Appendix_B.pdf

PDF 161 KB Posted

Attached to
McLeod Road Hazard Stewardship Project Federal contract opportunity
Solicitation number
AG-9A40-S-17-4001
Issued by
Department of Agriculture Forest Service

About this file

Appendix B

View the file

Other files for this federal contract opportunity

Other files attached to McLeod Road Hazard Stewardship Project, newest first.
File Type Posted
Amendment_No._1.pdf PDF
Meeting_Notes.pdf PDF
McLeod_Stewardship_Pre-bid_notes.pdf PDF
Appendix_A.pdf PDF
Fire_Plan.pdf PDF
Solicitation.pdf PDF
Wage_Determination.pdf PDF
McLeod_Contract_Area_Map.pdf PDF
Appendix_D.pdf PDF
Vicinity_Map_.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. AG-9A40-S-17-4001 McLeod Road Hazard Stewardship Project

APPENDIX B

STEWARDSHIP CONTRACT TIMBER REMOVAL SPECIFICATIONS

*BT.0 CONTRACT AREA

*BT.2 Claims

*CT.0 TIMBER SPECIFICATIONS

*CT.1 Included Timber *CT.1.1 Standard Timber *CT.1.2 Substandard Timber *CT.1.3 Damaged Timber *CT.1.3.1 Damaged by Contractor *CT.1.3.2 Negligent or Willful Damage *CT.1.3.4 Minor Damage by Natural Causes *CT.1.4 Unintentionally Cut Timber *CT.1.6 Other Material *CT.2 Utilization and Removal of Included Timber *CT.3 Timber Designations *CT 3.2.2 Other Authorized Clearings CT.3.5 Individual Trees *CT.3.7 Minor Changes *CT.4 Volume Estimate

*DT.0 RATES OF PAYMENT

*DT.1 Current Contract Rates *DT.4 Other Payment Rates *DT.4.1 Material and Quantities Not in Division AT *DT.4.2 Timber Cut Through Mistake *DT.4.2.1 Designated Timber Cut But Not Removed *DT.4.3 Undesignated Timber Damaged Without Negligence *DT.4.4 Undesignated Timber Unnecessarily Damaged or Negligently or Willfully Cut *DT.4.5 Liquidated Damages

ET.0 PAYMENTS

*ET.1 Amount Payable for Timber *ET.2 Integrated Resource Account *ET.3 Deposits When Payment Guaranteed

GT.0 OPERATIONS

*GT.4 Conduct of Logging *GT.4.1 Felling and Bucking *GT.4.1.1 Felling in Clearings *GT.4.1.2 Stump Heights *GT.4.1.3 Limbing *GT.4.2 Skidding and Yarding *GT.4.2.2 Landings and Skid Trails *GT.4.2.3 Skidding on Roads GT.4.2.4 Arches and Dozer Blades *GT.6.3 Temporary Roads *GT.6.4 Landings *GT.6.5 Skid Trails and Fire Lines *GT.6.6 Current Operating Areas *GT.6.7 Erosion Control Structure Maintenance *GT.7 Slash Disposal *GT 8 Measuring **GT.8.1 Product Identification

IT.0 OTHER CONDITIONS

*IT.1 Title and Liability *IT.1.1 Title Passage *IT.1.2 Liability for Loss *IT.5 Sale of Other Materials

SPECIAL WO OR REGIONAL K CLAUSES

WO-KT-IT.6.8# Use of Timber (Option 1) (9/04)

KT-GT.2.2# - Protection of Improvements R5-KT-CT.3.5# - Designation Of Timber, Cutting Unit Boundaries, and Payment Unit Boundaries (6/2012) KT_CT.3.5.3# Designation by Damage Class. (9/04) R5-KT-FT.3.5# – Road and Water Supply Use (5/2008) R5-KT-GT.3.1.4 - Release of Payment Units (2/2005) KT-GT.3.1.5# - Project Operations Schedule (12/2006) KT-GT.3.3.1 - Log Trucking (2/2005) KT-GT.3.7 - Substitute Methods (2/2005) KT-GT.4.1# - Felling, Bucking, and Limbing (8/2007) KT-GT.4.2# - Ground Based Skidding (12/2006) KT-GT.5 - Streamcourse Protection (2/2005) KT-GT.7# - Slash Treatment (12/2006) KT-GT.8.3 - Accountability (2/2005) KT-HT.2# - Specified Fire Precautions (06/2012) KT-HT.2.2# - Emergency Precautions (06/2012) \

Division AT Location and Area:

This Contract Area of 94 acres more or less is located in: T7S, R22E, sections 2,3,10,11 and 15 MDBM, in Madera County, California

Volume Estimate and Utilization Standards

Species Group Product Estimated Quantity *

Unit of Measure

Minimum Specifications Merchantable Tree Piece Required to be Removed Diameter Breast High (d.b.h.)

(inches)

Number of Minimum Pieces per Tree

Length

(feet)

Diameter Inside Bark at Small End

(inches)

1/

Incense Cedar 08 106.15 03 8.0 1 10 6.0 N/A Ponderosa pine 08 831.48 03 8.0 1 10 6.0 N/A Sugar pine 08 30.79 03 8.0 1 10 6.0 N/A

Timber Subject to Agreement

Total Quantity 968.42 1/ Enter Merchantability Factor (Merch. Factor) or Net Scale in % of Gross Scale, whichever is appropriate.

Timber Designations, acres are approximate:

Number Acres

Clearcutting Units (CT.3.1) Overstory Removal Units (CT.3.3) Understory Removal Units (CT.3.4) Individual Trees (CT.3.5) 94 Incompletely Measured (CT.3) Designation by Description or Prescription (KT-CT.3)

High Stumps

Species Product Maximum Stump Height (inches)

ALL 08 12

Roads Name and Date of Governing Road Specifications:

Project Design Class

Approx.

