AG-9AC7-S-12-0052.pdf

PDF 284 KB Posted

Attached to
South Fork Sacramento Stormproofing, Phase II Federal contract opportunity
Solicitation number
AG-9AC7-S-12-0052
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

Solicitation AG-9AC7-S-12-0052

View the file

Other files for this federal contract opportunity

Other files attached to South Fork Sacramento Stormproofing, Phase II, newest first.
File Type Posted
Amendment 1.pdf PDF
CA9_Mod 8 080312.pdf PDF
Technical Specifications.pdf PDF
SF 24 Bid Bond.pdf PDF
FIREPLAN and PALI.pdf PDF
SF_PLANS_2012.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

South Fork Sacramento Stormproofing, Phase II Sol: AG-9AC7-S-12-0052 Page 1 of 42

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-9AC7-S-12-0052

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE

ISSUED

08/23/2012

PAGE OF

PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

597053

6. PROJECT NO.

AAP 05NC141255340

7. ISSUED BY CODE 8. ADDRESS OFFER TO

Northern California Acquisition Service Area Redding Office 3644 Avtech Parkway Redding, CA 96002

Same as Block 7

9. FOR INFORMATION

CALL:

A. NAME

Pamela J. Vilhauer

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(530) 226-2454

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

SOUTH FORK SACRAMENTO STORMPROOFING, PHASE II

Shasta-Trinity National Forest, Siskiyou County, California Estimate Price Range is between $100,000 and $250,000.

Set-aside: 100% for HUB zone

Duns:________________________

Tax ID: _______________________

Email: ________________________

NOTE: Questions on this project need to be submitted in writing to pvilhauer@fs.fed.us.

11. The Contractor shall begin performance within 10 calendar days and complete it within 90 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See Section F.)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and _0 copies to perform the work required are due at the place specified in Item 8 by 04:30 pm (hour) local time 09/24/2012 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e) mailto:pvilhauer@fs.fed.us

Sol: AG-9AC7-S-12-0052 Page 2 of 42

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item

14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within 60 calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 9AC7 27. PAYMENT WILL BE MADE BY

Northern California Acquisition Service Area Redding Office

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

PAMELA J. VILHAUER

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

TABLE OF CONTENTS

PART I

SECTION A - SOLICITATION, OFFER, AND AWARD

SECTION B – SCHEDULE OF ITEMS

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

SECTION E – INSPECTION AND ACCEPTANCE

SECTION F – DELIVERIES OR PERFORMANCE

SECTION G - CONTRACT ADMINISTRATION DATA

SECTION H – SPECIAL CONTRACT REQUIREMENTS ………………………………. 14

PART II

SECTION I – CONTRACT CLAUSES

PART III

SECTION J – LIST OF ATTACHMENTS

PART IV

SECTION K – REPRESENTATIONS AND INSTRUCTIONS

SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES

INSTRUCTIONS FOR SUBMISSION OF OFFERS

SECTION M – EVALUATION FACTORS FOR AWARD

Sol: AG-9AC7-S-12-0052 Page 4 of 42

SECTION A - Solicitation/Contract Form

FAR 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 days. The time stated for completion shall include final cleanup of the premises.

Work Timing

Delays due to normal adverse weather, weekends and holidays have been included in the calculation of contract time.

Winter Shutdown

When winter weather sets in and the continuation of work is impractical, the Contracting Officer may authorize a total suspension until such time as work can proceed. During the period of total suspension, the calendar days elapsed will not be charged against the contract time specified.

FAR 52.232-5 Payments under Fixed-Price Construction Contracts. (SEP 2002)

(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.

(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

(1) The Contractor's request for progress payments shall include the following substantiation:

(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.

(ii) A listing of the amount included for work performed by each subcontractor under the contract.

(iii) A listing of the total amount of each subcontract under the contract.

(iv) A listing of the amounts previously paid to each such subcontractor under the contract.

