RevisedRoadLog.pdf

PDF 63 KB Posted

Attached to
Green Fire Maintenance Federal contract opportunity
Solicitation number
AG-9AC7-S-16-0039
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

3) Road 13N18 Road Repair Log

View the file

Other files for this federal contract opportunity

Other files attached to Green Fire Maintenance, newest first.
File Type Posted
15-2055_updated_3-16-2016.pdf PDF
SF-30_Amendment_001.pdf PDF
Solicitation_AG-9AC7-S-16-0039.pdf PDF
Updated_PAL_Fire_Plan_complete.pdf PDF
Location_Vicinity_Map.pdf PDF
Road_Structure_Details_801-1.pdf PDF
842_LS.pdf PDF
Standard_Specificationsdoc.pdf PDF
WD_05_2055_(Rev.19)_01_05_2016.pdf PDF
833-2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Road 13N18 Road Repair

General Notes / Road Log

General Notes

Government furnish aggregate is located at the rock pit on Forest Road13N18 at mile post 6. Haul is considered incidental to Spot Surfacing.

Compaction of spot surfacing material shall be method B, roller compaction. Aggregate material shall be at a water content suitable for maximum compaction in accordance with AASHTO T 310. Water hauling is considered incidental.

Disposal sites will be designated on the ground by the Contracting Officers Representative (COR).

Disposal sites will be within 2 miles of slide and sluff removal.

Road Log

13N18 – Donahue Flat Road Repair

MP 1.1: Install Drop Inlet on existing 18” culvert.

MP 2.0: Begin Brushing

MP 6.8: Clean Culvert inlet and remove two trees. There is a tree growing right next to the culvert inlet that needs removing and another that has pulled over plus a root wad about 15 feet up that needs removal. Haul to disposal area.

MP 6.9: Clean culvert inlet.

MP 7.1: 200 CY slide removal, haul to disposal area.

MP 7.4: Remove down tree from culvert inlet area.

MP 7.8: Remove tree from roadway.

MP 8.0: 20 CY of sluff removal.

MP 8.4: 20 CY of sluff removal.

MP 8.7: 100 CY of slide removal.

MP 8.8: 40 CY of slide removal.

MP 9.6: 80 CY of slide removal.

MP 10.0: Road settlement and crack. Grade the road through the settlement area (approximately 300 feet) and roller compact. (This is where the road takes a significant dip over a culvert and then crosses a reinforced fill).

MP 11.6: 40 CY slide removal.

MP 13.7: 30 CY slide removal.

MP 14.0 : End Brushing

Optional Item – Road 13N18

MP 2.0 to 2.3: Spot rock 4 inches depth.