Goose_Lake_Chipseal_Specs.doc
DOC document 158 KB Posted
- Attached to
- Goose Lake Road Chipseal Federal contract opportunity
- Solicitation number
- AG-82B1-S-09-0059
About this file
Attachments - J1- Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Goose_Brundage_VICINITY_MAP3 Model | — | |
| Upper_elev_pl Model | — | |
| AG-82B1-S-09-0059.doc | DOC document | |
| Solicitation - SF1442.pdf | ||
| fire precautions.doc | DOC document | |
| FS ARRA SIGN DETAILS.pdf | ||
| GOOSE_LAKE_COVER_SHEET Model | — | |
| Wage Determination | — |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
1Table of Contents
Preface 101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations.
101.04 Definitions.
102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract 103 - Scope of Work Deletions 104 - Control of Work Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
105.05 Use of Material Found in the Work.
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims.
107.06 Contractor’s Responsibility for Work.
107.09 Legal Relationship of the Parties.
107.10 Environmental Protection.
108 - Prosecution and Progress 108 Delete.
109 - Measurement and Payment 109 Deletions
109.02 Measurement Terms and Definitions.
155 - Schedules for Construction Contracts 155 Delete.
409 - Asphalt Surface Treatment
409.01 Description.
409.02 Material.
409.06 Weather.
409.06 Date & Time.
409.08 Asphalt Application.
409.10 Fog Seal.
409.11 Single Course Surface Treatments.
Table 409-1 Approximate Quantities of Material-Single Course Surface Treatment
409.13 Acceptance.
Table 409-4 Sampling and Testing Requirements.
409.14 Measurement
409.15 Payment
414 - Asphalt Pavement Crack and Joint Sealing
414.01 Description.
414.02 Material.
414.05 Crack Cleaning and Sealing.
414.05 Asphalt Pavement Crack Sealing and Filling
414.09 Payment.
634 - Permanent Pavement Marking
634.03 General
634.04 Conventional Traffic Paint (Type A)
635 - Temporary Traffic Control
635.03 General
702 - Asphalt Material Table 702-01 Application Temperatures – Range ◦F 712 - Joint Material
712.01 Sealants, Fillers, Seals, and Sleeves.
718 - Traffic Signing and Marking Material
718.05 Aluminum Panels
Preface
Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
| mp |
| Milepost |
| ppm |
| Part Per Million |
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
409 - Asphalt Surface Treatment
409.01_Forest_06_26_2009
409.01 Description.
Add the following to the end of the first paragraph:
Provide CRS-2P bituminous material for seal coat and CSS-1h asphalt emulsion for fog seal. Work shall include all asphalt surfaces including roadway, intersections, and curve widening, unless otherwise designated by the Contracting Officer. The roadway to Brundage Mountain Ski resort is not included in this contract.
409.02_nat_us_05_12_2004
409.02 Material.
Add the following:
When designated, conform to applicable State department of transportation asphalt cement or emulsified asphalt requirements.
409.06_nat_us_05_12_2004
409.06 Weather.
Delete the first paragraph and replace with the following:
Apply surface treatments with aggregate only when ambient air and surface temperatures are above 60 °F and rising in the shade, when the weather is not foggy or rainy, and when rain is not forecast for at least 24 hours after application.
409.06 Date & Time.
Add the following.
Construct fog seal and single-course surface treatments between June 15 and September 15 unless otherwise approved.
409.08_nat_us_06_21_2005
409.08 Asphalt Application.
Add the following to the 3rd paragraph:
Ensure the length of spread is no more than what can be covered with aggregate within 1 minute of the asphalt application.
409.10 Fog Seal.
Add the following to the first paragraph:
Dilute by adding an equal amount of water to the emulsified asphalt. Do not cut the emulsified asphalt more than once.
409.11 Single Course Surface Treatments.
409.01_Forest_06_26_2009
Add the following to the beginning of the first paragraph:
The contractor shall design the seal coat using accepted industry design methods. The design should be based on existing pavement condition and anticipated traffic.
Add the following:
Do not permit traffic to travel over any Asphalt Surface Treatment until completion of rolling.
409.10_nat_us_08_12_2004
Delete Table 409-1 and substitute the following:
Table 409-1 Approximate Quantities of Material-Single Course Surface Treatment
Table 409-1
Approximate Quantities of Material for
Single-Course Surface Treatment
| Designation |
| ADVANCE \d 3Nominal Maximum Size of Aggregate |
| Aggregate Gradation (1) |
| Estimated Quantity of Aggregate (2) pounds/yd2 |
| Estimated Quantity of Emulsified Asphalt (3) gallons/yd2 |
| Estimated Quantity of Asphalt Binder (3) gallons/yd2 |
| 1C |
| 3/8 inch |
| D |
| 20 – 26 |
| 0.44 – 0.48 |
| 0.13 – 0.24 |
(1) See Table 703-7 for aggregate gradations.
(2) Aggregate masses are for aggregates having a bulk specific gravity of 2.65, as determined by AASHTO T 84 and
T 85. Make proportionate corrections when the aggregate furnished has a bulk specific gravity above 2.75 or below 2.55.
(3) Adjust the asphalt content for the condition of the road.
409.13_nat_us_05_13_2004
409.13 Acceptance.
Delete the 2nd paragraph and replace with the following:
Aggregate gradation for asphalt surface treatment will be evaluated under Subsection 106.04.
Table 409-4 Sampling and Testing Requirements.
Delete the last cell (4th) under Sampling Frequency and replace with the following:
1 per tanker truck and 1 per trailer
Delete the 2nd and 3rd cell under Type of Acceptance and replace with the following:
Measured and tested for conformance (106.04)
409.14_forest_06_26_2009
409.14 Measurement
Delete and replace with:
Payment will be per Square Yard (9 square feet) actual quantity of area treated as staked or otherwise authorized AND per gallon actual quantity of bituminous material applied.
409.15_forest_06_26_2009
409.15 Payment
Delete and replace with:
The accepted quantities will be paid at the contract price per unit of measurement for the Section 409 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
414 - Asphalt Pavement Crack and Joint Sealing
414.01 Description.
Delete and replace with:
This work consists of preparing and sealing pavement cracks with low-modulus rubberized asphalt sealer as specified below.
414.02_forest_07_07_2009
414.02 Material.
Add the following:
Backer Rod
712.01(g)
Low-modulus rubberized asphalt
712.01 (a) (7)
All material used must meet or exceed the Low-Modulus Rubberized Asphalt Specifications. Use sealant meeting the requirements of ASTM D5167 and D5329 as shown below and specified in the Idaho DOT special provisions for crack sealing.
Prior to the prework meeting the contractor shall provide a manufacturer’s certificate for the proposed sealant that shows the product meets or exceeds the above requirements. If directed by the CO a sample will be available for confirmation testing. All containers of crack sealer shall be clearly marked with specific product name and numbers as shown on manufacturer’s certification. Product will be approved by CO prior to use.
414.05_ forest_07_07_2009
414.05 Crack Cleaning and Sealing.
Delete and replace with:
Crack seal and fill only when internal pavement temperatures are between 36 and 68 °F the road surface is dry, there is no frost in the road section, and the weather is not foggy or rainy.
Ensure the reservoir and crack are dry and free of dust, dirt and loose materials or deleterious matter adhering to the crack walls or remaining in the crack cavity so that the crack is clean and dry immediately before placing the backer rod, if applicable, and applying the sealant. Use air equipment producing at least 100 CFM and a continuous line pressure of at least 125 PSI. The air must be free of oil and water. Blow or brush dry material off the pavement surface. Avoid damage to the adjacent pavement.
Heat, mix, and apply the crack sealing and filling materials as recommended by the sealant manufacturer. Apply sealant, filling the reservoir flush to the top, using a pressure type applicator. Submit a copy of the manufacture’s recommendations to the CO prior to the start of work.
Route and clean all existing cracks between 1/8” and 1” wide. Route cracks to produce straight ½” vertical walls and a 1 ½” wide flat bottom reservoir. Remove and dispose of the routed material. Place sealant material within 72 hours of routing using a low-modulus rubberized asphalt. Completely fill the routed cross section flush with the pavement surface.
Install backer rod in cracks ¾” or wider or where the sealant penetrates more than two times the crack width for ½” -3/4” cracks.
For cracks with a width greater than or equal to 1 inch designated by the Contracting Officer, clean and fill flush to the existing surface with asphalt mix according to Section 401, 402, 403, 404, or 417.
Prior to chipsealing, repair potholes and damaged shoulders by sawcutting and removing damaged asphalt, recompacting the bedding, and repaving with asphalt mix according to Section 209 and Section 401, 402, 403, 404, or 417 Potholes and damaged shoulder work will be as designated in the following table:
| Milepost (appr.) |
| Action |
| Size (appr.) |
| 0.1 |
| Repair Pothole |
| 1 ½’ X 1 ½’ |
| 0.2 |
| Repair Sunken Trench |
| 2 ½’ X 22 ½’ |
| 0.83 |
| Repair Sunken Shoulder |
| 2’ X 7’ |
| 2.17 |
| Repair right shoulder |
| 3’ X 1’ |
| 2.8 |
| Repair Pothole Rt |
| 8’ X 3’ |
| 2.81 |
| Repair Pothole Lt |
| 9’ X 3’ |
| 3.5 |
| Repair Pothole |
| 1’ X 2’ |
For cracks less than ¼ inch wide, clean and fill with CSS-1, SS-1, or joint sealant. Apply a sealant band of 2” width over the crack, such that the crack is centered under the band. Submit a copy of, and adhere to, the manufacture’s recommendations for heating and applying the joint sealant.
Use approved methods to protect all seal materials from being picked up by traffic. Open the completed work to traffic only when the sealant will not track. Repair or replace all seal work damaged by traffic at Contractor expense. Treat seal material tracked onto the road surface as directed by the CO.
414.0_ forest_07_07_2009
414.09 Payment.
The accepted quantities will be paid at the contract price per unit of measurement for the Section 414 pay items listed in the bid schedule. Payments will be full compensation by linear feet for the work prescribed in this Section for crack sealing. No separate payment will be made for pavement patching. Patching work should be considered incidental to other bid items in the contract. See Subsection 109.05.
634 - Permanent Pavement Marking 634.00_01_us_10_12_2006
634.03 General.
Add the following:
On single lane roads, apply pavement markings according to the manufacturer’s recommendations and in a direction consistent with safe application.
634.04 Conventional Traffic Paint (Type A).
Delete subsection and replace with the following:
Apply paint when the pavement and air temperatures are above 40 °F. Spray paint at 25-mil minimum wet film thickness (before glass beads) or at a rate of 65 square feet per gallon. Immediately apply type 1 glass beads on the paint at a minimum rate of 6 pounds per gallon of paint.
635 - Temporary Traffic Control
635.03_nat_us_05_13_2004
635.03 General.
Add the following:
Install temporary traffic control signs to temporary posts or approved temporary sign mounts.
702 – Asphalt Material
409.14_forest_06_26_2009
Table 702-01 Application Temperatures – Range ◦F Remove CRS-2 and replace with:
CRS2, 2P
712 – Joint Material 712.01_nat_us_03_02_2005
712.01 Sealants, Fillers, Seals, and Sleeves.
(a) Joint sealants and crack fillers.
Add the following:
(7) Low-Modulus Rubberized Asphalt. Conform to ASTM D 3405 and the following.
| Cone Penetration, 75oF |
| 100-150 |
| Cone Penetration, -0oF |
| 25 minimum |
Flow, 140oF, 5h
3/8 in. maximum
| Resilience |
| 30-60% |
| Bond, -20oF, 200% extension |
| Pass 3 Cycles |
| Recommended Pour Temperature |
| 380oF |
| Safe Heating Temperature |
| 410oF |
| Asphalt Compatibility |
| Pass |
718 - Traffic Signing and Marking Material
718.05_nat_us_02_25_2008
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.