Length (mi./km.)

Sheet Numbers and Approval Date

Performance Responsibility

Survey Design Const.

Staking1/ Road No. Name

1/ Indicate timing, i.e., before clearing (BC) or after clearing (AC).

Specification sheets with itemized construction codes also attached

Schedule of Payment Units

Payment Unit Number

Approx.

Acres

To be Paid for at Flat Rates Total Flat Rate Payment

Total Required Deposits For Slash Disposal $ Species Products Quantity

Unit of Measure

APPLICABLE REGIONAL CLAUSES MAY BE ADDED

UNITED STATES DEPARTMENT OF AGRICULTURE

Forest Service

TIMBER REMOVAL SPECIFICATIONS

CLAUSES FOR TREE MEASUREMENT TIMBER REMOVAL CONTRACTS

(Applicable to Contracts to be Measured Before Felling)

This Division is organized into Parts, Sections, Subsections, and Items. These are numbered in accordance with the following scheme: Part BTl.0, Section BTl.1, Subsection BTl.11, and Item BTl.111. References to a Part include all Sections, Subsections, and Items within that Part; references to a Section include all Subsections and Items within that Section; and references to a Subsection include all Items within that Subsection. Cross references within this contract cite the reference number of the applicable Division, Part, Section, Subsection, and Item. Descriptive headings used are not to be considered in determining the rights and obligations of the parties hereunder. The Standard Clauses in this Division are subject to Specific Conditions of the contract stated in Division AT. Wherever appropriate, Specific Conditions established in Division AT are herein cited by reference number. References to Standard Clauses also apply to Special KT Clauses with the same numbers. These clauses are applicable only to the timber removal portion of the McLeod Road Hazard Stewardship Contract except where otherwise specifically referenced. “Timber” when used in this appendix includes timber and other products.

BT.0—CONTRACT AREA

BT.2 Claims. Valid claims are excluded from Contract Area, except those on which timber cutting is authorized in writing by the claimant and except mining claims on which cutting is authorized by the Act of July 23, 1955 (30 USC 614). Claims that limit Contractor’s rights to operate under this contract and that Forest Service has been able to identify are shown on Contract Area Map. Contractor is not obligated to operate contrary to existing claim limitations.

Forest Service shall designate boundaries of claims on the ground to the extent necessary to identify Included Timber.

CT.0—TIMBER SPECIFICATIONS

CT.1 Included Timber. “Included Timber” consists of:

CT.1.1 Standard Timber. Live and dead trees and portions thereof that meet Utilization Standards and are designated for cutting.

CT.1.2 Substandard Timber. Live and dead trees that:

(a) Do not meet Utilization Standards and

(b) Are located in Clearcutting Units or construction clearings or are otherwise designated for cutting.

CT.1.3 Damaged Timber.

CT.1.3.1 Damaged by Contractor. Undesignated live trees meeting Utilization Standards (a) within 200 feet slope distance from centerline of roads constructed hereunder which are damaged by Contractor's construction to the extent that considerable deterioration or mortality is imminent and are designated by Forest Service for felling before the nearest road segment is substantially completed; or (b) which are damaged by Contractor in logging and are subsequently Marked before Contractor has completed skidding or yarding operations in the immediate area. By agreement, such trees may be left without charge if their removal would cause undue damage or be grossly uneconomic.

CT.1.3.2 Negligent or Willful Damage. Undesignated timber meeting Utilization Standards and unnecessarily damaged or negligently or willfully cut by Contractor, if included by Forest Service.

CT.1.3.4 Minor Damage by Natural Causes. Undesignated trees within Contract Area and meeting Utilization Standards, that become insect infested, windthrown, suffer serious damage, or die, as designated by agreement.

CT.1.4 Unintentionally Cut Timber. Trees within or immediately adjacent to Contract Area or to road construction or other authorized clearing outside Contract Area, not designated for cutting but that are cut through mistake by Contractor, when included by Forest Service.

CT.1.6 Other Material. Species or products not listed in the contract, upon written approval of Forest Service.

CT.2 Utilization and Removal of Included Timber. “Utilization Standards” for trees and minimum pieces are stated in Division AT. To meet minimum tree specifications, trees must equal or exceed tree diameters listed in Division AT and contain at least one minimum piece. Except for timber required or authorized to be left, Contractor shall fell and buck such trees and shall remove from Contract Area all pieces that:

(a) Meet minimum piece standards in Division AT or

(b) Do not meet such standards, but would have qualified as part of minimum pieces if bucking lengths were varied to include such material.

CT.3 Timber Designations. Timber designated for cutting shall be confined to Contract Area, except as otherwise provided. Contract Area Map indicates Payment Units, if any, where Marking is to be done after solicitation, except for construction clearing, minor changes, and damaged timber. The boundaries of cutting units were plainly marked on ground before solicitation and are shown on Contract Area Map. The number of units and approximate acreage of timber designations are stated in Division AT.

CT.3.2.2 Other Authorized Clearings. Timber within authorized clearings for Temporary Roads, landings, or other construction clearings is designated for cutting. Quantities of such timber are not included in Division AT.

CT.3.5 Individual Trees. All trees to be cut, other than in the units described in CT.3.1, CT.3.2, CT.3.3, and CT.3.4, are Marked or designated by description. Trees are “Marked” when individually designated by Forest Service with paint marks above and below stump height. Contract Area Map indicates areas plainly identified on the ground where leave trees are Marked to be left uncut.

CT.37 Minor Changes. Within Contract Area, minor adjustments may be made in boundaries of cutting units or in the timber individually Marked for cutting when acceptable to Contractor and Forest Service.

CT.4 Volume Estimate. The estimated volumes of timber by species designated for cutting and expected to be cut under Utilization Standards are listed in Division AT. The estimated volumes stated are not to be construed as guarantees or limitations of the timber volumes to be designated for cutting under the terms of this contract.

DT.0—RATES OF PAYMENT

DT.1 Current Contract Rates. Included Timber that is released for Cutting shall be paid for at Current Contract Rates determined under this Section. “Current Contract Rates” shall be Flat Rates. Flat Rates shall be those listed in Division AT or B2 of the Schedule of Items. In the event contract time is adjusted, Current Contract Rates shall be continued in the same manner as immediately prior to the adjustment period.

DT.4 Other Payment Rates.

DT.4.1 Material and Quantities Not in Division AT. Incidental amounts of products or portions of trees of species that do not meet Utilization Standards may be removed without charge. Such material from Clearcutting Units and construction clearings may be purposely removed in more than incidental amounts without charge subject to agreement on deposits for road maintenance and use. Such material from other than Clearcutting Units and construction clearings may be purposely removed in more than incidental amounts without charge upon written approval of Contracting Officer, and subject to agreement on deposits if needed for road maintenance and use. Other species or products not listed may, upon written approval of Contracting Officer, be cut and removed without charge other than Required Deposits established by agreement. Timber for which the quantity is not included in the estimate, shall be paid for at Current Contract Rates and Required Deposits.

DT.4.2 Timber Cut Through Mistake. Undesignated timber meeting Utilization Standards, cut by Contractor through mistake and included by the Forest Service, shall be removed and paid for at Current Contract Rates and Required Deposits, unless such material is not listed. In such event, Forest Service, in accord with standard Forest Service methods, shall establish rates to be paid.

DT.4.2.1 Designated Timber Cut But Not Removed. Standard timber shall be removed prior to acceptance of a Subdivision for completion of logging. There shall be no charge when (a) leaving the incidental material is justified under existing conditions, or (b) Cut timber is left by option or requirement.

DT.4.3 Undesignated Timber Damaged Without Negligence. Undesignated timber meeting Utilization Standards, damaged without negligence by Contractor and designated by Forest Service, shall be cut, removed, and paid for at Current Contract Rates and Required Deposits.

DT.4.4 Undesignated Timber Unnecessarily Damaged or Negligently or Willfully Cut. Undesignated timber meeting Utilization Standards and unnecessarily damaged or negligently or willfully cut by Contractor, if included by Forest Service shall be cut, removed, and paid for at Current Contract Rates and Required Deposits that are in addition to liquidated damages. If such timber is of a species or size not listed in Division AT or is of a quality different from designated timber, Contracting Officer shall establish payment rates in accord with standard Forest Service methods.

DT.4.5 Liquidated Damages. Unnecessary damage to or negligent or willful cutting of undesignated timber, on portions of Contract Area cut over under this contract is likely to cause substantial silvicultural or other damage to the National Forest. It will be difficult, if not impossible, to determine the amount of such damage. Therefore, Contractor shall pay as fixed, agreed, and liquidated damages an amount equivalent to the amount payable at Current Contract Rates. If designated by the Forest Service, Contractor shall remove such damaged timber.

ET.0—PAYMENTS

ET.1 Amount Payable for Timber. Current Contract Rates and Required Deposits in effect when a Payment Unit is released for cutting shall be applied to the timber quantities to determine the amount Contractor shall pay. Payment shall be in the form of Stewardship Credits or cash.

E.2 Stewardship Account “Stewardship Account” is an account of all Contractor’s deposits, credits, Payment Guarantees, and the charges for:

a. Timber, or other Products at rates specified in contract

b. Slash disposal and road maintenance at Required Deposit rates,

c. Stewardship Credits established,

d. Contract Scaling Deposits, and

e. Other Charges provided in this contract.

Cash deposits and Stewardship Credits earned shall be recorded currently in such account.

Charges for timber cut shall be made when Forest Service prepares and furnishes to Contractor periodic statements of volume and value of such timber cut and scaled. Charges against Stewardship Credits shall be limited to timber value in excess of Required Deposits. Required Deposits and Other Charges shall be paid in cash.

Contractor shall make cash deposits to meet Contractor’s obligations within 15 days of billing by the Forest Service. Deposits shall be made to Forest Service, USDA, by mail or delivery to the address shown on the bill for collection.

ET.3 - Deposits When Payment Guaranteed. (05/10) To the extent payment guarantee is provided under Clause entitled, “PRODUCT PAYMENT GUARANTEE” requirements for advance cash deposits shall be waived for the value of Product on contract area that is cut, but not removed, and for the value of Products removed from contract area, up to limit of remaining stewardship credits to be earned and exchanged for value of included product except for Required Deposits and Associated Charges. Associated charges shall be waived for not more than one monthly billing period.

GT.0—OPERATIONS

GT.4 Conduct of Logging. Unless otherwise specifically provided herein, Contractor shall fell trees designated for cutting and shall remove the portions which meet Utilization Standards, except for occasional trees inadvertently not cut or trees or pieces not removed for good reason, including possible damage to forest resources or gross economic impracticability at the time of removal of other timber. Logging shall be conducted in accordance with the following, unless other clauses set forth requirements to meet special or unusual logging conditions:

GT.4.1 Felling and Bucking. Felling shall be done to minimize breakage of Included Timber and damage to residual timber. Unless agreed otherwise, felling shall be done by saws or shears. Bucking shall be done to permit removal of all minimum pieces set forth in Division AT. Contractor may buck out cull material when necessary to produce pieces meeting Utilization Standards. Such bucked out material shall contain a minimum amount of sound wood, not in excess of the net Measure in percentage of gross Measure, or based on the merchantability factor, whichever is stated in Division AT. If necessary to assess extent of defect, Contractor shall make sample saw cuts or wedges.

GT.4.1.1 Felling in Clearings. Insofar as ground conditions, tree lean and shape of clearings permit, trees shall be felled so that their tops do not extend outside construction clearings and areas of regeneration cutting.

GT.4.1.2 Stump Heights. Stumps shall not exceed, on the side adjacent to the highest ground, the maximum heights set forth in Division AT, except that occasional stumps of greater heights shall be acceptable when necessary for safe and efficient conduct of logging. Except for acceptable high stumps stated above, Contractor shall re-cut high stumps so they will not exceed heights specified in Division AT and shall dispose of severed portions in the same manner as other logging debris or as otherwise agreed. The stump heights shown in Division AT were selected with the objective of maximum reasonable utilization of the timber unless Contract Area Map shows special areas where stump heights are lower for aesthetic, land treatment or silvicultural reasons.

GT.4.1.3 Limbing. When Forest Service determines it is necessary to minimize damage to the residual stand during skidding, Contractor shall cut exposed limbs from products prior to skidding. Contractor may leave uncut those limbs that cannot be cut with reasonable safety.

GT.4.2 Skidding and Yarding. Methods of skidding or yarding specified for particular areas, if any, are indicated on Contract Area Map. Outside Clearcutting Units and construction clearings, insofar as ground conditions permit, products shall not be skidded against reserve trees or groups of reproduction and tractors shall be equipped with a winch to facilitate skidding.

GT.4.2.2 Landings and Skid Trails. Location of all landings, tractor roads, and skid trails shall be agreed upon prior to their construction. The cleared or excavated size of landings shall not exceed that needed for efficient skidding and loading operations.

GT.4.2.3 Skidding on Roads. Products may be skidded on permanent roads authorized for hauling only by prior written agreement.

GT.4.2.4 Arches and Dozer Blades. Skidding tractors equipped with pull-type arches or dozer blades wider than tractor width or C-frame width, whichever is greater, shall not be used in residual timber outside Clearcutting Units and other authorized clearings, except on constructed tractor roads or landings, unless there is written agreement that residual timber will not be damaged materially by such use.

GT.6.3 Temporary Roads. As necessary to attain stabilization of roadbed and fill slopes of Temporary Roads, Contractor shall employ such measures as outsloping, drainage dips, and water-spreading ditches.

After a Temporary Road has served Contractor’s purpose, Contractor shall give notice to Forest Service and shall remove bridges and culverts, eliminate ditches, outslope roadbed, remove ruts and berms, effectively block the road to normal vehicular traffic where feasible under existing terrain conditions, and build cross ditches and water bars, as staked or otherwise marked on the ground by Forest Service. When bridges and culverts are removed, associated fills shall also be removed to the extent necessary to permit normal maximum flow of water.

GT.6.4 Landings. After landings have served Contractor’s purpose, Contractor shall ditch and slope them to permit water to drain or spread. Unless agreed otherwise, cut and fill banks around landings shall be sloped to remove overhangs and otherwise minimize erosion.

GT.6.5 Skid Trails and Fire Lines. Contractor shall construct cross ditches and water-spreading ditches on tractor roads and skid trails, where staked or otherwise marked on the ground by Forest Service. Forest Service shall designate cross ditching on Contractor-built fire lines prior to or during construction. By agreement, Contractor may use other comparable erosion control measures, such as backblading skid trails, in lieu of cross ditching.

GT.6.6 Current Operating Areas. Where logging, road construction, or other stewardship project work is in progress but not completed, unless agreed otherwise, Contractor shall, before operations cease annually, remove all temporary log culverts and construct temporary cross drains, drainage ditches, dips, berms, culverts, or other facilities needed to control erosion.

Such protection shall be provided, prior to end of November 15 , for all disturbed, unprotected ground that is not to be disturbed further prior to end of operations each year, including roads and associated fills, tractor roads, skid trails, and fire lines. When weather permits operations during Normal Operating Season (May 1st to November 15th), Contractor shall keep such work on any additional disturbed areas as up to date as practicable.

GT.6.7 Erosion Control Structure Maintenance. During the period of this contract, Contractor shall provide maintenance of soil erosion control structures constructed by Contractor until they become stabilized, but not for more than 1 year after their construction. Contractor shall not be responsible for repair of such structures damaged by other National Forest users whose activities are not a part of Contractor’s Operations.

GT.7 Slash Disposal. Contractor’s timing of product removal and preparatory work shall not unnecessarily delay slash disposal. Specific slash disposal measures to be employed by Contractor are stated in elsewhere herein and are in addition to Required Deposits for slash disposal.

GT.8 Measuring. “Measuring” is the estimation of timber quantities using certain dimensions and applicable volume tables or formulae to determine the contents of trees or stands in a standard manner. Sampling may be on an individual tree or area basis. Examples of standard procedures are tree measurement, sample tree measurement, and area estimate. The quantity of timber designated or to be designated for cutting has been or shall be Measured, as specified in this contract

GT.8.1 Product Identification. For contracts west of the 100th meridian, before removal from Contract Area, unless Contracting Officer determines that circumstances warrant a written waiver or adjustment, Contractor shall:

(a) Hammer brand all products that are eight (8) feet or more in length and one-third (1/3) or more sound, on each end that is seven (7) inches or more in diameter

(b) Paint with a spot of highway-yellow paint all domestic processing products that are eight (8) feet or more in length and one-third (1/3) or more sound, on each end that is seven (7) inches or more in diameter. Each paint spot must be not less than three (3) square inches in size.

Contracting Officer shall assign brands and, if Contract Area is within a State that maintains a log brand register, brands shall be registered with the State. Contractor shall use assigned brand exclusively on logs from this contract until Contracting Officer releases brand. Contractor will furnish and apply highway-yellow paint of a lasting quality (oil-base or equivalent).

All hammer brands and/or highway-yellow paint must remain on logs until they are domestically processed.

Contractor shall replace identifying marks if they are lost, removed, or become unreadable. Contractor may remanufacture products into different log lengths. Except for logs remanufactured as part of the mill in-feed process immediately before processing, remanufactured products must be rebranded with the assigned contract brand and repainted with highway-yellow paint, unless otherwise agreed to in writing by Contracting Officer. For such remanufactured products, Contracting Officer may approve use of a brand to be used exclusively as a catch brand, in lieu of the assigned contract brand.

IT.0—OTHER CONDITIONS

IT.1 Title and Liability.

IT.1.1 Title Passage. All right, title, and interest in and to any Included Timber shall remain in Forest Service until it has been cut, removed from Contract Area or other authorized cutting area, and paid for, at which time title shall vest in Contractor. Timber cut under the terms of clause Product Payment Guarantee, shall be considered to be paid for.

Title to any Included Timber that has been cut and paid for, but not removed from Contract Area or other authorized cutting area by Contractor on or prior to contract termination, shall remain in Forest Service.

IT.1.2 Liability for Loss. If Included Timber is destroyed or damaged by an unexpected event that significantly changes the nature of the Included Timber, such as fire, wind, flood, insects, disease, or similar cause, the party holding title shall bear the timber value loss resulting from such destruction or damage; except that such losses caused by insect or disease after felling of timber shall be borne by Contractor, unless Contractor is prevented from removing such timber by the Forest Service. Deterioration or loss of value of salvage timber is not an unexpected event. In the event Included Timber to which Forest Service holds title is destroyed, Contractor will not be obligated to remove and pay for such timber. In the event Included Timber to which Forest Service holds title is damaged, Contracting Officer shall make an appraisal to determine for each species the difference between the appraised unit value of Included Timber immediately prior to the value loss and the appraised unit value of timber after the loss.

Current Contract Rates in effect at the time of the value loss shall be adjusted by said differences to become the redetermined rates.

There shall be no obligation for Forest Service to supply, or for Contractor to accept and pay for, other timber in lieu of that destroyed or damaged. This Subsection shall not be construed to relieve either party of liability for negligence.

IT.5 Sale of Other Materials. Forest Service reserves the right to sell from Contract Area during the period of this contract any materials or products not subject to its terms, but shall not permit removal, possession or use thereof which will materially interfere with Contractor's Operations. Contractor shall not be obligated to do any work made necessary by the action of others.

KT-CT.3.5# - DESIGNATION OF TIMBER, CUTTING UNIT BOUNDARIES, AND SUBDIVISION/PAYMENT UNIT BOUNDARIES (6/2012) Trees are designated for cutting under BT.3.5# only if designated as shown in the Timber Designation table below. The boundaries of Subdivisions/Payment Units and Cutting Units are designated as shown in the Boundary Designation table below. Trees used for boundary designation are not to be cut.

SPECIFICATIONS PURSUANT TO KT-CT.3.5# - DESIGNATION OF TIMBER, CUTTING UNIT

BOUNDARIES, AND SUBDIVISION/PAYMENT UNIT BOUNDARIES

Timber Designation Table

Cutting Unit/ Subdivision/Area/Payme nt Unit

Tree Paint Color

Designation or Specification

ALL Blue Hazard Tree. Notwithstanding BT.3.2 all dead and unstable live trees which are leaning towards a road or are otherwise hazardous to a road, and are sufficiently tall to reach Contractor's landings or the roadbed of National Forest System roads within Contract Area, shall be felled by Contractor when Marked in the specified paint color above and below stump height by Forest Service in advance of felling any other timber in the vicinity. Pieces meeting Utilization Standards from such dead and unstable live trees shall be removed unless Contractor is notified in writing that removal would cause unacceptable damage to areas requiring special protection such as residual timber, roads, administrative sites, streamside management zones, and areas identified on Contract Area Map or on the ground.

N/A Individual Tree Mark. Individual trees are designated for cutting only if Marked above and below stump height with the specified paint color.

All Orange Leave Tree Mark. All Dead < ≥8.0 inch DBH > are designated for cutting unless Marked as leave trees. Leave trees are Marked above and below stump height with the specified paint color. Contract Area Map indicates areas plainly identified on the ground where leave trees are Marked to be left uncut.

N/A Wildlife Trees. Notwithstanding the designation for cutting under BT.3.l, BT.3.3, BT.3.4, or BT.3.5, trees which are identified by standard Forest Service metal wildlife tree sign or painted with the specified paint color on the uphill and downhill side, shall be left uncut. In event such trees are destroyed in Contractor's Operations, Forest Service may designate alternate trees to be saved.

All units Black Marked Out Trees. When it is necessary to delete previously marked trees, an unique tree marking paint color will be Marked over or adjacent to the original mark, but will not obscure the original marking. Trees Marked with the original marking paint color and the unique tree marking paint color are not Included Timber.

Designation by Spacing KT-CT.3.5.1# Designation by Species and Diameter, KT-CT.3.5.2# ALL Designation by Damage Class, KT-CT.3.5.3# Designation by Row Spacing, KT-CT.3.5.4#

KT-CT.3.5.3# – DESIGNATION BY DAMAGE CLASS. (9/04) Within Payment Unit 1, as shown on Contract Area Map, the following criteria are used to designate trees and other products for cutting and removal:

(a) Trees that have 100 percent brown or red foliage and within 1 ½ time there height distance from roads. Also logs that have been previously felled.

(b) Additional trees to be cut, if any, are Marked with BLUE paint.

(c) Cutting unit boundaries and other trees that shall be left uncut are Marked with N/A paint.

Subdivision/Payment Unit and Cutting Unit Boundary Designation Table

Subdivision/Payment Unit Boundary Paint

Boundary Designation

Cutting Unit Boundary Paint

Boundary Designation

Unit 1 Blue Flagging Flagged at 200 Feet distance from the centerline of the road.

Corners shall have multiple flags along with Contract Area Tags.

Unit 2 Blue Flagging Flagged at 150 feet from the centerline of the road. Corners shall have multiple flags along with Contract Area Tags.

KT-IT.6.8# – USE OF TIMBER. (9/04) (a) This contract is subject to the Forest Resources Conservation and Shortage Relief Act of 1990, as amended (16 USC 620, et seq.).

(b) Except for 1/NONE determined pursuant to public hearing to be surplus, unprocessed Included Timber shall not be exported from the United States nor used in direct or indirect substitution for unprocessed timber exported from private lands by Contractor or any person as defined in the Act (16 USC 620e).

(c) Timber in the following form will be considered unprocessed:

(i) Trees or portions of trees or other roundwood not processed to standards and specifications suitable for end product use;

(ii) Lumber, construction timbers, or cants intended for remanufacturing not meeting standards defined in the Act (16 USC 620e); and

(iii) Aspen or other pulpwood bolts exceeding 100 inches in length.

(d) Unless otherwise agreed in writing, unprocessed Included Timber shall be delivered to a domestic processing facility and shall not be mixed with logs intended for export.

(e) Prior to award, during the life of this contract, and for a period of 3 years from Termination Date, Contractor shall furnish to Forest Service, upon request, records showing the volume and geographic origin of unprocessed timber from private lands exported or sold for export by Contractor or affiliates.

(f) Prior to delivering unprocessed Included Timber to another party, Contractor shall require each buyer, exchange, or recipient to execute an acceptable agreement that will:

(i) Identify the Federal origin of the timber;

(ii) Specify domestic processing for the timber involved;

(iii) Require the execution of such agreements between the parties to any subsequent transactions involving the timber;

(iv) Require that all hammer brands and/or yellow paint must remain on logs until they are either legally exported or domestically processed, whichever is applicable; and

(v) Otherwise comply with the requirements of the Act (16 USC 620d).

(g) No later than 10 days following the execution of any such agreement between Contractor and another party, Contractor shall furnish to Forest Service a copy of each such agreement. Contractor shall retain, for 3 years from Termination Date, the records of all sales, exchanges, or dispositions of all Included Timber.

(h) Upon request, all records dealing with origin and disposition of Included Timber shall be made available to Contracting Officer.

(i) For breach of this Subsection, Forest Service may terminate this contract and take such other action as may be provided by statute or regulation, including the imposition of penalties. When terminated by Forest Service under this Subsection, Forest Service will not be liable for any Claim submitted by Contractor relating to the termination.

KT-FT.3.5# – ROAD AND WATER SUPPLY USE. (5/2008) National Forest water supply locations, access, method of filling trucks, period of water availability and procedures designed to maintain water quality at each location shall be agreed in advance of use. Such use shall at no time reduce water supplies to the level that further use may be detrimental to aquatic resources or other established use. Waterholes and other improvements relating to said water supplies shall be put into condition, prior to expected seasonal periods of precipitation or runoff, to avoid resource damage.

Damage to resources at such locations caused by Contractor's Operations, other than fire suppression activities, shall be repaired by Contractor in a timely and agreed manner to the extent practicable to restore and prevent further resource damage.

Unless otherwise agreed, Contractor’s use of roads and other water supply requirements shall conform to the following table.

SPECIFICATIONS PURSUANT TO KT-FT.3.5# - REQUIREMENTS OF ROAD AND WATER SUPPLY USE

Load Limitations Contractor shall notify Forest Service in writing of the planned size and load distribution for equipment which exceeds the State of California Vehicle Code legal size and weight, and the National Forest System roads to be used. Such notice may be part of plan of operation under GT.3.1.1. Within l5 days after receipt of the written notice Forest Service shall notify Contractor in writing of any regulations or restrictions that may be needed to protect National Forest Transportation Facilities.

A written permit shall be required for moving any vehicle which is in excess of the established legal size and weight which is not listed in the above plan, except as may be authorized in prior written agreements.

Existing Non- National Forest System Roads

Roads not shown on Contract Area Map may be used as Temporary Roads if there is agreement before use is started.

Snow Removal

If Contractor removes snow from roads, such work shall be done with Forest Service approval and in a manner that will protect roads and adjacent resources.

Snow berms shall be removed or placed to avoid accumulation of melt water on the road and prevent water concentration on erosive slopes or soils.

Snow must not be removed to the road surface. A minimum < > inch snow depth must be left to protect the roadway. If the road surface is damaged, Contractor shall replace lost surface material and repair structures damaged in blading operations prior to hauling, unless climatic conditions prevent necessary work from being accomplished or as otherwise agreed in writing.

Single lane roads shall be plowed full width including turnouts. In event double lane roads are not plowed to full width, warning signs shall be required and plowing shall be no less than single lane (12 feet) with intervisible turnouts.

Water Supply Deposits

N/A

Surface Replacement Deposits

N/A

KT-GT.3.1.4 - RELEASE OF PAYMENT UNITS. (2/2005) Except for Specified Road Payment Units, Forest Service shall not Release for Cutting more Payment Units than can be logged within 60 calendar days at Contractor's normal rate of logging. Unless otherwise agreed in writing, upon completion of all contract requirements in a Payment Unit, additional Payment Units may be Released for Cutting.

KT-GT.3.1.5# - PROJECT OPERATIONS SCHEDULE. (12/2006) Unless otherwise agreed in writing, Contractor’s Operations shall be performed in accordance with the following schedule:

SCHEDULE PURSUANT TO KT-GT.3.1.5# - PROJECT OPERATIONS SCHEDULE (12/2006)

Subdivision/ Area/Unit

Conditions of Operation

Purpose

Payment Unit 1 Unit 1

No operations from March 1 to June 30 for denning habitat.

Limiting Operation Period (LOP) for Pacific Fisher, KT-GT.3.3.1 - LOG TRUCKING. (2/2005) To promote safe operations on National Forest roads and on Specified Roads, loads shall be safely secured before trucks move from the landing or loading location.

KT-GT.3.7 - SUBSTITUTE METHODS. (2/2005) Notwithstanding other provisions herein, for minor changes such as changes in logging systems for areas smaller than 5 acres, Contractor and Forest Service may agree in writing that use of substitute methods or equipment will achieve Forest Service objectives under this contract and may be used in lieu of those specified for Contractor's Operations.

KT-GT.4.1# - FELLING, BUCKING, AND LIMBING. (8/2007) Unless otherwise agreed in writing, Contractor’s felling, bucking, and limbing operations shall be conducted as specified in the table below.

SPECIFICATIONS AND TREATMENTS PURSUANT TO KT-GT.4.1# - FELLING, BUCKING AND LIMBING

Treatment Method

Felling, Bucking and Limbing Specifications

Limbing

Outside of construction clearings, Clearcutting Units and regeneration units, unless otherwise provided by GT.4.1.3, Purchaser shall, prior to skidding/yarding operations, cut exposed limbs from products which are to be skidded/yarded. Such limbing of stems shall be done to a top diameter of approximately < 3 > inches, at which point the top shall be cut from the remainder of the stem.

Lop

Entire contract area

Whole Tree Yarding

“Whole”

Notwithstanding the requirements above, within units or payment units designated “Whole” on Contract Area Map, trees smaller than < 18 > inches DBH shall be skidded/yarded to agreed landing locations prior to limbing, bucking, and lopping. Trees larger than or equal to < 18 > inches DBH shall be bucked into two or more pieces with the butt portion being no longer than < > feet prior to skidding/yarding. The butt log < shall > be limbed prior to skidding/yarding.

Directional Felling

Within areas designated DF on Contract Area Map, Included Timber shall be directionally felled away from < road drainage structures, trails, distribution lines, improvements listed in KT-GT.2.2# > with the use of specialized equipment. Such directional felling shall not be required when in the faller’s judgment it is unsafe to do so, and shall be left standing.

Treatment of Stumps

N/A

Maximum Log Length

Cut trees shall be bucked prior to skidding so that resulting logs shall not exceed the maximum log length including trim allowance shown in following table:

Unit Number Maximum Log Length

1 & 2 41 feet

Minimum Stump Height

Unit/Subdivision Minimum Stump Height (inches) Purpose or Reason

Contract Area 1.0 inches on the uphill side Accountability

KT-GT.4.2# - GROUND BASED SKIDDING. (12/2006) Unless otherwise agreed in writing, the method of skidding Included Timber shall be as shown on the Contract Area Map, by areas, with symbols defined in the following table:

Ground-Based Skidding Table

- KT-

GT.4.2#Map Symbol

Requirements

TRAC Skid road pattern shall be agreed in advance of felling and main skid roads shall be flagged on the ground in advance of felling. Contractor shall stage-log by felling and skidding Included Timber in two or more separate operations when necessary to prevent undue damage to the resources or residual stand. Needed tractor trails shall be constructed in advance of skidding.

Products shall be end-lined as needed to protect resources or residual timber from unnecessary damage. The number of chokers shall be limited as necessary to avoid unnecessary damage to resources or residual timber. By agreement, tractors may be used to separate products to prevent stain.

SUSP Products shall be skidded with leading end clear of ground.

SPACE Skid roads will average 150 feet from center to center, except where converging.

ENDL Endlining shall not be required for distances in excess of 75 feet uphill, and 125 feet downhill.

MAX Tractors used for skidding outside Clearcutting Units, regeneration units or other authorized clearings, shall be of the type (rubber-tired or track-laying) shown on the Contract Area Map and shall not exceed the overall width designated on Contract Area Map.

MH Contractor shall cut Included Timber and move it to designated skid trails using equipment with a boom having an operating radius of at least 20 feet for bunching trees, capable of severing, lowering and placing trees up to 22 inches diameter at stump height on the ground prior to skidding. Such equipment must be capable of operating on slopes up to 35%.

Notwithstanding above, hand felling using chainsaws may be required in or adjacent to sensitive areas to protect resources from unnecessary damage.

Trees which exceed capability of specified equipment may be felled, bucked and skidded in a manner consistent with the requirements of GT.4.1 - Felling and Bucking, KT-GT.4.1# - Felling, Bucking, and Limbing Requirements and the above “TRAC”, “SUSP”, “SPACE”, “ENDL”, and “MAX” requirements.

KT-GT.5 - STREAMCOURSE PROTECTION. (2/2005) Unless otherwise agreed in writing, wheel or track laying equipment shall not operate within "Buffer Strips" except as necessary for fire suppression activities. “Buffer Strips” are areas marked on the ground or are within the distances identified on the Contract Area Map measured from the apparent high water mark of streamcourses. Boundaries of Buffer Strips may be modified by agreement in writing to meet unforeseen operating conditions.

Culverts, bridges, or other suitable structures shall be required on skid roads and trails only at points where it is necessary to protect Stream courses. The type of crossing structures, method of installation and removal shall be determined by agreement. Contractor in accordance with KT-GT.6 - Erosion Prevention and Control, shall remove such structures and associated fills.

Damage to Stream course or Buffer Strips caused by unauthorized Contractor's Operations shall be repaired by Contractor in a timely and agreed manner to the extent practical as determined by Forest Service to restore and prevent further damage to Stream courses.

KT-GT.6# - EROSION PREVENTION AND CONTROL. (5/2008) Erosion prevention and control work, including Streamcourse protection, required by KT-GT.5 and GT.6 shall be completed within l5 calendar days after skidding operations related to each landing are substantially completed or after Forest Service designation on the ground of work where such designation is required hereunder. Said time limit shall be exclusive of full days lost in Contractor's Operations due to causes beyond Contractor's control. Such on the ground designation shall be done as promptly as feasible unless it is agreed that the location of such work can be established without marking on the ground. After September 15 and as long thereafter as operations continue the work shall be done as promptly as practicable.

Damage resulting from Contractor's Operations due to failure to perform required work shall be repaired by Contractor.

Notwithstanding other provisions in this contract and unless otherwise agreed in writing, any hay, straw, or mulch used in this contract shall be State of California certified weed free.

Additional erosion control requirements of this contract are listed in the following table.

SPECIFICATIONS PURSUANT TO KT-GT.6# - EROSION PREVENTION AND CONTROL.

Vegetative Soil Stabilization Where soil has been disturbed by Contractor's Operations and the establishment of vegetation is needed to minimize erosion, Contractor shall take appropriate measures normally used to establish an adequate cover of grass or other vegetation acceptable to Forest Service or take other agreed stabilization measures. Forest Service shall designate on the ground such disturbed areas annually as logging and Temporary Road construction are completed.

Forest Service upon request shall provide advice as to soil preparation and the application of suitable seed mixtures, mulch and fertilizer and the timing of such work. In no event shall Contractor be required to treat more acres than that shown in the legend of Contract Area Map.

Contractor shall use the type of native seed mixtures, mulch, and fertilizer as listed below:

Seed Mix Pounds/Acre Type of Mulch Fertilizer

N/A N/A N/A N/A

Special Erosion Prevention Measures Contractor shall give adequate treatment by spreading slash or wood chips or by agreement giving other treatment to portion of tractor roads, skid trails, landings, cable yarding corridors, tractor-end lined corridors and Temporary Road fills where necessary to supplement other erosion prevention measures required elsewhere in this contract. In no event shall Purchaser be required to treat more acres than that shown in the legend of Contract Area Map. The specific locations to be treated shall be designated on the ground by Forest Service. These special erosion prevention measures are to be done within the same date and time periods as stated above.

Areas of increased waterbars (decreased waterbar spacing) Maximum Acres to Treat

Skid Roads and Tractor Roads designated by Forest Service where skid trails are parrallel to SMZ within 25 feet of flagged SMZ boundary, or on skidtrails from or within a distance of 50 feet from SMZ boundary.

Areas of equipment restriction or specified equipment Maximum Acres to Treat

Required slash piling on slopes exceeding 15% will require grapple piler or manual piling. N/A

Soil Scarification. In addition to meeting the requirements of GT.6.3 and GT.6.4, Contractor shall scarify the following areas; unless otherwise agreed:

(a) Traveled Way of National Forest System roads used by Contractor and listed in the legend of Contract Area Map.

(b) Roadbeds of any Temporary Roads used for log hauling by Contractor.

(c) Landings or portions thereof located outside Roadbed limits of National Forest System roads not designated for scarification.

Scarification shall be to a depth of 6 inches, with intervals between striations not to exceed l2 inches, unless otherwise agreed.

Backblading Within recreation development sites and public use areas designated on Contract Area Map, Purchaser shall, at Forest Service request, backblade skid trails in lieu of cross ditching.

KT-GT.7# - SLASH TREATMENT. (12/2006) Contractor shall pile, scatter, yard, construct firelines or otherwise treat slash defined in specifications below, within designated areas. Work required of Contractor shall be in accordance with the following slash plan and specifications, and the Contract Area Map.

All vegetative debris associated with construction of Specified Roads such as unutilized timber, brush and grubbed stumps is Construction Slash. Measures to be taken by Contractor for treatment of Construction Slash are set forth in the attached road construction specifications and in the attached slash treatment specifications.

Vegetative debris larger than 1 inch in diameter outside bark and 3 feet long resulting from Contractor's Operations, other than Construction Slash, is Logging Slash. Measures to be taken by Contractor for treatment of Logging Slash are set forth below unless otherwise agreed in writing.

Forest Service and Contractor shall jointly develop a schedule for completion of slash treatment on the various portions of Project Area prior to Contractor's Operations.

Removing may be substituted for treatment of any other specified method.

By agreement in writing, certain slash may be left for fuelwood. When the specified treatment is by a combination of methods, Logging Slash not treated by one of the methods shall be treated by the other(s).

See the slash treatment specification table below.

SPECIFICATIONS PURSUANT TO KT-GT.7# - SLASH TREATMENT (12/2006)

Specified slash treatment methods shall be shown on Contract Area Map or listed in the following tables by the following symbols:

Slash Treatment Methods

Symbol Method Definition Buck-L “Bucking Large Logging

Slash” Tops and limbs over 4 inches diameter outside bark (d.o.b.), not to be otherwise treated, shall be bucked into lengths not to exceed 6 feet, unless agreed otherwise.

Mach "Machine Piling" Concentrations of Logging Slash, excluding scattered individual pieces, shall be Machine Piled by tractor equipped with brush rake for disposal by Forest Service.

Pile "Piling" small material Logging Slash smaller than <> inches in large end d.o.b. and <> feet long shall be hand Piled for disposal by Forest Service.

Fell “Damaged Small Tress” Unless treated under other provisions, all trees smaller than the minimum d.b.h. in AT.2, over 5 feet in height, and damaged beyond recovery by Contractor's Operations shall be felled. Such trees shall be limbed to a stem diameter outside bark of approximately 3 inches, at which point the top shall be cut from the remainder of the stem, and shall be bucked into lengths not exceeding 20 feet.

PILING…