Supplimental Specifications_Final.doc

DOC document 566 KB Posted

Attached to
Kalispell Bay Boat Launch Federal contract opportunity
Solicitation number
AG-82B1-S-09-0010
Issued by
Department of Agriculture Forest Service Washington Office Economic Recovery Operations Center Intermountain

About this file

Supplemental Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Kalispell Bay Boat Launch, newest first.
File Type Posted
Page 3 of 3.doc DOC document
sf_30 - 2.doc DOC document
sf_30.doc DOC document
AG-82B1-S-09-0010 1 .rtf RTF text file
Kalispell Boat Dock 6_13_09.pdf PDF
SF 1442 Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Supplemental Specifications for

Standard Specifications for Construction of

Roads and Bridges on

Federal Highway Projects

FP-03

U.S. Customary Units

U.S. DEPARTMENT

OF TRANSPORTATION

Federal Highway Administration Kalispell Bay

Boat Launch Facility

IDAHO PANHANDLE NATIONAL FORESTS

Priest Lake Ranger District

6/03/2009

Preface_wo_03_15_2004_m Preface Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

TABLE OF CONTENTS

DIVISION 100 GENERAL REQUIREMENTS

Page

Section 101 Terms, Format and Definitions Section 102 Bid, Award, and Execution of Contract Section 103 Scope of Work Section 104 Control of Work Section 105 Control of Material Section 106 Acceptance of Work Section 107 Legal Relations and Responsibility to the Public Section 108 Prosecution and Progress Section 109 Measurement and Payment

DIVISION 150 PROJECT REQUIREMENTS

Section Mobilization

Construction Survey and Staking …………………………………25

Contractor Quality Control Contractor Sampling and Testing Schedules for Construction Contracts Public Traffic Soil Erosion Control

DIVISION 200 EARTHWORK

Section Clearing and Grubbing ……………………………………………35

Removal of Structures and Obstructions Excavation and Embankment Structure Excavation and Backfill

DIVISION 300 AGGREGATE COURSES

Section Untreated Aggregate Courses ….…………………………………42

DIVISION 400 ASPHALT PAVEMENTS AND SURFACE TREATMENTS

Section Minor Hot Asphalt Concre ….….…………………………………43 Section 412 Asphalt Tack Coat ………………………………………………...44

DIVISION 550 BRIDGE CONSTRUCTION

Section Driven Piles

Structural Concrete

553A Precast Concrete Structures Reinforcing Steel

DIVISION 600 INCIDENTAL CONSTRUCTION

Section Minor Concrete

Manholes, Inlets and Catch Basins ………………………………..62

Rental Equipment

Turf Establishment Signal, Lighting and Electrical Systems Prefabricated Dock Gangway Prefabricated Floatable Steel Truss Dock Prefabricated Permanent Steel Truss Dock

DIVISION 700 MATERIAL

Section Aggregate

Roadside Improvement Material

Traffic Signing and Marking Material …………………………… 78

Miscellaneous Material Supplemental Project Specification Kalispell Bay Boat Launch Facility 101 - Terms, Format, and Definitions 101.01_nat_us_04_04_2007

101.01 Meaning of Terms.

Add the following:

Delete all references in FP-03 to Transportation Acquisition Regulations (TAR).

101.03_nat_us_06_16_2006

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI Symbols:

mp
Milepost
ppm
Part Per Million

101.04_nat_us_03_29_2007

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 103 - Scope of Work

103.00_ipnf_us_06_03_2009 103 Delete

Delete all but subsection 103.01 Intent of Contract and add the following.

103.01 Intent of Contract. This project is for the removal and disposal of an existing dock system and replacing it with a new steel truss dock system, and to make improvements to the dock/pier system, launch area, access roads and parking areas. Project includes designing, furnishing, and installing floatable and permanent steel truss dock systems, furnishing and installing piling, forming and placing concrete for sidewalks, drive pad and dock abutment, furnishing and installing precast boat ramp planks, excavation, embankment, crushed aggregate surfacing, asphalt paving, surface drainage improvements and all other incidental work items necessary to complete the project in accordance with the plans and specifications.

Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work in accordance with the contract specifications and drawings.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 104 - Control of Work

104.00_nat_us_06_16_2006

Deletions

Delete Sections 104.01, 104.02, and 104.04.

