Wage_Determination.pdf PDF
McLeod_Contract_Area_Map.pdf PDF
Fire_Plan.pdf PDF
Appendix_B.pdf PDF
Appendix_D.pdf PDF
Vicinity_Map_.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT/ORDER AL ITEMS 1. REQUISITION NUMBER

Page 1 of 78 OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

2. CONTRACT NO. 3. AWARD/EFFECTIVE 4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICIATION ISSUE

DATE

AG-9A40-S-17-4001

DATE

July 5, 2017,

a. NAME b. TELEPHONE NUMBER(No collect calls) 8. OFFER DUE DATE/

7. FOR SOLICITATION LOCAL TIME

INFORMATION CALL: Patrick J. Gallegos 559 297-0706 4830 August 1, 2017 - 4:30 pm

9. ISSUED BY CODE 10. THIS ACQUISITON IS 11. DELIVERY FOR 12. DISCOUNT TERMS

FOB DESTINATION

USDA Forest Service Region 5 Acquisitions 1600 Tollhouse Rd.

Clovis, CA 93611

UNRESTRICTED UNLESS BLOCK IS

SET ASIDE: 100 % FOR MARKED

SMALL BUSINESS SEE

SCHEDULE

HUBZONE SMALL

BUSINESS 13a. THIS CONTRACT IS A RATED

ORDER UNDER DPAS (15 CFR 700)

8(A) 13b. RATING

NAICS: 115310

SIZE STANDARD: $ 17.5 million 14. METHOD OF SOLICITATION

RFQ IFB RFP

15. DELIVER TO CODE

16. ADMINISTERED BY CODE

See address in Block 9

17a. CONTRACTOR/ CODE FACILITY

OFFEROR CODE

18a. PAYMENT WILL BE MADE BY CODE

Sierra National Forest 1600 Tollhouse Rd Clovis Ca 93611-0532

TELEPHONE N0.

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

IS CHECKED

SEE ADDENDUM Send Invoices to Address in Block 9

19. 20. 21. 22. 23. 24.

ITEM N0. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

McLeod Road Hazard Stewardship Project Sierra National Forest

DUNS:_________________________

TIN:_________________________

E-mail Address:___________________________

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.2124. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 29. AWARD OF CONTRACT: REF. ___________________ OFFER

1 COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY DATED .. YOUR OFFER ON SOLICITATION ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN. (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

PATRICK J. GALLEGOS

31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1449 (REV.4/2002)

PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.2\

Solicitation No. AG-9A40-S-17-4001

PART I – THE SCHEDULE

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 GENERAL INFORMATION:

Proposals shall be valid for 60 days after the date of receipt for the solicitation. Refer to Section L for instructions on preparing your Technical and Price proposal.

B.2 SCHEDULE OF ITEMS

B.2.1 MANDATORY WORK ACTIVITIES:

ITEM

NO.

DESCRIPTION OF

MANDATORY WORK

ACTIVITIES

UNIT ESTIMATED

QUANTITY

UNIT

PRICE TOTAL

Fell, skid, remove Biomass and cull timber, and Pile logging slash

Acres 94 $________ $_______

B.2.2 TIMBER/PRODUCT REMOVAL PRICE SCHEDULE:

Note: These schedules are for pricing/payment purposes. See Instructions to Offerors for business proposal requirements.

B.3 LAND MANAGEMENT ACTIVITIES.

Performance of land management activities shall be in accordance with Section C – Project Description and Work Specifications. Payment for Land Management Work Activities in Schedule B-2.1 will be made in Stewardship Credits in lieu of cash, as defined in Section G. All Base Work Activities shall be performed.

SPECIES PRODUCT QTY UNIT OF

MEASURE

MINIMUM

ACCEPTABLE

OFFER

OFFER

(FLAT)

TOTAL

OFFER

Combined Softwoods Biomass 968 CCF $.25 $______ $_______

B.4 PRE-BID CONFERENCE OR TOURS

A pre-bid tour will be conducted on July 19, 2017 at 10:00 a.m. We will meet at the Bass Lake Ranger Station, 57003 Road 225, North Fork, CA 93643.

Bidders may request information about the tour by contacting Patrick J. Gallegos, telephone 559-297-0706 ext. 4830 at the Forest Supervisor’s office located at 1600 Tollhouse Rd., Clovis, CA 93611.

SECTION C – DESCRIPTION/ SPECIFICATIONS

STATEMENT OF WORK

C.1 AGAR 452.211-72 STATEMENT OF WORK/SPECIFICATIONS (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

C.2 PROJECT DESCRIPTION

(a) Description of Work – The McLeod Road Hazard IRSC Project is located on the Bass Lake Ranger District of the Sierra National Forest. There are 2 (units) work activity bid items that will be treated in addition to felling, skidding and hauling on 94 acres. These stewardship work activity items are described in detail in Appendix A and attachments. Treatment areas consist of hazard tree removal from along Forest Service system road 5S07. Hazard tree removal will be accomplished through cutting of trees that are dead within the unit boundaries.

Reduction of hazardous fuels will be accomplished by the removal and/or treatment of slash, and cull logs. Improved safety for forest visitor, homeowners and FS employees and contractors.

(b) Unit Description – Work unit boundaries are shown on the Contract Area Map and delineated on the ground blue flagging and/or blue tags facing into the unit.

(c) Project Location – The McLeod project has approximately 94 acres. The project is located north of the Malum Ridge road #274 approximately 3 miles to the south end of the Lite Greys Timber sale. Project is located in Township 7 South, Range 22 East, Sections 2, 3, 10, 11 & 15, MDBM.

(d) Resulting Contract - Any resultant contract will be a Commercial Service contract with provisions for timber removal.

C.3 Specifications Specifications for each Stewardship Activity individually described by an item number in Schedule B pages can be found in Appendix A. Specifications for timber removal can be found in Appendix B.

C.4 Contract Area Map The boundaries of Subdivisions or Payment Units and any cutting units thereof, are as shown on the attached "Contract Area Map," which is made a part hereof, and were, before solicitation, designated on the ground by Forest Service to meet the anticipated needs of the parties. The location of the Subdivisions or Payment Units and their approximate acreage are stated in Division A/AT. Subdivisions or Payment Units may be revised and additional ones may be established only by written agreement of both parties. Where applicable, the following are also identified on Contract Area Map:

(a) Identified claims limiting Contractor's rights;

(b) Boundaries of cutting units;

(c) Areas where leave trees are marked to be left uncut;

(d) Roads listed

(e) Sources of base course, rock riprap and surface rock;

(f) Roads where log hauling is prohibited or restricted;

(g) Roads and trails to be kept open;

(h) Improvements to be protected;

(i) Locations of known historical sites;

(j) Maximum stump heights when more than one height is listed by areas;

(k) Skidding or yarding methods specified;

(l) Streamcourses to be protected;

(m) Other features required by Appendix B; and

(n) Boundaries of stewardship work activities.

C.5 GOVERNMENT-FURNISHED PROPERTY: None Provided

C.6 OPERATING PLAN AND SCHEDULE

The Contractor will provide a detailed timeline of when the contract requirements will be accomplished while conforming to the requirements within Section F.4. The operating plan should indicate the sequence of activities that will take place to accomplish the tasks described within the solicitation, Appendix A, and Appendix B including proposed start and completion dates. The operating plan and schedule should contain the following elements:

• A list of employees/personnel working on this contract identifying each by the Occupational Code/Job Title for the work as it applies to this contract under the applicable Service Contract Act wage rate.

• All Subcontractors must also provide a list of all employees/personnel working on this contract identifying each by their Occupational Code/Job Title as it applies to this contract under the applicable Service Contract Act wage rate.

• A proposed communication plan regarding findings, progress, information exchange, questions, and concerns of both parties.

Depending upon how the contractor proposes accomplishing the activities within the solicitation, the Operating Plan and Schedule may be developed by indicating when and how all work activities within individual units will be completed, when and how individual tasks will be completed, or a combination of when and how units or tasks will be completed. The contractor should be able to display through an operating plan and schedule that all of the contract activities will be accomplished in a timeline that will meet the contract requirements.

C.7 KEY PERSONNEL

The follow personnel are considered key personnel by the government:

• Overall Project Manager

• Logging Supervisor

• Fuels Treatment Supervisor

• Individual Sub-Managers – Individuals supervising individual sub-contracts for work items not covered by personnel noted previously herein.

• The contractor shall provide a project manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The project manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between 7:00 a.m.

to 6:00p.m., Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons.

C.8 DEFINITIONS

Acceptable Quality Level: The allowable leeway or variance from a standard before the government will reject the specific service. An AQL does not say that the contractor may knowingly offer defective service. It implies that the government recognizes that defective performance sometimes happens unintentionally. As long as the percent of defective performance does not exceed the AQL, the service will not be rejected by the government. The contractor, however, must re-perform the defective service when possible.

Contracting Officer (CO): Individual with authority to bind the government with their signature on the contract.

Contracting Officer Representative (COR): Individual(s) designated to act on the behalf of the CO within the delegation given them in writing.

Period of performance (also Performance period or Contract time): All calendar days allowed for completion of contract work. Includes all days of the week including weekends and holidays.

Quality Assurance: Those actions taken by the government to check goods or services to determine that they meet the requirements of the SOW.

Quality Assurance Surveillance Plan (QASP): An organized written document used for quality assurance surveillance. The document contains information about how the government will assess performance, checklists, and may contain decision tables.