(v) Additional supporting data in a form and detail required by the Contracting Officer.

(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration.

Material delivered to the Contractor at locations other than the site also may be taken into consideration if -

(i) Consideration is specifically authorized by this contract; and

Sol: AG-9AC7-S-12-0052 Page 5 of 42

(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.

(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)

I hereby certify, to the best of my knowledge and belief, that -

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor's performance.

(Name) (Title) (Date)

(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall -

(1) Notify the Contracting Officer of such performance deficiency; and

(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until -

(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or

(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.

(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, Sol: AG-9AC7-S-12-0052 Page 6 of 42 the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as -

(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or

(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.

(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

(h) Final payment. The Government shall pay the amount due the Contractor under this contract after -

(1) Completion and acceptance of all work;

(2) Presentation of a properly executed voucher; and

(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of 1940 (31 U.S.C. 3727 and 41 U.S.C.

15).

(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR Subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(j) Interest computation on unearned amounts. In accordance with 31 U.S.C. 3903(c)(1), the amount payable under subparagraph (d)(2) of this clause shall be -

(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor

Sol: AG-9AC7-S-12-0052 Page 7 of 42 receives the unearned amount; and

(2) Deducted from the next available payment to the Contractor.

52.236-5 Material and Workmanship. (APR 1984) 52.236-7 Permits and Responsibilities. (NOV 1991)

Sol: AG-9AC7-S-12-0052 Page 8 of 42

PART I - THE SCHEDULE

SECTION B - SCHEDULE OF ITEMS

SOUTH FORK SACRAMENTO STORMPROOFING 2012

SHASTA-TRINITY NATIONAL FOREST

SISKIYOU COUNTY, CALIFORNIA

The bidder must bid on all items

Item No. Desc. Unit Qty Unit Price Total

BASE BID

15101 Mobilization Job 1 $ $

15713 Soil Erosion and Pollution Control LS 1 $ $

20419(a) Drainage Excavation, Type, Ditch Cleaning LF 1,087 $ $

20419(b) Drainage Excavation, Type, Slough Removal LF 5,757 $ $

20419© Drainage Excavation, Type, Berm Removal LF 581 $ $

20420(a) Drainage Excavation, Type Rolling Dip, EA 30 $ $

20420(b) Drainage Excavation, Type Rocked Rolling Dip, EA 25 $ $

20420(c) Drainage Excavation, Type Rocked Critical Dip EA 13 $ $

20420(d) Drainage Excavation, Type, Rocked Ford EA 5 $ $

20420(e)

Drainage Excavation, Type, Rocked Vented Ford EA 9 $ $

20420(f) Drainage Excavation, Type, Culvert Cleaning EA 6 $ $

32201

Aggregate Base, Grading D, Compaction Method B. (Spot Rocking) TON 659 $ $

30324 Road Reconditioning, Compaction Method E. LF 1373 $ $

Sol: AG-9AC7-S-12-0052 Page 9 of 42

The bidder must bid on all items

Item No. Desc. Unit Qty Unit Price Total

60250

24-Inch Corrugated Metal Pipe, 0.1345-inch thickness for steel and 0.1019-Inch thickness for aluminum LF 180 $ $

TOTAL OF BASE

CONSTRUCTION

OPTION ITEM: ROAD

40N26 Options will be awarded at time of contract award.

20419(a) Drainage Excavation, Type, Ditch Cleaning LF 6,760 $ $

TOTAL OF OPTION

ITEMS $ $

TOTAL OF ALL ITEMS $ $

B-2 NOTE:

Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 15101 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

NOTE: BID BOND MUST BE IN THE AMOUNT OF 20 PERCENT OF THE TOTAL BID

Sol: AG-9AC7-S-12-0052 Page 10 of 42

SECTION C - DESCRIPTION/SPECIFICATION/WORK STATEMENT

SOUTH FORK SACRAMENTO STORMPROOFING PHASE II

C.1. DESCRIPTION OF WORK

This project involves furnishing all labor, equipment and materials to storm proof 4 roads for a total of

7.2 miles. For this project storm proofing consists of constructing rocked rolling and rocked critical dips, rocked vented fords, rocked fords, cleaning ditches and culverts, removing berms and slough material, spot rocking, road reconditioning and culvert installations. See drawings for more information.

Option Item: Consists of ditch cleaning 1.28 miles of road 40N26.

C.2. PROJECT LOCATION

The project is located south west of the city of Mt. Shasta.

From Redding, CA. take I-5 North to exit 738. Turn left onto Lake Street. Turn left onto Old Stage Road and stay right at the Y onto WA Bar Road. To access the first part of the project site, turn right onto North Shore Road. North Shore Road turns into 40N27 after approximately 3.5 miles. The remainder of the project site can be accessed from Castle Lake Road from WA Bar. Continue on WA Bar Road until it turns into 40N26 road.

C.3. PRE-BID CONFERENCE

A Pre-Bid meeting has not been scheduled. Contact Todd Moxness, project COR, (530) 226-2325 for further information.

C.4. CONTRACT TIME AND ESTIMATED STARTING DATE

Estimated starting date is July 11, 2013, or as soon as weather permits. The contract time will be 90 days.

C.5. PROJECT ACCESS

All roads under this contract may be closed for a maximum delay of eight hours per day during construction. The roads will be required to be made passable for emergency vehicles should the need arise. The Forest Service shall be given a 14 day notice, prior to construction, for public notification.

C.6. TECHNICAL INFORMATION

The Contractor shall furnish a Traffic control plan, Safety Plan and a Spill Plan, along with a detailed plan of operation for approval by the Government prior to starting work. Technical information concerning this project can be obtained from Todd Moxness, Shasta-Trinity National Forest Supervisor’s Office, Redding, CA, telephone (530) 226-2325.

Sol: AG-9AC7-S-12-0052 Page 11 of 42

SECTION D--PACKAGING AND MARKING

For this Solicitation, there are NO clauses in this Section.

SECTION E--INSPECTION AND ACCEPTANCE

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause Number

Title Date

52.246-12 Inspection of Construction AUG 1996

INSPECTIONS

Government inspections are for the purpose of satisfying the Government that the supplies and/or services are acceptable and do not relieve the Contractor of the responsibility for maintaining quality control. The Contractor (or designated representative) is encouraged to be present to observe inspections.

FINAL CLEANUP

Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all Contractor's rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.

http://www.arnet.gov/far/ http://www.usda.gov/procurement/policy/agar.html

Sol: AG-9AC7-S-12-0052 Page 12 of 42

SECTION F--DELIVERIES OR PERFORMANCE

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause Number

Title Date

52.242-14 Suspension of Work APR 1984

AGAR 452.236-75 MAXIIMUM WORKWEEK-CONSTRUCTION (NOV 1996)

Within five calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

The maximum workweek that will be approved is 7 days.

Sol: AG-9AC7-S-12-0052 Page 13 of 42

SECTION G--CONTRACT ADMINISTRATION DATA

DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

The Contracting Officer designates the Contracting Officer's Representative(s) (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)

On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

GOVERNMENT-FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in

NONE

Payment for Materials off Site

In accordance with Clause 52.232-5, progress payments may include payment for materials stored off site. Contractor shall provide a copy of the paid invoice; provide evidence that the material will be included in the finished project; and identify the location where the materials are stored, so that the government may make visual inspection if the Contracting Officer deems it necessary. The Contractor shall be liable for loss, damage, or destruction of the materials until such time as the materials are physically in the possession and control of the government. The Contractor will not be held liable to the extent that the Contracting Officer determines that the loss, damage, or destruction occurred through the fault or negligence of the government or its agents.

Incidental Items

The intent of the contract is to provide for the completion of the project described in the contract.

Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment of items shown.

Sol: AG-9AC7-S-12-0052 Page 14 of 42

SECTION H--SPECIAL CONTRACT REQUIREMENTS

MOISTURE SENSITIVE SOILS

Contractors are cautioned that the roadway structure is designed so that the completed road will support highway legal loads during a limited use season. Construction equipment often subjects the uncompleted roadway structure to loadings it is not designed to support. This is especially critical during periods of excessive moisture. Materials on this project are sensitive to excessive moisture and will require careful selection and scheduling of equipment to permit efficient operation. Any damage resulting from operations, which renders the material unsuitable for use or results in potential siltation of streams, will be corrected by the Contractor at Contractor's expense.

AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held at a mutually agreeable location.

AGAR 452.236-77 EMERGENCY RESPONSE (NOV 1996)

(a) Contractor's Responsibility for Fire Fighting. (1) The Contractor, under the provisions of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work. (2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents or employees.

(b) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor's Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.

EMERGENCIES

Fire Plan

[ X]See Section J, Fire Plan [ ]Not applicable; however, Contractors are required to comply with State law during fire season.

Area of Responsibility for Fire. Unless otherwise noted elsewhere in the contract, the following define the limits of a contractor's area of responsibility for fire under the terms of the Fire Plan (Section J):

[ ] (a) Trail Construction - 100 meters on either side of the centerline [X] (b) Construction of Structures - 100 meters around the perimeter of the project [ ] (c) Road Construction - 400 meters on either side of the centerline [ ] (d) Special for this project:

Sol: AG-9AC7-S-12-0052 Page 15 of 42

SUPERINTENDENCE BY CONTRACTOR

In addition to Clause 52.236-6, the following applies: The name and the specific authorities of the foreman or superintendent must be designated in writing to the Contracting Officer. The Contractor may use his/her own prepared letterhead stationery or a "Designation of Contractor's Representative" form available from the Contracting Officer. If the Contractor or the designee is not present when work is being performed on the contract, a Suspend Work Order may be issued with contract time continuing to run. The Contractor shall have a person on-site that is fully conversant in the English language.

LANDSCAPE PRESERVATION

The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.

a. Prevention of the Landscape Defacement. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or other natural features or any other improvements in the work area unless specifically authorized by the Contracting Officer. Unless otherwise provided herein, the Contractor shall confine contract operations to within the areas designated in contract documents.

b. Protection of Streams, Lakes, and Reservoirs. The Contractor shall take sufficient precautions to prevent pollution of streams, lakes, small ponds, and reservoirs with fuels, oils, bitumens, calcium chloride, silt, or other harmful materials. Mechanical equipment shall not be operated in live streams without written approval of the Contracting Officer.

CONTRACTOR'S USE OF EXISTING ROADS

The Contractor is authorized to use roads in the immediate construction project area for performance of work under this contract. The authorization is limited to roads necessary for direct access between the construction area and storage sites, disposal areas, and other work areas designated in

The roads authorized for use will be subject to the following general conditions:

(1) State laws governing traffic rules and equipment requirements on State and County Highways.

(2) Federal Regulations contained in 36 CFR 261.12. These regulations prohibit use in excess of State Codes for weight and size, damaging a road while using it, and blocking a road open to use by others.

The Contractor shall be responsible for and perform road maintenance commensurate with his use of Forest Service roads in the construction area.

Sol: AG-9AC7-S-12-0052 Page 16 of 42

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause No Title Date

52.202-1 DEFINITIONS JAN 2012

52.203-3 GRATUITIES APR 1984

52.203-5 COVENANT AGAINST CONTINGENT FEES APR 1984

52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT SEPT 2006

52.203-7 ANTI-KICKBACK PROCEDURES OCT 2010

52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY JAN 1997

52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY JAN 1997

52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS OCT 2010

52.204-4 PRINTED OR COPIED DOUBLE- SIDED ON POSTCONSUMER FIBER CONTENT PAPER MAY 2011

52.204-7 CENTRAL CONTRACTOR REGISTRATION FEB 2012

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS

DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT

DEC 2010

52.211-18 VARIATION IN ESTIMATED QUANTITY APR 1984

52.215-2 AUDIT AND RECORDS -- NEGOTIATION OCT 2010

52.217-4 EVALUATION OF OPTIONS EXERCISED AT TIME OF CONTRACT AWARD JUN 1988

52.219-3 NOTICE OF HUBZONE SET ASIDE OR SOLE SOURCE AWARD NOV 2011

52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS JAN 2011

52.222-3 CONVICT LABOR JUN 2003

52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT – OVERTIME COMPENSATION JUL 2005

52.222-6 DAVIS-BACON ACT JUL 2005

52.222-7 WITHHOLDING OF FUNDS FEB 1988

52.222-8 PAYROLLS AND BASIC RECORDS JUN 2010

52.222-9 APPRENTICES AND TRAINEES JUL 2005

52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS FEB 1988

52.222-11 SUBCONTRACTS (LABOR STANDARDS) JUL 2005

52.222-12 CONTRACT TERMINATION – DEBARMENT FEB 1988

52.222-13 COMPLIANCE WITH DAVIS-BACON AND RELATED ACT REGULATIONS FEB 1988

52.222-14 DISPUTES CONCERNING LABOR STANDARDS FEB 1988

52.222-15 CERTIFICATION OF ELIGIBILITY FEB 1988

52.222-21 PROHIBITION OF SEGREGATED FACILITIES FEB 1999

52.222-26 EQUAL OPPORTUNITY MAR 2007

52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION FEB 1999

52.222-35 EQUAL OPPORTUNITY FOR VETERANS SEPT 2010

52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES OCT 2010

52.222-37 EMPLOYMENT REPORTS ON SPECIAL DISABLED VETERANS, VETERANS OF THE VIETNAM ERA, AND OTHER ELIGIBLE VETERANS

SEP 2010

Sol: AG-9AC7-S-12-0052 Page 17 of 42

52.222-50

COMBATING TRAFFICKING IN PERSONS

FEB 2009

52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION JUL 2012

52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION

CONTRACTS

JUL 2012

52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (ALTERNATE I) JAN 1997

52.223-6 DRUG-FREE WORKPLACE MAY 2001

52.223-15 ENERGY EFFICIENCY IN ENERGY-CONSUMING PRODUCTS DEC 2007

52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION

CONTRACTS

MAY 2008

52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING AUG 2011

52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES JUN 2008

52.227-1 AUTHORIZATION AND CONSENT DEC 2007

52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT DEC 2007

52.227-4 PATENT INDEMNITY – CONSTRUCTION CONTRACTS DEC 2007

52.228-2 ADDITIONAL BOND SECURITY OCT 1997

52.228-11 PLEDGES OF ASSETS JAN 2012

52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS OCT 1995

52.228-14 IRREVOCABLE LETTER OF CREDIT DEC 1999

52.228-15 PERFORMANCE AND PAYMENT BONDS – CONSTRUCTION OCT 2010

52.229-3 FEDERAL, STATE, AND LOCAL TAXES APR 2003

52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS SEP 2002

52.232-9 LIMITATION ON WITHHOLDING OF PAYMENTS APR 1984

52.232-17 INTEREST OCT 2010

52.232-23 ASSIGNMENT OF CLAIMS JAN 1986

52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS OCT 2008

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – CENTRAL CONTRACTOR REGISTER OCT 2003

52.233-1 DISPUTES – ALTERNATE I (DEC 1991) JULY 2002

52.233-3 PROTEST AFTER AWARD AUG 1996

52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM OCT 2004

52.236-2 DIFFERING SITE CONDITIONS APR 1984

52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK APR 1984

52.236-5 MATERIAL AND WORKMANSHIP APR 1984

52.236-6 SUPERINTENDENCE BY THE CONTRACTOR APR 1984

52.236-7 PERMITS AND RESPONSIBILITIES NOV 1991

52.236-8 OTHER CONTRACTS APR 1984

52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

APR 1984

52.236-10 OPERATIONS AND STORAGE AREAS APR 1984

52.236-11 USE AND POSSESSION PRIOR TO COMPLETION APR 1984

52.236-12 CLEANING UP APR 1984

52.236-13 ACCIDENT PREVENTION – Alternate I (NOV 1991) Alternate II (NOV 1991)

NOV 1991

52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS

Alternate I (APR 1984)

APR 1984

52.236-17 LAYOUT OF WORK APR 1984

52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION FEB 1987

52.236-26 PRECONSTRUCTION CONFERENCE FEB 1995

52.242-13 BANKRUPTCY JUL 1995

52.243-4 CHANGES JUN 2007

52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS DEC 2010

Sol: AG-9AC7-S-12-0052 Page 18 of 42

52.245-1 GOVERNMENT PROPERTY APR 2012

52.245-2 GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES APR 2012

52.246-21 WARRANTY OF CONSTRUCTION – ALTERNATE I (APR 1984) MAR 1994

52.248-3 VALUE ENGINEERING – CONSTRUCTION OCT 2010

52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) – Alternate I (SEP 1996) APR 2012

52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) APR 1984

52.253-1 COMPUTER GENERATED FORMS JAN 1991

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 REIMBURSEMENT FOR BOND PREMIUMS – FIXED-PRICE CONSTRUCTION CONTRACTS NOV 1996

452.236-71 PROHIBITION AGAINST THE USE OF LEAD-BASED PAINT NOV 1996

452.236-72 USE OF PREMISES NOV 1996

452.236-73 ARCHEOLOGICAL OR HISTORIC SITES FEB 1988

452.236-74 CONTROL OF EROSION, SEDIMENTATION AND POLLUTION NOV 1996

452.236-77 EMERGENCY RESPONSE NOV 1996

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (APR 2012)

(a) Definitions. As used in this clause— Long-term contract means a contract of more than five years in duration, including options.

However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

https://www.acquisition.gov/far/current/html/52_217_221.html#wp1135887

Sol: AG-9AC7-S-12-0052 Page 19 of 42

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure that they reflect the Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it is, is not a small business concern under NAICS Code 237310 assigned to contract number ______________.

[Contractor to sign and date and insert authorized signer’s name and title].

FAR 52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (SEP 2010)

(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984

( 46 U.S.C. App. 1702), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the

Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or http://www.sba.gov/content/table-small-business-size-standards https://www.acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508 http://uscode.house.gov/

Sol: AG-9AC7-S-12-0052 Page 20 of 42

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements the Buy American Act (41 U.S.C. 10a - 10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: NONE]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American Act.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the http://uscode.house.gov/ http://uscode.house.gov/ https://www.acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123

Sol: AG-9AC7-S-12-0052 Page 21 of 42

Contracting Officer will modify the contract to allow use of the foreign construction material.

However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON

Construction Material Description Unit of Measure Quantity Price (Dollars)* Item 1:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2: _______ _______ _______ Foreign construction material _______ _______ _______ Domestic construction material [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

FAR 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 Million, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

Sol: AG-9AC7-S-12-0052 Page 22 of 42

AGAR 452.209 – 71 REPRESENTATION BY CORPORATIONS REGARDING AN UNPAID TAX

LIABILITY OR A FELONY CONVICTION (DEVIATION 2012-01) (FEB 2012) (Alternate 1 Feb 2012)

(a) This award is subject to the provisions contained in the Consolidated Appropriations Act, 2012

(P.L. No. 112-74), Division E, Sections 433 and 434 regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –

(1) does not have a tax delinquency, meaning that it is not subject to any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and

(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered…