Attachment_02-SanpeteBunkhouse.Specifications.Final.1.11.2017.docx

DOCX document 366 KB Posted

Attached to
Sanpete Bunkhouse Construction with Utilities Federal contract opportunity
Solicitation number
AG-84N8-S-17-0012
Issued by
Department of Agriculture Forest Service R4-Intermountain Region

About this file

Attachment 02 - Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Sanpete Bunkhouse Construction with Utilities, newest first.
File Type Posted
Scanned_Amendment_04.pdf PDF
Scanned_Amendment_03.pdf PDF
Scanned_Amendment_02.pdf PDF
Scanned_Amendment_01.pdf PDF
Attachment_01-SanpeteBunkhouse.Drawings.Final.Signatures.1.11.2017.pdf PDF
Sol_AG-84N8-S-17-0012.pdf PDF
Attachment_03_-_Wage_Determination.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

SANPETE BUNKHOUSE

Final– 1/11/2017

SCOPE OF CONTRACT

This project consists of the installation of a new modular housing unit at the Sanpete Ranger District Office Administrative Site on the Manti-Lasal National Forest. The project includes the following Bid Items.

Base Bid Work includes the following:

Construction work includes the following items:

Installation of new utilities and modification of existing utilities as required in the drawings and specifications, including water, sewer, natural gas, and electricity. Exterior cable and telephone will be done by others.

Installation of the bunkhouse on a concrete foundation, all HVAC systems, and a complete and finished building as shown in the drawings and specifications. Installation of the bunkhouse shall include utility connections.

Site clearing and grubbing and grading, installation of concrete sidewalks, curb and gutter, concrete pads, and signs as shown in the drawings and specifications.

Removal of portions of existing fence as shown on the drawings.

Work includes construction staking for the base bid and any and all option items awarded.

“Bid Option “A” work includes the following as shown in the schedule of Items:

Installation of asphalt parking and roadways as shown in the drawings and specifications Quantities associated with these options are identified in the Schedule of Items.

PROJECT LOCATIONS

The project is located at the Forest Service Sanpete Ranger District Office Administrative Site. The Administrative Site is located in the city of Ephraim Utah at 540 South Main, Ephraim, UT 84627, via Hwy 89.

SITE INFORMATION AND LIMITATIONS

The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

Construction sites will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access with fencing.

All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations. Do not offload heavy equipment prior to inspection.

Utilities are available at the site for construction purposes. The Contractor will be responsible for coordinating the use of utilities with the COR.

The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.

TRAFFIC CONTROL AND CONSTRUCTION SIGNING

No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Idaho Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

WORK CAMPS, STAGING AND STORAGE AREAS

Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work) on site.

No overnight camping will be allowed on site.

INSPECTION OF WORKSITE

The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

START DATE

May 2017

CONTRACT TIME

Base Bid: 180 Calendar Days

SPECIFICATIONS

The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

Section 000050 - Modular Unit Section 010250 - Construction Staking Section 011250 - Measurement And Payment Section 011900 - Mobilization Section 013300 - Submittal Procedures Section 014100 - Quality Control Section 023701 - Sediment And Erosion Control Measures Section 033000 - Cast-In-Place Concrete Section 061000 - Rough Carpentry Section 061600 - Sheathing Section 061753 - Shop-Fabricated Wood Trusses Section 064023 - Interior Architectural Woodwork Section 071113 - Bituminous Dampproofing Section 072100 - Thermal Insulation Section 074113 - Metal Roof Panels Section 074600 - Siding Section 076200 - Sheet Metal Flashing And Trim Section 079200 - Joint Sealants Section 081113 - Hollow Metal Doors And Frames Section 081416 - Flush Wood Doors Section 087100 - Door Hardware Section 092900 - Gypsum Board Section 096520 - Sheet Vinyl Floor Coverings Section 096530 - Resilient Wall Base And Accessories Section 097200 - Wall Coverings (Fiberglass Reinforced Plastic (Frp) Panels) Section 099113 - Exterior Painting Section 099123 - Interior Painting Section 099300 - Staining And Transparent Finishing Section 101400 - Exterior Signs Section 102800 - Toilet And Bath Accessories Section 113100 - Residential Appliances Section 122113 - Horizontal Louver Blinds Section 211313 - Fire Sprinkler System Section 221100 - Water Distribution Systems Section 221102 - Curb Valves And Boxes Section 221116 - Domestic Water Piping Section 221119 - Domestic Water Piping Specialties Section 221300 - Sewer Systems Section 221316 - Sanitary Waste And Vent Piping Section 221319 - Sanitary Waste Piping Specialties Section 223300 - Electric, Domestic-Water Heaters Section 224100 - Residential Plumbing Fixtures Section 230529 - Hangers And Supports For Hvac Piping And Equipment Section 231123 - Facility Natural-Gas Piping Section 260500 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260526 - Grounding And Bonding For Electrical Systems Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 262416 - Panelboards Section 262726 - Wiring Devices Section 262816 - Enclosed Switches Section 312000 - Earthwork Section 312100 - Project Site Preparation And Grading Section 312225 - Excavation & Embankment Section 321200 - Hot-Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 322640 - Pavement Marking

END OF SECTION C

Dec 2016

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1

USDA FOREST SERVICE, R4

SANPETE BUNKHOUSE

SECTION 000050 - MODULAR UNIT

1. GENERAL

SUMMARY

This item shall consist of the supply and installation of modular buildings and demolition of structures as follows.

Base Bid Item 000050-1:

Accessible Modular Bunkhouse Building minimum 1092 sq ft., including utility connections The building shall be constructed from approved building plans developed by the successful bidder in accordance with these specifications. Floor plans and elevations shall be similar or equal to the given floor plans from the Forest Service. The proposed building shall include a new permanent concrete foundation. Necessary site grading, structural excavation, backfill and connections to utilities (Water Sewer, Power, Natural Gas) are included in the building cost. See drawings for site utility improvements. The proposed building shall include items listed as appliances, shown plumbing fixtures, Heating and Air Conditioning, doors and hardware, cabinets, and other items shown on plans, except for those items shown as N.I.C. (Not In contract) in the drawings. All floor areas shall be defined as the gross areas within the exterior face of exterior wall lines. All units shall be placed on concrete footings and foundation where the top of the foundation walls are a minimum of 6” higher than finished exterior grade. Bottom of footings shall be a minimum of 4.5 feet lower than the top of the foundation wall.

The Modular Bunkhouse Building shall meet all 2004 ADA/ABA Guidelines.

The buildings shall be designed, constructed, and installed in accordance with the Codes referenced in paragraph 1.3, below.

MEASUREMENT AND PAYMENT

000050-1: The quantity to be measured shall be "Lump Sum Quantity" (LSQ) as shown on the Schedule of Items for the listed modular building, completed, installed, accepted, and ready for use. Payment shall be at the contract unit price as shown on the Schedule of Items. The measurement for the modular buildings shall include all work items including utilities, excavation, back-fill and grading extending outside those limits to 15 feet outside the building.

REFERENCE SPECIFICATIONS

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

2015 International Building Code 2015 International Plumbing Code 2015 International Mechanical Code 2015 International Fuel Gas Code 2009 International Energy Conservation Code 2014 National Electrical Code 2014 National Fire Protection Association Standards 13D.

2004 Americans with Disabilities Act/Architectural Barriers Act Guidelines (ADA/ABAG) (http://www.access-board.gov/adaag/html/adaag.htm)

PRODUCTS AND EXECUTION

GENERAL - The bunkhouse units shall be configured in accordance with the following specifications:

Submitted Floor Plans and Elevations shall be similar or equal to the provided drawings for each Modular Unit, and shall be designed in consultation with the Contracting Officer. Overall square footages of the buildings shall be a minimum of what it listed above. If alternate floor plans are submitted that are different than the government supplied plans, the Contractor shall provide building plans that will fit within the allowed areas for the buildings shown on the site plan supplied by the government. Contractor shall also coordinate the location of utility line connections for the buildings with the location of the existing utilities shown on the utility site plan. The bunkhouse shall be in full compliance with the 2015 International Building Code for R-3 occupancy, congregate living facility and will include installation of an NFPA 13D compliant fire sprinkler system. See paragraph 2.8 below for additional fire sprinkler system requirements.

The contractor shall submit a professionally prepared preliminary design (floor plan and elevations) to the Contracting Officer for approval within (2) weeks after the Notice to Proceed.

Upon approval of the preliminary design by the Forest Service, the Contractor shall submit five (5) full sets of drawings as indicated below, and design calculations to the Contracting Officer for approval through the Region 4, Director of Engineering within (4) weeks after approval of the preliminary design.

The detailed drawings shall include:

Complete construction details and schedules for the building.

Foundation plan and details.

Framing plans and details for porches and covers for entries and ramps.

Plans and details for ramps.

Mechanical plans showing equipment.

Plumbing plans, showing all waste and vent piping, water piping and their sizes, location of water heaters, their make, model and specifications.

Fire sprinkler plan showing riser, layout and equipment, and flow calculations.

Cut sheets for appliances and equipment, demonstrating Energy Star compliance.

Electrical plans, showing all panel and lighting schedules, device locations, circuitry, makes, models, and specifications.

Finish grading plan that shows grading and drainage around building and at concrete pads.

IECC 2015 Residential Energy Conservation Code Check. See Section E below.

The drawings shall be stamped by an Engineer or Architect, licensed in the state the building will be installed.

Upon final approval of the drawings by the Contracting Officer, the Contractor shall submit to the Contracting Officer 2 full sets of stamped, original, 24 inch by 36 inch (D-size) reproducible drawings, and an electronic copy on CD (in DXF or DWG file format) along with 4 sets of the final working drawings on 22-lb bond.

Unless noted otherwise below, all appliances, fixtures, and component parts or details not specifically covered by these specifications shall be those which are considered standard or better quality for commercial home building use, be energy star rated, or as approved by the Contracting Officer.

This building shall be designed to exceed the International Energy Conservation Code (IECC), 2015 for multi-family residential construction. The Government is required to save an additional 30 percent energy use over International Energy Conservation Code (IECC), 2015 Supplement Edition as is cost effective. Compliance shall be demonstrated by providing detailed reports from software such as ResCheck (current version) or similar software. All energy related requirements identified throughout this specification are intended to be mandatory. The following required report shall show that the energy performance above code requirements have been met.

Building envelope, including construction assembly (i.e. walls, ceiling/roof assemblies, floor assemblies, foundations), and windows and doors.) The Compliance Certificate as generated by REScheck meets this requirement.

Address mandatory compliance requirements of the IIEC for envelope and systems noted in the checklists for REScheck.

Modular Bunkhouse Units shall be designed with the following areas and requirements:

Three each, minimum 120-square foot, bedrooms. In the Building one bedroom shall be fully ADA/ABAG compliant (accessible). See Drawings Two toilet and shower rooms with the following components: floor mounted tank toilet, toilet paper dispensers, towel hook, towel bar, toilet seat cover dispensers, mirror unit, soap dispensers, wood framed, laminate covered countertop with top mounted lavatories, faucet, hand dryer, a prefabricated 36” x 36” shower units, with soap dish, mixing valve and shower head, cubicle framing and finishing, stainless steel curtain rod and anti-microbial curtains.

In the Building, one of the two bathrooms shall be fully ADA/ABAG compliant (accessible). Accessible fixtures shall be provided in this bathroom. See Drawings. There shall be one common use accessible toilet room with the following components: One floor mounted toilet, 42”, 36”, and 18”stainless steel, wall mounted grab bars, toilet paper dispenser, toilet seat cover holder, wood framed, laminate covered countertop with top mounted lavatory and faucet, soap dispenser and anti-scald drain guard. See ADA/ABA Accessible guidelines for any additional requirements.

A common kitchen of approximately 150/SF to accommodate range/ovens as shown on the plans, 1-sink, refrigerators, freezers, or refrigerator/freezer combinations as shown on the plans, one dishwasher, and a minimum of 14-linear feet of 24-inch deep countertops including 1-double sink, and an 8’-foot island with an 6-foot eating counter (30-inches above finished floor) located on the dining room side of island. Provide a minimum 12’ of 28” high by 12” deep upper cabinets. Provide 1 countertop microwave unit. See the appliance specifications.

Approximately 180/SF dining/common use area. This space shall be open and adjacent to the recreation/living area, and shall include a laundry closet. Provide a continuous decorative wood chair rail around the room to protect the wall.

Mechanical closet to accommodate water heaters, fire riser, and furnace. Heating shall be a natural gas furnace. See paragraph 2.6 and 2.7 below for mechanical requirements and additional information. Floor drains shall be installed to accommodate drain lines. Provide an area for housing the fire sprinkler support equipment for the building including any required booster pump for building water supply may be located in this room.

Finishes of Walls and Ceilings All interior wall finishes shall be “light orange peel” textured, semi-gloss painted 5/8 inch type-x gypsum board with rubber cove base. Ceiling finish shall be textured, painted gypsum board. Wall finishes in bathrooms and adjacent to showers shall be a 3’ tall tile wainscot. Wall finishes in mechanical room shall be Fiberglass Reinforced Plastic wainscoting (FRP) over 5/8 inch waterproof type-x gypsum board. IBC requirements for fire partitions and corridor fire resistance for R-3 occupancy are required.

Colors:

Exterior and Interior colors shall be as selected by the Contracting Officer’s Representative from the full line of products available for the materials specified:

Doors and Hardware:

All interior doors shall be flush, birch veneer, solid core, a minimum of 1 ¾” x 3’-0” x 6’-8”. All interior hardware shall have levered handles, and shall meet ADA/ABA accessibility Guidelines. Interior doors to bedrooms shall have lever handled, separately keyed, entrance locksets with a privacy type deadbolt keyed to match each entrance lockset. All interior locksets/deadbolts shall be master keyed to all exterior and other keyed door hardware. Doors to bathrooms shall have lever handled bathroom type privacy locksets. Water heater closet doors may be narrower, but must be sized to allow service and replacement of units.

All exterior doors shall be 1-3/4 inch thick x 3-feet wide x 6-feet 8-inches tall insulated metal doors with closers and with half light. All exterior door hardware shall meet ADA requirements and have a satin chrome or satin stainless steel (US26D or US32D) finish. Provide wall mounted 8-inch by 15-inch minimum, red photo luminescent exit signs centered above interior trim on every exterior door. Exterior doors shall have lever handled entrance locksets and deadbolts. All keyed exterior entry locks shall be keyed alike and shall be provided with 20 standard keys and 2 Access Bow Keys.

Kitchen:

Kitchen cabinets shall be provided in compliance with Specifications Section 064023 Interior Architectural Woodwork. Provide a minimum of 14-lineal feet of countertops with 4-inch backsplashes for base cabinets in kitchens and laundry room and wall hung countertops for restrooms. Provide 6 LF of Upper cabinets. Provide 4x8 ft island countertop with wider profile, and 30” high eating area as shown on the drawings. Provide approximately 5 lineal feet of upper wall cabinets in laundry area.

See Architectural Drawings for Preferred Layout of Kitchen and Cabinetry.

Exterior Front Entryway and Ramp:

All required handrails, guardrails, and railing shall painted steel components railing shall meet IBC code requirements and be installed per 2004 ADA/ABAG requirements including proper termination at top and bottom of ramps.

Building elevation must be set to reduce the need for stairs and minimize runs of ramps. All exterior landings at doors and bottom of ramps shall be a minimum of 5-feet square. Top landings shall be installed to match finish floor elevation of bunkhouse unit with only slight slope from building to drain. (i.e., maximum elevation differential between landing and top of door threshold shall not exceed ½ inch.). Ramps shall be a minimum of 36-inches clear width and any intermediate landing with a change in direction from the ramp shall be a minimum of 42-inches wide. Ramp shall be constructed and equipped in accordance with 2004 ADA/ABAG and have a maximum slope of 1 in 12 with a maximum rise of 30-inches between landings. Ramp and landing areas shall be equipped with guardrails/handrails as per ADA/ABAG.

BUNKHOUSE BUILDING – The following construction requirements shall apply:

Roof, Soffits and Fascia Construction Roofing shall be PBR metal roof panels, see specification, meeting requirements of specification Section 074113, with 6-feet wide ice dam membrane installed over roof sheathing at eaves and valleys, and 3-foot wide ice dam membrane at ridges and gables. Roof pitch shall be not less than 4 in 12, with all overhangs 24-inches minimum. All roof penetrations shall be made within 24-inches of the ridge of the roof and shall be painted to match roof color. Attic ventilation shall be installed on the roof gables and continuously in soffits. Fascias shall be steel and match roofing in color and material. Roof trusses must be an energy truss style to maximize energy efficiency. Provide R-49 Roof pitch shall be not less than 4 in 12, with all overhangs 24-inches minimum. All roof penetrations shall be made within 24-inches of the ridge of the roof and shall be painted to match roof color. Attic ventilation shall be installed on the roof gables and continuously in soffits. Soffits shall be vented fiber cement board soffits. Fascia shall be fiber cement board with a smooth finish. All Fiber Cement board shall be installed per manufacturer recommendations, and colors shall be selected by COR from manufacturer full range of color. Roof trusses must be an energy truss style to maximize energy efficiency. Provide R-49 insulation.

Siding and trim material shall be as follows:

Horizontal Siding shall be a fiber cement composite lap siding with an 7-inch exposure, with a minimum 15 year factory applied finish, color as selected by the Contracting Officer. Horizontal Siding shall not have continuous vertical joints at adjoining building modules.

Vertical Siding shall be a Fiber Cement Board and Batten as shown in the drawings with a minimum 15 year factory applied finish.

Trim shall be a minimum of 1 1/4-inch thick approximately 6-inches, and 4-inches wide and be cement composite material matching siding. Trim shall be factory primed and receive a minimum of 2-finish coats of paint or have 15 year factory finish as described above. Windows shall have a 4” trim border. All corners of the buildings shall receive vertical trim pieces, installed to butt up against each other. All nail holes shall be painted and covered with Manufacturers supplied matching paint and color. All cut edges shall receive the same number of coats as the factory finished fiber cement board product.

Except for the accessible restroom, the lavatories shall be mounted in a plastic laminate countertop with a 4-inch high backsplash. Accessible lavatory shall be wall mounted. Toilets shall be elongated bowl, 1.2 gallon or less per flush type with pressure assist flushometer tank with tank lever located on accessible side of tank or push operators located centered on tank lid.

Finished floors shall be covered with commercial grade, sheet resilient floor covering or tile as described in the drawings. Sheet flooring shall be per specification Section 096520 Resilient Floor Coverings. Tile shall be as per specification Section 093000 Tiling. Wall base shall be per specifications Section 096530 Resilient Wall Base and Accessories. Resilient floor transition strips shall be ADA/ABAG compliant vinyl or rubber. Submit sample of transition strips for approval by Contracting Officer.

Shower surrounds shall be waterproof (acrylic, or fiberglass), a minimum of 36-inches square. Accessible shower shall be fully ADA/ABAG compliant, including a removable, fold-down shower seat, grab bars, and shower curtain. Floor drain shall be installed centered in front of access to accessible shower. Non-accessible showers shall be equipped with shower doors. All shower units shall be equipped with anti-scald type, lever-handled shower valves, soap dish, and shelf (integral or mounted type).

The bunkhouse shall be insulated with the following minimum resistance rating:

WallsR-21
Ceilings/roof (energy truss required)R-49
FloorsR-15 for slab

R-30 for crawlspace floor.

Foundation walls R-15 Exposed water piping in crawlspace Minimum 3” pipe insulation.

An extra furring wall and insulation shall be provided at all locations where piping is placed in exterior walls. See Bathroom, Laundry and Kitchen Layouts All windows shall be sliding style, fully weather-stripped, double-glazed, low-E, elevation adjusted and argon filled. Windows shall be rated highly for use in high wind areas. Windows shall be fiberglass framed windows. Glazing in bathrooms shall be double-glazed obscure type.

Basis of Design Window:

Pella Impervia Fiberglass Windows.

Color: as approved by COR from Manufacturers full range of colors.

Windows shall be installed per manufacturer’s recommendations.

Provide fiber 3-1/2” wide fiber cement trim around all windows.

Windows located in bedrooms shall be sized and located for egress requirements per 2015 IBC. Provide 1-inch horizontal metal blinds for each window except bathroom windows per specifications Section 122113 Blinds.

APPLIANCES - The following appliances shall be furnished and installed of one color, chosen by the COR. See Appliance Specification 113100 for Basis of Design Products.

Install Freestanding electric range/oven with temperature-controlled self-cleaning bake oven with glass oven door, and four burners. Matching, exterior vented, range hood shall be supplied for range/oven and cook top. Range/oven shall be equipped with front controls for ADA requirements and may be a drop-in type unit.

Install cooktop stove with Island overhead hood in kitchen. See Appliances specification for more information on product and style. Cook top and Island Overhead hood shall be installed per manufacturer’s recommendations.

Range and overhead hood for cooktop shall be fully vented to exterior, a minimum 160 CFM fan capacity, with light. Color shall match range/oven. See electrical requirements paragraph 2.7D for required location of controls on the accessible range hood.

One each high energy efficiency (Energy Star Rated), full size upright refrigerator without freezer unit (25-cubic foot minimum capacity).

One 21 cubic foot capacity upright freezer. (Energy Star Rated).

One dishwasher, large capacity, high energy efficiency (Energy Star Rated), simple accessible controls, water saver model.

One clothes washers shall be large capacity, front loading, water saving washers, energy efficient (Energy Star Rated), and simple controls. The manufacturer of washer shall match the manufacturer of the dryer, See 113100, Residential Appliances.

One electric dryers shall have auto dry cycle (i.e. senses moisture content), minimum 7 cubic foot capacity. Electric Dryer shall be front loading. Controls for washers and dryers must be front mounted. The manufacturer of dryer shall match the manufacturer of the washer.

Microwaves: Provide 1 each 1.7 CU capacity microwave with turntable, 1000 Watts, stainless finish.

STRUCTURAL

Basis of Design Structural Requirements are as follows:

Governing Building Code: International Building Code (IBC) 2015 Risk Category 2 Suspended Floor Loads:

Live Load = 40 PSF Dead Load = 30 PSF Roof Loads:

Flat Roof Snow Load, PF: 45 PSF Ground Snow Load, PG: 48PSF Snow Exposure Factor, CE: 1.0 Snow Load Importance Factor, IS: 1.0 Thermal Factor, CT:1.2 Live Load = 20 PSF Dead Load – 20 PSF Wind Design:

Basic Wind Speed (3 Second Gust); 115MPH Wind Exposure: C Component and Cladding Design Wind Pressure shall be as required per ASCE 7-10.

Seismic Design:

Seismic Importance Factor, IE: 1.0 Site Class: D Seismic Category: D Foundation:

Design Soil Pressure 2,000 PSF The modular building shall be set on a permanent, engineered concrete foundation wall system with concrete footings at a minimum 48 inches below grade, and 6 inches minimum below frost line, set into the ground to minimize ramps and stair access into the building. Foundation footings shall not be placed over disturbed soil. Design and construction of the bunkhouse foundation shall conform to the 2015 International Building Code and meet all seismic requirements of this code. Top of foundation wall shall be 6” above grade.

Engineered, stamped drawings and calculations for the building foundation, required hold downs, required roof structures, ramps and ramp footings shall be submitted for approval by the Contracting Officer as part of the plan review process.

Provide Foundation ventilation. Vents shall be the automatic type closing at approximately 40 degrees F and opening fully at approximately 70 degrees F. Locate foundation vents to meet IBC requirements and protect well openings from precipitation, irrigation, and roof shedding.

All concrete and concrete placement shall be in accordance with Section 033000.

The bunkhouse building module shall not be placed on the building foundation until the foundation construction is approved in writing by the Contracting Officer.

SITE WORK

See the Utility Site Plan for correct orientation of the building and locations of utilities. Contractor shall verify utility locations for building supplied. See Utility Site Plan for required site improvements including concrete pads and walkways. Accessible walkways shall provide an accessible route from accessible entrance to accessible parking, including direct access (i.e. shortest distance possible) to the accessible parking space.

Provide a continuous, approximately 24 inch wide, gravel drip bed at all drip lines around building which extends from face of building foundation to just beyond drip line of roof eaves. Gravel size shall be 3/8” crushed.

MECHANICAL:

Please see the Civil Engineering drawings for the configuration of the water supply lines for domestic service and the required fire protection system.

Both hot and cold water and water shall be supplied to each sink, lavatory, shower, and service sink and washing machine. Cold water lines and fixtures shall be supplied to each water heater, water closet and to two freeze-proof-type hose bibs (front and rear) for the unit. The water system in the building shall be designed for easy winter shut-down of the building including drainage of all water piping. Provide Shrader valve connection in mechanical closet to blowout all piping for winterization. The Contractor shall provide a written plan in the required O&M manual, per paragraph 2.10A below, containing the building water system shut-down and startup procedures for the building. The water service line shall be connected to the proposed water system as shown on the Site Plan. It is requested that the contractor utilize alternative water piping materials that are freeze resistant such as PEX. Provide drain lines and venting required by code. Consolidate waste venting to minimize roof penetrations and place roof penetrations within 2 feet of the roof ridge.

Provide central air and heat via furnace, coil and condenser with duct supply and return lines. Provide air conditioning.

Water supply and Drain, Waste and Vent piping shall be designed and installed in conformance with the International Plumbing Code, and State and local codes, which ever is more stringent.

Kitchen shall have 1 stainless steel double sinks with lever style faucet controls with separate or integral sprayer. One sink shall have one bowl with a maximum 6-inch depth and installed in countertop to meet ADA/ABAG requirements.

ELECTRICAL

The unit shall be provided with a complete and operable electric system, including service lateral conduit, load center, grounding, boxes, branch circuits, and all devices as called for in these specifications (pumps, HVAC, etc.).

Electrical layout shall be 2014 National Electrical Code residential style with 20-amp circuits minimum, except as shown in drawings. Provided is electrical layout drawings that show minimum requirements based on layout.

The Contractor shall be responsible for coordinating installation of electrical service and obtaining any and all electrical permits and paying service fees and other fees associated with the permits or obtaining service.

Accessible Range hood Range hood shall be connected for accessibility as follows:

Disconnect factory switches for light and fan, leaving the automatic fan (turns on during high heat) connected. Label "Controls on front of cabinet."

Install a dual switch on a single yoke to the front of the cabinet as shown in cabinet details.

Factory label or other acceptable means the switch cover so the top switch is labeled "light" and the bottom switch is labeled "fan".

Install the range hood light (high, not night light) on the top switch. The night light function will not be connected.

Install the range hood fan on high on the bottom switch. The low fan function will not be connected.

Install the range hood fan high ambient temperature function on an always hot line from the switch.

Fire Pump for Fire Sprinkler System (if required by sprinkler design) The branch circuit to the fire pump panel shall be routed outside the building, either below the siding or buried 12" minimum.

IMC or Rigid Steel Conduit is required for the entire length to the fire pump disconnect.

The overcurrent device shall be sized to carry the locked-rotor current of the fire pump motor and associated equipment indefinitely.

The fire pump panel and disconnect shall both be labeled "Fire Pump Disconnect" in letters at least 1" high, visible without opening enclosure doors or covers.

Telephone Provide telephone outlet and connection as called for. No service at this time shall be included.

Water Heater Tank: Provide 50 gallon water heater tank Basis of Design Product:

A.O. Smith ProMax 50-Gallon Electric Water Heater or approved equal Model ECT-52 4500 watts, Energy Factor 0.91

FIRE SPRINKLER SYSTEM

The system design shall meet the requirements of 2007 NFPA 13D standards plus specifications section 211313 fire Sprinkler System and the following requirements/design considerations:

All sprinkler heads shall be concealed.

Sprinkler system water flow shall be integrated with the plumbing system by way of circulation loop(s), so the plumbing and the sprinkler can be drained and winterized together.

The system must be designed to operate with or without a building water supply with a dynamic/fire flow of 20 pounds per square inch (PSI) minimum/56 gallons per minute (GPM). Building water supply will be shut down during winter months, but fire protection must still function. See paragraph 2.6 and coordinate for required pressure requirements. System may be designed to be supplied by a pump/tank combination listed for use in an NFPA 13D fire sprinkler system.

Piping system shall be installed and concealed in crawlspace and walls. Heads shall be installed in walls to allow for drainage, and possible winterization. Piping may be installed exposed only in mechanical rooms or fire equipment room.

BATHROOMS AND MISCELLANEOUS

Bathroom accessories shall include the following:

Bathrooms:

Dual-roll toilet paper dispenser, wall mounted soap dispenser (at lavatory), 1-coat hook (54-inches maximum above finished floor), 42”, 36” and 18” stainless steel grab bars (accessible bathroom), 24” x 36” mirror, toilet seat dispenser, stainless paper towel dispenser for folded paper towels.

Under Kitchen Counter Fire Extinguisher:

1 10 lb residential fire extinguisher.

OPERATIONS AND MAINTENANCE MANUAL

Provide a complete, bound operations and maintenance manual upon completion of project. Manual shall include manuals for all equipment installed, including operation, maintenance, and users guides, separated with labeled, tabbed dividers, by equipment. A maintenance chart shall be included listing all equipment and indicating maintenance required on a monthly, quarterly, semi-annual, and annual basis for each piece of equipment installed. O&M Manual shall have a cover sheet with the building name, date of project completion, and full name and address of the prime contractor and names and addresses for all sub-contractors/installers of equipment included in manual.

EXECUTION

GENERAL

Work shall be completed in accordance with the contract drawings and specifications.

END OF SECTION

Dec 2016

MODULAR UNIT 000050-10

USDA FOREST SERVICE, R4

SANPETE BUNKHOUSE

SECTION 010250 - CONSTRUCTION STAKING

1. GENERAL

SUMMARY

This work shall consist of the construction staking for: paths, buildings, and utilities in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.

QUALITY CONTROL

Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.

MEASUREMENT AND PAYMENT

Measurement shall be lump sum for surveying and staking the project through all phases of construction.

PRODUCTS

GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS

The Government will provide the contractor with a set of survey control sheets showing horizontal and vertical control for site to be staked. The Government will provide the Contractor with layout information that will include:

Control Points - Northing, Easting, Existing Elevations.

Paths, - Northing, Easting, and Finish Elevations, no points will be provided for stairs.

Buildings - Northing, Easting, Finished Floor Elevations at corners of buildings.

Utility Lines – No points will be provided for utilities due to short lengths of the laterals. Contractor shall field stake utilities based on plans. Propane tank slab shall be staked in the field no closer than 10 ft from the building by the contractor and accepted by the COR prior to placement of concrete.

STAKES

Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:

Waterlines, utilities, and culverts-Blue
Roads, parking lots, and sidewalks-Orange
Buildings, excavation and grading-Yellow

SURVEY NOTE PAPER AND BOOKS

Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.

EXECUTION

GENERAL

The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract. The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.

Accuracy requirements:

Minimum position close; 1/1000 Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal) Cross section and slope stake precision:

Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.

Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross section points will not exceed: 1.0 ft.

Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%. Clearing limits: 1.0 ft.

ESTABLISHING AND REFERENCING IMPROVEMENT LOCATIONS

Waterline, Sewerline, & other Utilities Waterline, Sewerline, & other Utilities shall be staked at the locations shown on the drawings with the specified minimum burial depth. Waterline and sewerline elevations shall be accurately staked to provide for drainage as indicated on the drawings. Grade stakes shall be established as necessary to provide the control for the construction work.

Buildings Slope stakes and slope stake references shall be established at each corner and as necessary to provide adequate construction control.

DISCREPANCIES

The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.

VERTICAL CONTROL

Vertical control for construction shall be as referenced on the Drawings.

MARKING STAKES

All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;

PIPoint of Intersection of tangents
PCPoint of curvature
POCPoint on curve
PtPoint of tangency
POTPoint on tangent
RPReference point
PP-line (preliminary location line)
LL-line (final location line)
BMBench mark
TBMTemporary bench mark
BTBegin taper (any)
ETEnd taper (any)
CCut
FFill
LCenterline
DDitch
WWidth

SURVEY NOTES

All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.

Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey was performed, and survey data or sketched that cannot be electronically recorded. The party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.

END OF SECTION 010250

January 2017

CONSTRUCTION STAKING 010250-3

USDA FOREST SERVICE, R4

SANPETE BUNKHOUSE

SECTION 011250 - MEASUREMENT AND PAYMENT

1. GENERAL

SUMMARY

Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

DETERMINATION OF QUANTITIES

The following measurements and calculations shall be used to determine contract quantities for payment.

For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

UNITS OF MEASUREMENT

Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

Cubic Yard (CY): A measurement computed by one of the following methods:

Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

Each (EA): One complete unit, which may consist of one or more parts.

Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

Linear Foot (LF): Measurement of work along its length from point-to-point; parallel to the base or foundation. Do not measure overlaps.

Lump Sum (LS): One complete unit.

Square Foot (SF): Measured on a plane parallel to the surface being measured.

METHOD OF MEASUREMENT

One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

As a result of changes in the work authorized by the CO.

As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

PRODUCTS (NOT APPLICABLE)

EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

January 2017

MEASUREMENT AND PAYMENT 011250-2

USDA FOREST SERVICE, R4

SANPETE BUNKHOUSE

SECTION 011900 - MOBILIZATION

1. GENERAL

SUMMARY

This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

MEASUREMENT AND PAYMENT

The measurement shall be lump sum for mobilization. Payment shall be as follows:

Bond premiums will be reimbursed after receipt of the evidence of payment.

50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

Progress payments for mobilization and preparatory work shall be subject to retainage.

PRODUCTS (NOT USED)

EXECUTION (NOT USED)

END OF SECTION 011900

January 2016

MOBILIZATION 011900-1

USDA FOREST SERVICE, R4

SANPETE BUNKHOUSE

SECTION 013300 - SUBMITTAL PROCEDURES

1. GENERAL

SUMMARY

This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .