road is 16 feet

Road 6N20 – MP 1.49: Replace 18-inch diameter culvert with 24-inch culvert 60 feet long.

Fill 51 CY Distance from edge road to inlet is 5 feet Distance to outlet from edge of road is 30 feet

Road 6N20 - MP 3.14: Replace 18-inch diameter culvert with 24-inch culvert 60 feet long. Existing culvert outlet is buried.

Fill 418 CY Distance from edge road to inlet is 19 feet Distance to outlet from edge of road is 13 feet

Road 5N34 - MP 1.25: Replace 36-inch diameter culvert with 48-inch culvert 95 feet long. New culvert shall extend to the bottom of the existing scour hole at outlet.

Fill 1838 CY Distance from edge road to inlet is 32 feet Distance to outlet from edge of road is 32 feet

Road 5N13 - MP 0.97: Replace 18-inch diameter culvert with 36-inch culvert 80 feet long.

Fill 630 CY Distance from edge road to inlet is 13 feet Distance to outlet from edge of road is 60 feet

Sims Culverts 2016 Road Logs
Culvert Repl Gen Notes