Quality Control: Those actions taken by a contractor to control the production of goods or services so that they will meet the requirements of the Performance Statement of Work. Refer to Inspection and Acceptance in clause 52.212-4 and Contractors Quality Control Plan as described in Section E.

Quality Control Plan: Contractors plan for self-monitoring work prior to Government inspection and acceptance. See Section E.

Random Sampling: A method of looking at a few individual items in a lot to determine the quality of that lot against a standard.

(Acceptable) Service: A job performed to the standard and within the acceptable quality level. The contractor must do the specific job, and meet the standard, and meet the acceptable quality level before one can say that performance has been acceptable and that he/she should be paid.

Standard: An acknowledged measure of comparison.

Stewardship Contracting: An exchange of goods/products for services including construction.

Sustainable Acquisitions (FAR Part 23.4 – Use of recovered materials and biobased products)

a. Biobased Products: Managed by the U.S. Department of Agriculture (USDA), the goal of the BioPreferred program is to increase the purchase and use of biobased products. The BioPreferred program was created by the 2002 Farm Bill and reauthorized and expanded as part of the Agricultural Act of 2014 (the 2014 Farm Bill). The program's purpose is to spur economic development, create new jobs and provide new markets for farm commodities. The increased development, purchase, and use of biobased products reduce our nation's reliance on petroleum, increase the use of renewable agricultural resources, and contribute to reducing adverse environmental and health impacts. Information on biobased/biopreferred products can be found at the BioPreferred Site .

The Contractor shall comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts and the provision at FAR 52.223-1, Biobased Product Certification.

b. EPA-designated items: Products that are or can be made with recovered material. The Comprehensive Procurement Guideline (CPG) program is part of EPA's continuing effort to promote the use of materials recovered from solid waste. Buying recycled-content products ensures that the materials collected in recycling programs will be used again in the manufacture of new products. See http://www.biopreferred.gov/BioPreferred/faces/pages/AboutBioPreferred.xhtml http://www.biopreferred.gov/BioPreferred/faces/pages/AboutBioPreferred.xhtml http://www.gpo.gov/fdsys/pkg/BILLS-113hr2642enr/pdf/BILLS-113hr2642enr.pdf http://www.biopreferred.gov/BioPreferred/ http://www.epa.gov/epawaste/conserve/tools/cpg/index.htm

FAR 52.223-17 Affirmative Procurement of EPA-designated items in Service and Construction Contracts.

SECTION D – PACKAGING AND MARKING

There are no clauses in this section.

SECTION E - INSPECTION AND ACCEPTANCE

E.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://www.acquisition.gov/far

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

E.2 CONTRACTOR QUALITY CONTROL INSPECTION SYSTEM

The Contractor shall identify the quality control inspection system it will use to ensure that contract specifications will be achieved. At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contractor shall produce written inspection records in a format and at times and places satisfactory to the Contracting Officer. Inspection records shall be made available upon request of the Contracting Officer and be maintained until the date of contract closure.

The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data.

E.3 ACCEPTANCE

The Contractor’s shall provide a written request for inspection and submit inspection sheets in accordance with the QCP. The Government will conduct an inspection and up to one re-inspection for each unit. If the contractor fails to meet the minimum AQL, the contractor shall rework the unit. Anytime more than two inspections are required per unit, the contractor may be assessed for additional inspections, which will include mileage and hourly rate of the COR. If follow-up inspections indicate that the minimum AQL was not met, the work will be deemed unsatisfactory and a deduction in payment may result (Section G-3.4). Acceptance may be made for all or portions of work.

E.4 GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN

Quality assurance specific to individual items will be found in Appendix A.

http://www.arnet.gov/far

SECTION F - DELIVERIES OR PERFORMANCE

General Clauses and Provisions Pertaining To All Items

F.1 52.252-2 CLAUSE INCORPORATED BY REFERENCE (FEB 1998)

effect as if they were given in full text. Upon request, the Contracting Officer will make this address: http://www.acquisition.gov/far

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-15 Stop-Work Order (Aug 1989) 52.247-55 F.O.B. Point for Delivery of Government-Furnished Property (JUN 2003)

F. 2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

The Contractor shall be required to (a) commence work under this contract in accordance with the accepted operation plan; starting work when the Contractor receives the Notice to Proceed, (b) prosecute the work diligently, and (c) complete the entire project including final cleanup of the premises by December 31, 2018.

F.3 AGAR 452.211-74 PERIOD OF PERFORMANCE (FEB 1988)

The effective period of this contract is from August 20, 2017 through December 31, (End of Clause)

F.4 SCHEDULES AND REPORTS

Contractor shall provide the following submittals as stated below unless otherwise mutually agreed upon. The Contractor shall update all submittals as needed, or as required by the CO, but in no case less than once per calendar year on a date specified by the Contracting Officer:

http://www.arnet.gov/far

ITEM DESCRIPTION COPIES

REQUIRED

Proposed progress schedule showing starting and completion dates of various phases of the work 2

List of proposed sub-contractors and their intended work. Sub-contractors must have Contracting Officer’s written approval prior to starting work on the project.

Traffic Control Plan 2 Soil Erosion and Water Pollution Control Plan 2 Designation of Contractor personnel describing responsibilities and authorities 2

All schedules and reports shall be submitted to the Contracting Officer’s Representative identified by the CO, unless the Contracting Officer directs the Contractor to submit any schedules or reports directly to the CO.

SECTION G – CONTRACT ADMINISTRATION DATA

G.1 MEASUREMENT

All linear and area measurements under this contract are measured on a horizontal plane.

G.2 PAYMENT

It is anticipated that funds will be exchanged in the performance of this contract because the value of the timber or other products will not completely offset the value of the work to be performed. Payment shall only be made under this clause to the extent that the work performed will not be offset by the timber or other products value during the contract period. When payment is made to the contractor for work performed, it will be made in accordance with FAR 52.212-4 Contract Terms and Conditions-Commercial Items (i) – Payments and 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (See clause 52.212-5). Submit certification G.8 with all invoices. Invoices are to be submitted to the contracting Officer.

The value of work completed and timber or other products removed will be documented in a Stewardship Statement of Account produced by Timber Sale Accounting (TSA) monthly when harvesting operations are underway.

G.2.1 Final Payment - Release of Claims

The Government shall pay the amount due the Contractor under this contract after—

(1) Completion and acceptance of all work;

(2) Presentation of a properly executed invoice; and

(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release.

G.3 INCIDENTAL PAYMENT ITEMS

The intent of the contract is to provide for the complete performance of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

G.4 PRODUCT PAYMENT GUARANTEE

To guarantee payment for product in advance of cutting, Contractor may earn Stewardship Credits in advance of cutting, or provide a product payment guarantee in the form of an acceptable surety payment bond, irrevocable letter of credit (ILOC), cash, or a deposit in a Federal Depository negotiable securities of the United States.

Securities shall be deposited through the Contracting Officer accompanied by a power of attorney and agreement authorizing the bond-approving officer to sell or collect such securities if payment is not made within 15 days of billing by Forest Service. The penal sum of such surety bond or the market value at time of deposit of such negotiable securities shall be the maximum amount of the payment guaranteed.

Product payment guarantee for a single contract shall be provided utilizing Form FS6500-12 Payment Bond.

Blanket Payment Bond:

a. Contractor may furnish an acceptable bond, or deposits securities, to guarantee payment for product from multiple contracts. Contractor shall not start cutting hereunder until this contract receives an allocation that will meet the obligation for product payment guarantee.

b. The amount of such bond or deposited securities shall be allocated to such contracts by the Forest Service. The Contractor shall provide the contact information for the Forest Service representative administering the blanket payment bond to the Contracting Officer. The Forest Service representative administering the blanket payment bond will provide the Contracting Officer with documentation showing the allocation to this contract.

c. When there is to be no product cutting or removal hereunder for 30 days or more and payment of current charges has been made, the allocation to this contract may be reallocated to other contracts at Contractor’s request.

d. Payment guaranteed with acceptable blanket payment bond for multiple contracts shall be provided utilizing Form FS-6500-12a Blanket Payment Bond.

G.5 STEWARDSHIP CREDITS

Stewardship Credits are credits that are earned and established when work listed in the B.1 Schedule of Supplies/Services has been performed and accepted. Stewardship credits shall be earned at the rate as shown in the Schedule. Earned credits may be used to pay for timber or other products value included in Schedule B.2. Unless otherwise indicated in the Schedules, credits will be earned based upon Actual Quantities accomplished and accepted.

G.6 ESTABLISHMENT OF STEWARDSHIP CREDITS

Notwithstanding references to payments in “Payment” clauses of this contract, payment for Stewardship Activities will be made with Product Value or other funding as indicated in the award document.

Stewardship Credits will be established on a monthly basis. Stewardship credits will be established for the number of units of each activity that have been completed and accepted. Acceptance may be for all, or a reasonable portion of, any specific activity.

Stewardship credits will not be established for work that is in progress that has not been accepted by the Forest Service. No credits will be established for work performed under terms of Schedule B.2.3.

G.7 CONTRACTOR CERTIFICATION

CONTRACTOR CERTIFICATION - EARNED STEWARDSHIP CREDITS

McLeod Stewardship Project

I hereby certify, to the best of my knowledge and belief, that--

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) Payments to subcontractors and suppliers have been made, and timely payments will be made for the work activities covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments/credits does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor's performance.

(Name)

(Title)

(Date)

G.8 EXCESS STEWARDSHIP CREDITS

In the event there are excess (unused) established Stewardship Credits when all of the included timber or other products has been cut and removed the Forest Service, at its option, shall either add more timber or other products or make cash payment for the unused credits.

G.10 EXCESS TIMBER OR OTHER PRODUCTS VALUE

In the event the value of the included timber or other products exceeds the total value of all of the mandatory activities plus the ordered optional activities, the Contractor shall make cash payment for the excess timber or other products value.

G.11 REFUND OF EXCESS CASH

If at any time the credit balance of the Stewardship Statement of Account exceeds the charges for timber or other products removed to date and for timber or other products that the Forest Service estimates will be cut within the next 60 calendar days, any portion of such excess from cash in the account shall be refunded if requested by Contractor. If no cutting is planned within the next 60 calendar days, refund of the entire unencumbered cash balance may be made. After a refund, deposits shall be made to meet the requirements of the clause entitled, “PRODUCT PAYMENT GUARANTEE” before additional timber or other products may be cut.

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1 AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled within 10 days after the date of contract award. The conference will be held at the TBD, and will include discussion of contract terms and work performance requirements, work progress schedule and fire prevention/suppression and safety plans.

H.2 AGAR 452.236-72 USE OF PREMISES (NOV 1996)

(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.

(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.

H.3 AGAR 452.237-74 KEY PERSONNEL (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

1. Overall Project Manager

2. Logging Supervisor

3. Individual Sub-Managers – Individuals supervising individual sub-contracts for work items not covered by personnel noted previously herein. Information on key personnel qualifications are found in Section C.

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.

Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

H.4 SAFETY

Contractor’s Operations shall facilitate Forest Service’s safe and practical inspection of Contractor’s Operations and conduct of other official duties on Contract Area.

Contractor has all responsibility for compliance with safety requirements for Contractor's employees. In the event that a conflict develops between the requirements of this contract or agreed upon methods of proceeding hereunder and State or Federal safety requirements, the contract shall be modified and Contractor may request an equitable adjustment.

H.5 REQUIREMENTS OF RIGHTS-OF-WAY

Contractor’s use on rights-of-way shall be confined to said rights-of-way and limited by the related easements and stipulations, if any, unless Contractor makes other arrangements that will not infringe upon or adversely affect the grantee’s rights. Said easements or right-of-way documents are available in the offices of the Forest Supervisor and District Ranger.

H.6 USE OF ROADS BY CONTRACTOR

Contractor is authorized to maintain roads, bridges, and other transportation facilities, as needed for harvesting Included Timber or other products on National Forest and other lands where Forest Service has such authority. The location and clearing widths of all Temporary Roads or facilities shall be agreed to before construction is started.

Contractor is authorized to cut and use for construction without charge construction timber or other products designated by agreement. Except as provided herein, Contractor is authorized to use existing National Forest roads and Specified Roads, when such use will not cause damage to the roads or National Forest resources and when hauling can be done safely. If Contractor’s use of an existing temporary or National Forest system road cannot be satisfactorily accommodated without reconstruction, Contractor shall be authorized to use such road upon agreement as to the minimum reconstruction work that Contractor shall perform before hauling.

The Contract Area Map shows existing temporary or permanent roads that for such reasons as limitations in structural capacity, safety, and protection of soil, water, and roads:

(a) Cannot be used for log hauling or

(b) May be used only under the restrictive limitations stated therein.

Contractor's use of existing roads identified on Contract Area Map by the following codes is prohibited or subject to restrictive limitations, unless agreed otherwise:

Code Use Limitations X Hauling prohibited R Hauling restricted U Unsuitable for hauling prior to completion of agreed reconstruction P Use prohibited A Public use restriction W Regulation waiver

Roads coded A will be signed by the Forest Service to inform the public of use restrictions. Contractor's use of roads coded R, A, or W shall be in accordance with the following restrictions:

Road Number Road Name

Termini Map Description of Restrictions

From To Legend

MAD274

5S07

5S07Z

Malum Ridge Road Beasore Road None

Road 200

PVT

Road 5S07

EOR

N 2.7miles Trailhead

R R R

Hauling prohibited 6PM on Friday until 6AM Monday. No hauling on federal holidays.

Hauling is prohibited on weekdays from 7PM to 6AM

5S07U 5S07 EOR A Block road when hauling/use is completed.

5S07T 5S07 EOR A Block road when hauling/use is completed.

5S07TA 5S07 EOR A Block road when hauling/use is completed.

5S07P 5S07 EOR A Block road when hauling/use is completed.

5S07S 5S07 EOR A Block road when hauling/use is completed.

5S07Q 5S07 EOR A Block road when hauling/use is completed.

EOR – End of Road FS/PVT – Forest Service/Private

H.7 TRAFFIC CONTROL PLAN

Unless otherwise agreed in writing, when Contractor’s Operations are in progress adjacent to or on Forest Service controlled roads and trails open to public travel, Contractor shall furnish, install, and maintain all temporary traffic controls that provide the user with adequate warning of hazardous or potentially hazardous conditions associated with Contractor’s Operations. Contractor and Forest Service shall agree to a specific Traffic Control plan for each individual project prior to commencing operations.

Devices shall be appropriate to current conditions and shall be covered or removed when not needed. Except at otherwise agreed, flagmen and devices shall be as specified in the “Manual on Uniform Traffic Control Devices for Streets and Highways” (MUCD) and as shown on Plans, Contract Area Map, Traffic Control Plan or in specifications attached hereto.

H.8 USE BY OTHERS

Forest Service shall have the right to use any road constructed by Contractor under this contract for any and all purposes in connection with the protection and administration of the National Forest. Other parties, in connection with the logging of tributary National Forest timber, may use roads constructed by Contractor hereunder when such use will not materially interfere with Contractor’s Operations. Such third party use shall be contingent upon the third party paying a fair share of maintenance cost commensurate with such commercial use. Unless otherwise provided, Forest Service shall authorize other uses of roads constructed by Contractor hereunder only if:

(a) Forest Service makes appropriate arrangements to relieve Contractor of related maintenance costs commensurate with such other uses and

(b) Such other uses will not materially interfere with Contractor’s Operations.

Where Contractor reconstructs a road having established use, the use during reconstruction and thereafter by Contractor shall be such as to reasonably accommodate such established use. Contractor shall have the right to use such reconstructed road without material additional interference from other users.

H.9 PROTECTION OF LAND SURVEY MONUMENTS

Forest Service shall appropriately designate on the ground all known survey monuments, section corners, and other corner accessories. Forest Service shall post identifying signs on two sides of each known bearing tree.

Forest Service shall arrange protective or perpetuative action that does not cause unnecessary delay to Contractor in authorized clearings, such as Clearcutting Units and road construction, and in other instances where damage to monuments, section corners, and other corner accessories is unavoidable.

Contractor shall protect all known survey monuments, witness corners, reference monuments, and bearing trees against avoidable destruction, obliteration, or damage during Contractor’s Operations. If any known monuments, corners, or accessories are destroyed, obliterated, or damaged by Contractor’s Operations, Contractor shall hire the appropriate county surveyor or a registered land surveyor to reestablish or restore at the same location the monuments, corners, or accessories at no additional cost to the Government. Such surveyors shall use procedures in accordance with the Bureau of

Land Management “Manual of Instructions for the Survey of the Public Lands of the United States” for General Land Office surveys and in accordance with State law for others. Contractor shall record such survey in appropriate county records.

H.10 PROTECTION MEASURES NEEDED FOR PLANTS ANIMALS, CULTURAL

RESOURCES, AND CAVE RESOURCES

1. Areas, known by Forest Service prior to contract solicitation, needing special measures for the protection of plants, animals, cultural resources, and/or cave resources are shown on Contract Area Map and/or identified on the ground, and shall be treated as follows:

a. Unless agreed otherwise, wheeled or track laying equipment shall not be operated in areas identified as needing special measures except on roads, landings, tractor roads, or skid trails. Contractor may be required to backblade skid trails and other ground disturbed by Contractor’s Operations within such areas in lieu of cross ditching.

b. Unless agreed otherwise, trees will not be felled into areas identified as needing special measures.

c. Contractor shall conduct operations in a manner that does not damage or disturb identified areas. In the event that protective measures identified by the Forest Service are for any reason inadequate, Contracting Officer may delay or interrupt Contractor’s operations, under this Contract, and/or modify this Contract.

d. Contractor shall immediately notify the Forest Service if its operations disturb or damage any area identified as needing special protection, and shall immediately halt its operations in the vicinity of such area until the Forest Service authorizes continued operations. In the event that Contractor's operations disturb or damage an area identified as needing special protection, then Contractor shall reimburse the Forest Service for the full cost and expense of any evaluative and remedial measures undertaken by the Forest Service in connection with such disturbance or damage. Such payment shall not relieve Contractor from civil or criminal liability under applicable law.

2. Nothing contained in this clause shall establish, or be deemed to establish any express or implied warranty on the part of the Forest Service that the Forest Service has identified all areas within the Contract Area requiring special protection, or that measures prescribed by the Forest Service for protection of such areas are adequate.

3. Following contract solicitation, additional areas needing special measures for protection may be discovered or identified; protective measures may be revised or newly prescribed; and, additional species of plants and/or animals may be added to federal lists of protected species. In such event, Contracting Officer may delay or interrupt Contractor’s operations, under this Contract, and/or modify this Contract.

4. Discovery, by either the Contractor or the Forest Service, of additional areas, resources, species, or members of species needing special protection shall be promptly reported to the other party.

5. Site Specific Protection Measures

a) Identified as "CA-1" on Contract Area Map. Unless otherwise agreed, no Contractor Operation will be permitted within areas flagged with blue/black candy striped flagging and solid white ribbon tied together.

b) Logging and associated timber sale activities are anticipated and/or required within Controlled Areas (CA-1). Extraordinary treatment methods will be required within and around such identified special areas of consideration. Notwithstanding KT-CT.3.5# (Appendix B) - Designation of Timber, trees marked, or portions of trees, may be required to be left within such areas, if Contractor is notified in writing that removal will cause unacceptable damage to the resource. Such areas are identified on the Contract Area Map. Prior to initiating treatments within Controlled Areas (CA-1s), Forest Service and Contractor shall agree in writing, treatments that will occur within the Controlled Area. Additional CA-1s requiring special Controlled Area treatments may be discovered and identified during sale operations; these areas will be protected from ground disturbing activities or may be treated only by agreement in writing.

c) Identified as NOX on Contract Area Map (weeds). Unless otherwise agreed, no Contractor Operations are permitted within areas flagged in orange "Noxious Weeds" flagging.

H.11 PROTECTION OF RESIDUAL TREES

Contractor's Operations shall not unnecessarily damage young growth or other trees to be reserved.

H.12 SANITATION AND SERVICING

Contractor shall take all reasonable precautions to prevent pollution of air, soil, and water by Contractor’s Operations. If facilities for employees are established on Contract Area, they shall be operated in a sanitary manner. In the event that Contractor’s Operations or servicing of equipment result in pollution to soil or water, Contractor shall conduct cleanup and restoration of the polluted site to the satisfaction of Forest Service.

Contractor shall maintain all equipment operating on Contract Area in good repair and free of abnormal leakage of lubricants, fuel, coolants, and hydraulic fluid. Contractor shall not service tractors, trucks, or other equipment on National Forest lands where servicing is likely to result in pollution to soil or water. Contractor shall furnish oil-absorbing mats for use under all stationary equipment or equipment being serviced to prevent leaking or spilled petroleum-based products from contaminating soil and water resources. Contractor shall remove from National Forest lands all contaminated soil, vegetation, debris, vehicle oil filters (drained of free-flowing oil), batteries, oily rags, and waste oil resulting from use, servicing, repair, or abandonment of equipment.

H.13 PREVENTION OF OIL SPILLS

If Contractor maintains storage facilities for oil or oil products on Contract Area, Contractor shall take appropriate preventive measures to ensure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual States.

If the total oil or oil products storage exceeds 1,320 gallons in containers of 55 gallons or greater, Contractor shall prepare a Spill Prevention Control and Countermeasures Plan. Such plan shall meet applicable EPA requirements (40 CFR 112), including certification by a registered professional engineer.

Contractor shall notify Contracting Officer and appropriate agencies of all reportable (40 CFR 110) spills of oil or oil products on or in the vicinity of Contract Area that are caused by Contractor’s employees agents, contractors, Subcontractors, or their employees or agents, directly or indirectly, as a result of Contractor’s Operations.

Contractor will take whatever initial action may be safely accomplished to contain all spills.

H.14 HAZARDOUS SUBSTANCES

Contractor shall notify the National Response Center and Contracting Officer of all releases of reportable quantities of hazardous substances on or in the vicinity of Contract Area that are caused by Contractor’s employees, agents, Subcontractors or their employees or agents, directly or indirectly, as a result of Contractor’s Operations, in accordance with 40 CFR 302.

H.15 EQUIPMENT CLEANING

In order to prevent the spread of noxious weeds into the Contract Area, Contractor shall be required to clean all off-road logging and construction equipment prior to entry on to the Contract Area. This cleaning shall remove all soil, plant parts, seeds, vegetative matter, or other debris that could contain or hold seeds. Only logging and construction equipment so cleaned and inspected by the Forest Service will be allowed to operate within the Contract Area. All subsequent move-ins of equipment to the Contract Area shall be treated in the same manner as the initial move in. "Off-road equipment" includes all logging and construction machinery, except for log trucks, chip vans, service vehicles, water trucks, pickup trucks, cars, and similar vehicles.

Contractor shall employ whatever cleaning methods are necessary to ensure that off-road equipment is free of noxious weeds. Equipment shall be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material.

Disassembly of equipment components or specialized inspection tools is not required.

Unless otherwise agreed, Contractor shall give the Forest Service at least 24 hours’ notice when equipment is ready for inspection. Notification will include an agreed upon location where the equipment will be available for inspection by the forest service.

New infestations of noxious weeds, of concern to Forest Service and identified by either Contractor or Forest Service, on the Contract Area or on the haul route, shall be promptly reported to the other party. Contractor and Forest Service shall agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.

H.16 EROSION PREVENTION AND CONTROL

Contractor’s Operations shall be conducted reasonably to minimize soil erosion.

Equipment shall not be operated when ground conditions are such that excessive damage will result. The kinds and intensity of erosion control work done by Contractor shall be adjusted to ground and weather conditions and the need for controlling runoff.

Erosion control work shall be kept current immediately preceding expected seasonal periods of precipitation or runoff.

If Contractor fails to do seasonal erosion control work prior to any seasonal period of precipitation or runoff, Forest Service may temporarily assume responsibility for the work and any unencumbered deposits hereunder may be used by Forest Service to do the work. If needed for such work, Contractor shall make additional deposits on request by Forest Service. Any money deposited or used for this purpose shall be treated as cooperative deposits.

H.17 STREAMCOURSE PROTECTION

“Streamcourses” that are subject to provisions of this Section are shown on Contract Map. Unless otherwise agreed, the following measures shall be observed to protect Streamcourses:

(a) Contractor’s Operations shall be conducted to prevent debris from entering Streamcourses, except as may be authorized under paragraph (d). In event Contractor causes debris to enter Streamcourses in amounts that may adversely affect the natural flow of the stream, water quality, or fishery resource, Contractor shall remove such debris as soon as practicable, but not to exceed 2 days, and in an agreed manner that will cause the least disturbance to Streamcourses.

(b) Culverts or bridges shall be required on Temporary Roads at all points where it is necessary to cross Streamcourses. Such facilities shall be of sufficient size and design and installed in a manner to provide unobstructed flow of water and to minimize damage to Streamcourses. Trees or products shall not be otherwise hauled or yarded across Streamcourses unless fully suspended.

(c) Wheeled or track-laying equipment shall not be operated in Streamcourses, except at crossings designated by Forest Service or as essential to construction or removal of culverts and bridges.

(d) Flow in Streamcourses may be temporarily diverted only if such diversion is necessary for Contractor’s planned construction and Forest Service gives written authorization. Such flow shall be restored to the natural course as soon as practicable and, in any event, prior to a major storm runoff period or runoff season.

Label on Contract Area Map

Restrictions

See CAM The Streamside Management Zone (SMZ) is shown on the contract area map and designated on the ground with White flagging with Blue polka dots. Equipment operations will be limited to crossings as agreed upon with the Forest Service. No landing piles will be allowed within the SMZ. Logs may be decked within the zone for later loading and hauling, in areas agreed upon with the Forest Service.

H.18 MEADOW PROTECTION

Reasonable care shall be taken to avoid damage to the cover, soil, and water in meadows shown on Contract Area Map. Vehicular or skidding equipment shall not be used on meadows, except where roads, landings, and tractor roads are approved.

Unless otherwise agreed, trees felled into meadows shall be removed by endlining.

Resulting logging slash shall be removed where necessary to protect cover, soil, and water.

H.19 WETLANDS PROTECTION

Wetlands requiring protection under Executive Order 11990 are shown on Contract Area Map. Vehicular or skidding equipment shall not be used in such wetlands, except where roads, landings, and tractor roads are approved by the Contracting Officer.

Additional measures needed to protect such areas are provided elsewhere herein.

H.20 AGAR 452.236-78 FIRE SUPPRESSION AND LIABILITY (MARCH 2016)

(a) Contractor's Responsibility for Fire Fighting. The Contractor, under the provisions of FAR clause 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work. The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents or employees subject to the following fire classifications:

(b) Fire Suppression Costs. The Contractor's obligations for cost of fire suppression vary according to three classifications of fires as follows:

(1) Operations Fire. An ``operations fire'' is a fire caused by the Contractor's operations other than a negligent Fire. The Contractor agrees to reimburse Forest Service for such cost for each operations fire, subject to a maximum of the dollar amount of $10,800.00. The cost of the Contractor's actions, supplies, and equipment on any such fire, or otherwise provided at the request of Forest Service, shall be credited toward such maximum. If the Contractor's actual cost exceeds contractor's obligation stated above, Forest Service shall reimburse the contractor for the excess.

(2) Negligent Fire. A ``negligent fire'' is a fire caused by the negligence or fault of the Contractor's operations including, but not limited to, one caused by smoking by persons engaged in the Contractor's operations during the course of their employment, or during rest or lunch periods; or if the Contractor's failure to comply with requirements under this contract results in a fire starting, or permits a fire to spread. Damages and the cost of suppressing negligent fires shall be borne by the Contractor.

(3) Other Fires on Contract Area. Forest Service shall pay the Contractor, at firefighting rates common in the area or at prior agreed rates, for equipment or personnel furnished by the Contractor at the request of Forest Service, on any fire on contract area other than an operations fire or a negligent fire.

(c) Contractor's Responsibility for Notification in Case of Fire.