104.03_ipnf_us_06_03_2009

104.03 Specifications and Drawings.

Add the following:

(c) As-Built-Plans. Furnish one set of as built plans to the Government. The Government will provide one set of contract plans to be used exclusively for recording the as-built details of the project. Use red pencil or red ink to record the information described below.

Note all additions or revisions to the location, character, and dimensions of the prescribed work shown on the contract plans. Line out all details shown that are not applicable to the completed work. Check off details shown that were incorporated into the completed work without change.

Retain the plans at the project site and, as work progresses, continuously update them to reflect the as-built details. Upon request, make the plans available to the CO to review for compliance with these specifications.

As a minimum, show the following types of changes on the as-built plans:

(1) Plan and elevation

· Changes in the construction limits

· Revisions in location, type, and grade of dock system and ramps

· Location and type of utilities

· Elevations for all aerial and underground crossings of utilities

· Revisions to grades, elevations, and stationing

· Location, length, stationing, and type of retaining walls

(2) Dock System

(a) Revisions to footing elevations

(b) Pile length, location, size, type, and tip elevation

(c) Any changes in plan or dimensions including any major changes in reinforcing

(3) Miscellaneous

(a) Revisions to parking areas or turnouts

(b) Final location, type and length of curbs, sidewalks, etc. (c) Dock material revisions and details

(d) Final location, type and length of curbs, sidewalks, boat ramps, etc. (e) Dimension revisions.

Furnish the as-built working plans to the CO before the final inspection. Correct all details found during the final inspection that are not shown on the as-built plans and return to the CO within 5 working days.

104.06_ipnf_us_06_03_2009 Add the following:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads and trails under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or National Forest resources, and when traffic can be accommodated safely.

Contractor will be responsible to restore or repair any road surface damage associated with their construction operations or the transportation of materials to the construction site.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 105 - Control of Material

105.02_ipnf_us_06_03_2009

105.02 Material Sources.

Add the following before the first paragraph.

Sources have been designated for this project as follows:

Crushed Aggregate Source - Commercial Source – There is no Government source for crushed aggregate material under this contract.

Borrow Site – No off site borrow material is anticipated for completion of this project.

Waste Site - Government Furnished – Government Designated Waste Site located at the Government pit at the end of Forest Road 789 in Section 10, T.60N., R. 5W AS SHOWN ON THE DRAWINGS. This waste site is to be used for the disposal of unsuitable or excess excavated material and clearing and grubbing debris only. All other materials designated for removal and disposal must be disposed of off National Forest System Lands per Section 203.05.

Under (b) Contractor-located sources add the following:

Prior to any pit development or use of materials, the pit site shall be approved by the Contracting Officer that the pit site is free of noxious weed as listed on the "All States Noxious Weeds List”.

105.05_nat_us_05_12_2007

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 106 - Acceptance of Work

106.01_nat_us_07_31_2007

106.01 Conformity with Contract Requirements.

Delete Subsection 106.01 and substitute the following:

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

(1) Sampling method;

(2) Number of samples;

(3) Sample transport;

(4) Test procedures;

(5) Testing laboratories;

(6) Reporting;

(7) Estimated time and costs; and

(8) Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

(1) Have the work accepted at a reduced price; or

(2) Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 107 - Legal Relations and Responsibility To the Public

107.02_ipnf_us_06_03_2009

107.02 Protection and Restoration of Property and Landscape.

Add the following:

Landscape Preservation

(a) Do not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. Confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Retrieve material which falls outside of these limits and dispose of, or incorporate in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products on site, take appropriate preventive measures to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states. If a spill of petroleum product should occur in water, immediately notify the Contracting Officer.

Service all equipment only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Meet all applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

Preserve the scenic and natural environment along this construction project.

(c) Do not allow objectionable material to enter any stream, river, lake, or other body of water. Retrieve material which falls in these areas and dispose of, or incorporate in the work as directed by the Contracting Officer, and repair damage to vegetation or structures outside the project limits as directed by the Contracting Officer.

(d) Do not operate equipment or otherwise disturb the natural vegetation and soil beyond the areas flagged on the ground or beyond two feet from edge of walkways, top of cuts, or toe of fills.

(e) Prior to the start of construction, submit to the Contracting Officer for approval a schedule and plan for temporary pollution control measures for the following phases of work:

· Boat ramp, concrete abutments and sidewalk construction

· Piling driving and filling

· Site excavation or ground disturbances that can promote surface erosion

107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06_nat_us_06_16_2006

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09_nat_us_06_16_2006

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

· Exact time and location of spill including a description of the area involved.

· Containment procedures.

· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 108 - Prosecution and Progress

108.00_nat_us_02_16_2005

108 Delete

Delete Section 108 in its entirety.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 109 - Measurement and Payment

109.02_ipnf_us_06_03_2009

109.02 Measurement Terms and Definitions

Add the following to this subsection:

One of the following methods of measurement for determining final payment is DESIGNATED IN THE PAY SCHEDULE for each PAY ITEM:

Methods of Measurement:

(a) Designed Quantities (DQ). These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:

(1) Changes in the work authorized by the CO.

(2) A determination by the CO that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.

(3) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.

(b) Stake Quantities (SQ). These quantities are determined from staked measurements prior to construction.

(c) Actual Quantities (AQ). These quantities are determined from measurements of completed work.

(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.

(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

109.02_nat_us_06_16_2006

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (MFBM). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

109.00_nat_us_02_17_2005

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 151 - Mobilization

151.00_01_us_10_11_2006

Delete Section 151 in its entirety and replace with the following.

Description

151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site; obtaining of permits, insurance, and bonds. This work also includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands, according to the requirements within.

Construction Requirements

Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.

Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.

Notify the Contracting Officer in writing at least 72 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.

Use methods of cleaning and locations for cleaning approved by the Contracting Officer.

For work at a commercial washing facility, use an approved facility.

New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or Forest Service, in the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.

Measurement

151.02 Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment for cleaning will only be made if subsequent cleanings are ordered by the Contracting Officer. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the Contracting Officer will not be included in the measurement for payment.

Measure mobilization according to Subsection 109.02.

Payment

151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Progress payments for mobilization lump sum will be paid as follows:

(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.

(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.

(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.

(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.

Include all costs associated with the initial cleaning of equipment in the unit bid price for Mobilization. Cleaning for subsequent move-ins will not be paid for unless after a suspension ordered by the Contracting Officer.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 152 – Construction Survey and Staking

152.00_ipnf_us_06_03_2009 152 – Construction Survey and Staking

Delete Section 152 in its entirety and add the following:

It will be the Contractor’s responsibility to protect construction stakes until the work has been accepted by the Government. Any replacement of construction stakes that are lost due to Contractor’s construction activities will be re-established at the expense of the Contractor. Once the project has been accepted, the Contractor will remove all construction staked within the project area.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 153 - Contractor Quality Control

153.02_nat_us_02_17_2005

153.02 Contractor Quality Control Plan.

Add the following:

Submit written proposals for approval of alternate AASHTO or State approved test methods. Alternate methods may be allowed based on documented equivalence to the specified method.

153.04_nat_us_10_24_2007

153.04 Records.

Delete all but the first sentence

Supplemental Project Specification Kalispell Bay Boat Launch Facility Section 154. Contractor Sampling and Testing

154.01_ipnf_us_06_03_2009 Description

154.01 Delete

Delete this subsection and replace with the following:

154.01 This work consists of obtaining samples for testing, testing and reporting required test results. It does not include Contractor quality control testing required under Section 153. However, include the work required under this Section in the Section 153 quality control plan.

154.02_ipnf_us_06_03_2009

Construction Requirements

154.02 Testing.

Delete this subsection and replace with the following:

Perform all tests required by the Sampling and Testing Requirement tables at the end of the following sections or as noted below:

SECTION 204- Excavation and Embankment

Comply with the requirements of Subsection 204.11 of these Supplemental Project Specifications SECTION 301- Untreated Aggregate Courses

Comply with the requirements of Section 301 and Table 301-1

SECTION 404- Minor Hot Asphalt Concrete Comply with the requirements of Section 404 and Table 404-1 SECTION 551- Driven Piles.

Comply with the requirements of Subsection 551.15 of these Supplemental Project Specifications.

SECTION 552- Structural Concrete

Comply with the requirements Section 552 and Table 552-9

154.06_ipnf_us_06_03_2009 Measurement

154.06 Delete

Delete this subsection and replace with the following:

Do not measure Contractor Sampling and Testing for Payment

154.07_ipnf_us_06_03_2009 Payment

154.07 Delete

Delete this subsection

Supplemental Project Specification Kalispell Bay Boat Launch Facility 155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004

155 Delete

Delete Section 155 in its entirety.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 156 – Public Traffic

156.03_ipnf_us_06_03_2009

156.03 Accommodating Traffic During Work.

Delete the first paragraph and replace with the following:

Accommodate traffic according to the requirements set forth below, MUTCD, and Section 635. Submit a traffic control plan for Contracting Officer review and approval at least 14 days before intended use.

Delete the following from the last paragraph:

…..according to Subsection 106.07(b)

156.06_ipnf_us_06_03_2009

156.06 Limitations on Construction Operations.

Delete this subsection and add the following:

The Contractor will be allowed to close the entire Kalispell Bay Boat Launch facility to public use during the construction period as outlined under Section C, subsection (g)- “Period of Performance”, and subsection (h)- “Restrictions”. Provide the appropriate signing in accordance with MUTCD and the traffic control plan. Place advanced closure barricades and signs at the entrance of all roads that provide access to this project. County Road No. 35 (West Lakeshore Road) will remain open to public traffic and signed for construction activities consistent with the site work being performed. Short traffic delays not to exceed 30 minutes can be approved upon a written request outlining the traffic delays. Submit to the Contracting Officer at least 7 days prior to starting construction operations that necessitates the traffic delays.

The contractor will be responsible for providing, maintaining and removal of all barricades and signs required for road closures and public traffic signing throughout the project area.

156.07_ipnf_us_06_03_2009

156.07 Nighttime Operations.

Delete this subsection in its entirety.

156.08_nat_us_02_24_2005

156.08 Traffic and Safety Supervisor.

Delete this section in its entirety.

156.10_ipnf_us_06_03_2009

156.10 Measurement and Payment

Add the following:

No separate measurement and payment will be made under this Section. All Labor, equipment and materials associated with this item will be considered incidental to other pay items shown on the SCHEDULE OF ITEMS.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 157 - Soil Erosion Control

157.02_01_us_08_23_2004

157.02 Materials

Add the following:

Provide bales, wattles, logs and rolls from a certified noxious weed free source.

157.03_ipnf_us_06_03_2009

157.03 General.

Add the following to the first paragraph:

Prior to the start of construction, submit a written Erosion Control Plan detailing all permanent and temporary control measures. Submit the erosion control plan proposal to the CO at least 14 days before beginning any operations.

Delete the second paragraph and replace with the following:

Include all special concerns and measures necessary to protect resources and government improvements in the Erosion Control Plan. Provide as a minimum, the following items in the Erosion Control Plan:

1.

Construction activities and sequence of implementation relating to specific erosion control measures.

2. The location and type of permanent controls to be implemented during construction.

3.

The location and type of temporary controls to be implemented during construction.

4.

For work in the lake, include a detailed dewatering plan or in-water work plan.

5.

For work in the lake, describe level of ground and vegetative disturbance and measures to reduce potential sediment delivery to the lake. Include methods to minimize disturbance to the lake and prevent runoff from the construction site entering directly into the lake.

6. The monitoring procedures that will take place.

As part of the “Soil Erosion Control Plan”, Contractor to provide the following:

(a) Emergency Spill Kit. Keep sufficient quantities of absorbent materials on the project site to absorb accidental fuel, hydraulic oil, or other petroleum produc spills. Use absorbent materials that are biodegradable, non-water absorbing and designed specifically for the types of spills associated with the Contractor’s operations.

(b) Straw/Hay Bales. Contractor to stockpile ten(10) straw/hay bales on the project site for the discretionary use as directed by the Contracting Officer in addition to any bales or silt fence that the Contractor intends to incorporate into the project as a part of the permanent and temporary erosion control measures as required under this specification. These straw/hay bales are intended for unforeseen emergency use and as the straw bales are used from the stockpile, Contractor shall replace the used bales within 48 hours. Upon completion of the project, the straw/hay bales shall remain in place or removed as directed by the Contracting Officer. Removed bales and remaining stockpiled bales shall be uniformly spread over seed disturbed areas upon substantial completion of the project.

Add the following to the third paragraph:

Upon completion of construction at the site, remove all temporary erosion control devices, dewatering materials and equipment from Government property.

157.08_ipnf_us_06_03_2009

157.08 Water Crossings.

Add the following:

At any channel crossing where there is running water, dewater by rerouting water flow around the site before and during excavation and embankment operations.

157.09_ipnf_us_06_03_2009

157.09 Diversions.

Delete the first sentence and replace with the following:

When shown on the plans, construct temporary channels, temporary culverts, or sandbags to divert water around disturbed areas and slopes. Earthen dams are prohibited.

157.15_ipnf_us_06_03_2009

157.15 Measurement

Add the following:

Do not measure stockpiled emergency use straw/hay bales or emergency spill kit as described under subsection 157.03.

157.16_ipnf_us_06_03_2009

157.16 Payment

Add the following:

No separate payment will be made for stockpiled emergency use straw/hay bales specified for discretionary use as directed by the Contracting Officer. These items will be considered incidental to other pay items in the bid schedule. See Section 109.05.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 201 - Clearing and Grubbing

201.01_ipnf_us_06_03_2009

201.01 Description.

Delete the first sentence and replace with the following:

This work consists of minor clearing and grubbing within the clearing limits of the construction site. Clearing shall be limited to only the construction areas and only that clearing necessary for construction of the access roads and parking areas. All clearing must be clearly delineated and then approved by the Contracting Officer before any clearing and grubbing can take place.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 203 – Removal of Structures and Obstructions

203.01_ipnf_us_06_03_2009 Delete Subsection 203.01 and replace with the following:

203.01 Description. This work consists of disposing of clearing slash, removing and disposing of existing floating boat docks, piers, piling, existing gangway, gabion baskets, concrete, asphalt corrugated steel pipe and other obstructions as SHOWN ON THE DRAWINGS.

203.04_ipnf_us_06_03_2009

203.04 Removing Material.

Add the following to this subsection:

Remove the existing dock system and piling. When possible, remove the existing pile in its entirety. If the pile can not readily be removed, cut the pile off one foot below the natural lake bottom.

203.05_ipnf_us_06_03_2009

203.05 Disposal of Material.

Add the following to this subsection:

(a) Removal from Project. All materials designated for removal under this contract are considered unsalvageable and become the property of the Contractor. Dispose of all materials off of National Forest System Lands in an environmentally safe manner in accordance with all Local, State and Federal requirements.

(b) Burn. All clearing slash is to be disposed of at the Government Designated Waste Site located at the Government pit at the end of Forest Road 789 in Section 10, T60N, R5W. Stumps and slash shall be relatively clean of dirt and piled in a location approved by the Contracting Officer for burning by the Contractor.

(c) Bury. Delete this subsection

(d) Decking. Deck unmerchantable logs at the Government Designated Waste Site located at the Government pit at the end of Forest Road 789 in Section 10, T60N, R5W. Should the Contractor elect not to take possession of merchantable logs as specified under Section 201.06, they can be cut into marketable saw log lengths and decked at the Designated Waste Site in a location approved by the Contracting Officer.

203.06_ipnf_us_06_03_2009

203.06 Acceptance.

Add the following to this subsection:

Clearing and grubbing will be evaluated under Subsection 201.

203.08_ipnf_us_06_03_2009

203.08 Payment.

Change the first sentence as follows:

The accepted quantities will be paid at the contract price per unit of measurement for the Section 201 and 203 pay items listed in the bid schedule.

Supplemental Project Specification Kalispell Bay Boat Launch Facility Section 204 – EXCAVATION AND EMBANKMENT

204.05_ipnf_us_06_03_2009

204.05 Conserve Topsoil.

Delete this subsection:

204.09_ipnf_us_06_03_2009

204.09 Preparing Foundation for Embankment Construction.

Delete subsection (a) and replace it with the following:

(a) Embankment less than 3 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying. Compact the ground surface according to Subsection 204.11.

204.10_ipnf_us_06_03_2009

204.10 Embankment Construction.

(a) General.

Delete the third paragraph and add the following:

Compact embankment side slopes flatter than 1:1.75 with a tamping type roller or by walking with a dozer. For slopes 1:1.75 or steeper, compact the slopes as construction of the embankment progresses.

204.11_ipnf_us_06_03_2009

204.11 Compaction.

Delete this subsection and substitute the following:

Adjust the moisture content to a level suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Use compression-type rollers at speeds less than 6 feet per second and vibratory rollers at speeds less than 3 feet per second. Compact each layer of material full width with one of the following and until there is no visible evidence of further consolidation.

(1) Four roller passes of a vibratory roller having a minimum dynamic force of 40,000 pounds impact per vibration and a minimum frequency of 1000 vibrations per minute.

(2) Eight roller passes of a 20-ton compression-type roller.

(3) Eight roller passes of a vibratory roller having a minimum dynamic force of 30,000 pounds impact per vibration and a minimum frequency of 1000 vibrations per minute.

Increase the compactive effort for layers deeper than 12 inches as follows:

( For each additional 6 inches or fraction thereof, increase the number of roller passes in (1) above by four passes.

( For each additional 6 inches or fraction thereof, increase the number of roller passes in (2) and (3) above, by eight passes.

204.13_ipnf_us_06_03_2009

204.13 Sloping, Shaping, and Finishing.

Delete section (d) and add the following:

(d) Finishing. Remove all material larger than 6 inches from the top 6 inches of the roadbed. Remove unsuitable material from the roadbed, and replace it with suitable material. Ensure that the subgrade is visibly moist during shaping and dressing. Bring low sections, holes, cracks, or depressions to grade with suitable material. Finish roadbeds to within ±0.05 feet of the staked line. Finish ditch cross-sections to within ±0.10 feet of the staked line and grade. Maintain proper ditch drainage. Finish the boat ramp surface to be smooth, uniform, and shaped to conform to the existing ramp sections. Remove unsuitable material from the boat ramp and replace it with suitable material. Finish surfaces to match the existing boat ramp.

204.14_ipnf_us_06_03_2009

204.14 Disposal of Unsuitable or Excess Material.

Delete the text of the first paragraph and substitute the following:

Dispose of unsuitable and excess material at the Government Designated Waste Site located at the Government pit at the end of Forest Road 789 in Section 10, T60N, R5W. Shape material to drain as directed by the Contracting Officer.

Measurement

204.16_ipnf_us_06_03_2009

204.16 (e) Waste. Delete this paragraph

Supplemental Project Specification Kalispell Bay Boat Launch Facility Section 209 – STRUCTURE EXCAVATION AND BACKFILL

209.10_ipnf_us_06_03_2009

209.10 Backfill.

(a) General.

Add the following:

Do not place or backfill footings or foundations that meets any of the following conditions until the excavation and foundation have been approved in writing by the CO:

· Embankment height greater than 6 feet at subgrade centerline.

· Installation in a lake or protected stream course.

· Any footing or foundation.

209.11_ipnf_us_06_03_2009

209.11 Compacting.

Delete the subsection and replace the following:

Adjust the moisture content of the material to a moisture content suitable for compaction. Compact material placed in all layers by operating compaction equipment over the full width of each layer until visible deformation of the layer ceases or, in the case of sheepsfoot roller, the roller “walks out” of the layer. Make at least four complete passes.

209.12_ipnf_us_06_03_2009

209.12 Acceptance

Delete reference to Table 209-1.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 301 – Untreated Aggregate Courses

Description

301.00_ipnf_us_06_03_2009

301.01 Add the following to this subsection:

Crushed aggregate shall meet the requirements specified in Subsection 703.05 and Table 703-2 – Subbase and Base Gradation for crushed aggregate base courses or a similar gradation that meets the Idaho Department of Transportation, or other Federal, State or local Government agency’s specifications and is approved by the Contracting Officer.

Crushed aggregate surfacing will not be placed by the Contractor until the subgrade has been approved in writing by the Contracting Officer.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 404 - Minor Hot Asphalt Concrete

404.02_nat_us_06_09_2006

404.02 Composition of Mix (Job-Mix Formula).

Delete the second paragraph and replace with the following:

Submit a job-mix formula and supporting documentation, test results, and calculations for the material to be incorporated into the work. Include copies of laboratory test results and mix design data that demonstrate that the properties of the aggregate, additives, and mixture meet the current requirements and criteria of Federal or state agencies. Ensure that the job-mix formula was performed no more than one year prior to placing the hot asphalt concrete. After reviewing the Contractor’s proposed job-mix formula, the CO will determine the final values for the job-mix formula to be used and notify the Contractor in writing.

404.04_nat_us_03_02_2005

404.04 Weather Limitations.

Change 35o F to 45o F:

404.06_nat_us_03_02_2005

404.06 Placing.

Add the following:

Do not place asphalt until the CO has approved in writing the area where it will be placed.

Delete the last sentence and replace with the following:

Offset the longitudinal joint of one layer at least 6 inches from the joint in the layer immediately below. Make the longitudinal joint in the top layer along the centerline of two-lane roadways or at the lane lines of roadways with more than two lanes. Offset transverse joints in succeeding layers and in adjacent lanes at least 10 feet, where possible.

404.07_nat_us_03_02_2005

404.07 Compacting (b).

Delete and replace with the following:

(b) Non-roadway paving. Compact by rolling with a hand-operated roller with a mass of least 1 ton or otherwise approved by the Contracting Officer. Perform initial compaction while the mixture is above 250 °F and continue until no roller tracks remain.

404.07_nat_us_03_02_2005

404.07 Compacting (a).

Delete and replace with the following:

(a) Roadway paving. Thoroughly and uniformly compact the surface a minimum of three passes with rollers that meet one of the following requirements:

(1) Steel-wheeled rollers, other than vibratory type, capable of exerting a force of not less than 1.5 ton/feet of width of the compression roll or rolls.

(2) Vibratory steel-wheel rollers with a minimum mass of 5 ton, equipped with amplitude and frequency controls, and designed to compact asphalt concrete.

(3) Pneumatic-tire rollers with smooth tread tires of equal size that provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 lbf/in2.

Perform initial compaction while the mixture is above 250 °F. Perform finish rolling with steel-wheel rollers and continue until no roller tracks remain.

404.09_ipnf_us_06_03_2009

404.09 Acceptance.

Add the following to the second paragraph:

See Table 404-1 for sampling and testing requirements.

Table 404-1. Delete and replace with the following:

Table 404-1. Sampling and Testing Requirements.

Material or Product
Type of Acceptance (Subsection)
Characteristic
Category
Sampling Methods Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Hot asphalt concrete pavement
Measured and tested for conformance (106.04)
Asphalt Cement

Compaction

AASHTO T168 and T308 Core Sampling & Testing per AASHTO Three minimum per project

At locations as directed by CO Roadway prior to compaction

Roadway after compaction Yes

Yes, when requested Tested by Government Upon completion of tests & prior to final payments

Compaction testing (core samples) only required should Contractor fail to meet specified temperatures, required compaction requirements or compaction results in an unconsolidated asphalt surface.

Kalispell Bay Boat Launch Facility

412 - Asphalt Tack Coat 412.07_nat_us_07_03_2007

Measurement

412.07 Acceptance

Delete the first paragraph and replace with the following:

Emulsified asphalt will be evaluated under Subsections 106.02, 106.03, and 702.07.

Supplemental Project Specification Kalispell Bay Boat Launch Facility

Section 551 – DRIVEN PILES 551.01_ipnf_us_06_03_2009

Description Add the following to Subsection 551.01:

551.01 Contractor is required to submit for approval a “Pile Driving Plan”. This plan shall outline the equipment, manpower, materials, schedule and testing requirements for the pile driving operation.

Contractor shall engage the services of a Professional Engineer responsible for the dock design with pile driving credentials to approve the pile driving plan and witness the installation of the piles at the site. Outside consultant shall monitor the pile driving operations and verify that the ultimate capacity is achieved during installation and certify that the installation of the driven piles meets the intent of the design.

Construction Requirements

551.06_ipnf_us_06_03_2009

551.06 Driven Pile Capacity.

Delete the first two paragraphs and replace with the following:

Drive piles to the specified penetration and to the depth necessary to obtain the required ultimate pile capacity as specified by the professional engineer responsible for the dock design. Splice piles not obtaining the required ultimate capacity at the ordered length, and drive until the required ultimate pile capacity is achieved.

The design engineer for the dock system will be responsible to specify what means are necessary to determine that the in-place pile meets the required ultimate pile capacity.

551.15_ipnf_us_06_03_2009

551.15 Acceptance.

Add the following:

The design engineer for the dock system will be responsible to monitor installation and certify that all piles meet the specified capacity and minimum depth of embedment and submit as-built drawings showing final pile depths.

Supplemental Project Specification Kalispell Bay Boat Launch Facility 552 - Structural Concrete 552.02_nat_us_06_20_2007

Material

552.02 Add the following:

Anchor bolts 717.01

Dowels 717.17

Epoxy resin adhesives 725.21

High strength non-shrink grout 701.02

Mortar 701.02

Portland cement 701.01

Sealants, fillers, seal, and sleeves 712.01

Construction Requirements

552.03 Composition (Concrete Mix Design).

Delete Tables 552-1, 2, and 3 and replace with the following:

Table 552-1

Composition…