SECTION 01 11 00 SUMMARY OF WORK 06/16 PART 1 GENERAL 1.1 WORK COVERED BY CONTRACT DOCUMENTS 1.1.1 Project Description The work includes all necessary labor equipment and materials to install CAT 6e uplink runs between the core networking/server infrastructure components already in place and end-point locations in end-users rooms. 1.1.2 Location The work shall be located at the USDA ARS BRL 1605 Albrecht Boulevard Fargo North Dakota approximately as indicated. The exact location will be shown by the.

View the file

Other files for this federal contract opportunity

Other files attached to Cabling Project, newest first.
File Type Posted
BRL_B102.pdf PDF
BRL_A104.pdf PDF
BRL_299J.pdf PDF
2016_BRL_CAT6a_Summary.xlsx XLSX spreadsheet
BRL_111.pdf PDF
BRL_2nd_FLoor.pdf PDF
BRL_155-134.pdf PDF
BRL_1st_FLoor.pdf PDF
BRL_111.pdf PDF
BRL_B102.pdf PDF
BRL_2nd_Floor_Overview.pdf PDF
BRL_1st_Floor_Overview.pdf PDF
BRL_A104.pdf PDF
BRL_155-1.34.pdf PDF
2016_BRL_CAT6e_Summary.xlsx XLSX spreadsheet
BRL_187.pdf PDF
FBO.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 11 00

SUMMARY OF WORK

06/16

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The work includes all necessary labor, equipment and materials to install CAT 6e uplink runs between the core networking/server infrastructure components already in place and end-point locations in end-users rooms.

1.1.2 Location

The work shall be located at the USDA ARS BRL, 1605 Albrecht Boulevard Fargo, North Dakota approximately as indicated. The exact location will be shown by the Contracting Officer's Technical Representative.

1.1.3 Base bid – BRL Building 1 and BRL Building 2 CAT 6e Ethernet

The internal network shall be capable of data transfer rates of up to 1 Gigabit per second (GB/s) between Wire Closet Patch Panel and terminated end point at designated room destination. Each CAT 6e run will be terminated in a properly rated patch panel using T-568B termination connections. Each CAT 6e run will be terminated in properly rated wall jacks using T-568B termination connections. All cabling will be tested and machine labeled at the Wire Closet patch panel (on the front of the physical Patch Panel as well as cable that feeds the Patch Panel, and at the wall jacks. See: LabelRequirements.pdf) No handwritten labels will be allowed. All CAT 6e will be Plenum and runs will be installed according to all applicable local, state and Federal building codes. Install CAT 6e Copper Ethernet cable and terminate.

Contractor shall keep the old copper Ethernet lines connected until the new cable is in place and then pull the old abandoned Ethernet cable upon successful testing of new CAT 6e cabling.

CAT 6e segments included are indicated on drawing 1 and are listed in detail in BLD5-BLD6_CAT6e_Summary.xlsx (lengths were obtained using AutoCad documents (see attachments as PDF) to scale, and including up/down wall distances from planned Patch Panel location and end point receptacles and linear distance with 10% excess factored in):

a. Segment 01 Wire Closet, BLD 1, BRL 155/134

1. Total Runs (CABLES): 240

2. Total Locations (DROPS): 66

3. Total Distance: 16508 FT

4. Total 48-port Patch Panels in Wire Closet (BRL 155): 5

5. Total 48-port Patch Panels in Wire Closet (BRL 134): 1

b. Segment 02 Wire Closet, BLD 2, BRL B102

1. Total Runs (CABLES): 78

2. Total Locations (DROPS): 24

3. Total Distance: 5746 FT

4. Total 48-port Patch Panels in Wire Closet (BRL B102): 2

1.1.3.1 Remove old Ethernet cable

Contractor shall keep the old copper Ethernet lines connected until the new cable is in place and then pull the old abandoned Ethernet cable upon successful testing of new CAT 6e cabling.

1.1.4 Alternate 1 – Segment 03 Wire Closet, BLD 1, BRL 111

a. Total Runs (CABLES): 144

b. Total Locations (DROPS): 44

c. Total Distance: 12993 FT

d. Total 48-port Patch Panels in Wire Closet (BRL 111): 3

1.1.4.1

Contractor shall keep the old copper Ethernet lines connected until the new cable is in place and then pull the old abandoned Ethernet cable upon successful testing of new CAT 6e cabling.

1.1.5 Alternate 2 – Segment 04 Wire Closet, BLD 1, BRL 187

a. Total Runs (CABLES): 190

b. Total Locations (DROPS): 59

c. Total Distance: 15048 FT

d. Total 48-port Patch Panels in Wire Closet (BRL 187): 4

1.1.5.1

Contractor shall keep the old copper Ethernet lines connected until the new cable is in place and then pull the old abandoned Ethernet cable upon successful testing of new CAT 6e cabling.

1.1.6 Alternate 3 – Segment 05 Wire Closet, BLD 3 “Barn”, A104

a. Total Runs (CABLES): 62

b. Total Locations (DROPS): 18

c. Total Distance: 5143 FT

d. Total 48-port Patch Panels in Wire Closet (BRL A104): 2

1.1.6.1

Contractor shall keep the old copper Ethernet lines connected until the new cable is in place and then pull the old abandoned Ethernet cable upon successful testing of new CAT 6e cabling.

1.2 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract.

Before work is started, the Contractor shall arrange with the Contracting Officer's Technical Representative a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

Attachments:

LabelRequirements.pdf 2016_BRL_CAT6e_Summary.xlsx BRL 111.pdf BRL 155-134.pdf BRL 187.pdf BRL A104.pdf BRL B102.pdf BRL_1st_Floor_Overview.pdf BRL_2nd_Floor_Overview.pdf

EVALUATION FACTORS FOR AWARD

· 1. Past Performance -

· Quotes will be evaluated based on the offeor’s past performance as provided by the offerors references.

· 2. Offeror’s Technical Solution-

· The Government will evaluate the performance of the offeror’s product for capability and performance.

· 3. Quality and Reliability-

· Quotes will be evaluated on the offeror’s product for its level of Quality and Reliability.

· 4. Price-

· The quoted price is fair and reasonable.

· NOTE:

· All evaluation factors other than cost or price, when combined, are significantly more important than cost or price. Factors and sub-factors are prioritized in the following order of importance (i.e. most important first, least important last) for award evaluation 2, 3, 1, 4.

· The Government will evaluate quotes for award purposes, considering the evaluation factors above, and will award to that offeror whose proposal represents the best value to the Government.

· RFQ Brand Name or Equal and Buy Best Value statements:

· 52.211-6 -- Brand Name or Equal (1999)

· (a) If an item in this solicitation is identified as "brand name or equal," the purchase description reflects the characteristics and level of quality that will satisfy the Government's needs. The salient physical, functional, or performance characteristics that "equal" products must meet are specified in the solicitation.

· (b) To be considered for award, offers of "equal" products, including "equal" products of the brand name manufacturer, must-

· (1) Meet the salient physical, functional, or performance characteristic specified in this solicitation;

· (2) Clearly identify the item by-

· (i) Brand name, if any; and

· (ii) Make or model number;

· (3) Include descriptive literature such as illustrations, drawings, or a clear reference to previously furnished descriptive data or information available to the Contracting Officer; and

· (4) Clearly describe any modification the offeror plans to make in a product to make it conform to the solicitation requirements. Mark any descriptive material to clearly show the modification.

· (c) The Contracting Officer will evaluate "equal" products on the basis of information furnished by the offeror or identified in the offer and reasonably available to the Contracting Officer. The Contracting Officer is not responsible for locating or obtaining any information not identified in the offer.

· (d) Unless the offeror clearly indicates in its offer that the product being offered is an "equal" product, the offeror shall provide the brand name product referenced in the solicitation.

· (End of provision)

52.232-18 Availability of Funds.

As prescribed in 32.705-1(a), insert the following clause in solicitations and contracts if the contract will be chargeable to funds of the new fiscal year and the contracting action is to be initiated before the funds are available:

AVAILABILITY OF FUNDS (APR 1984)

Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

(End of clause) (SS 7-104.91(a) 1962 SEP)

Please make sure quotes are valid until 10/31/2016