Site_Visit_Questions-perimeter_fence.docx
DOCX document 10 KB Posted
- Attached to
- Perimeter Fencing Federal contract opportunity
- Solicitation number
- AG-6538-S-17-0034
About this file
questions and answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_1A-AG-6538-S-17-0034.docx | DOCX document | |
| SF18-AG-6538-S-17-0034.pdf | ||
| Attachment_IB-specifications-AG-6538-S-17-0034.docx | DOCX document | |
| AG-6538-S-17-0034_RFQ_Const_Clauses_(07-2016).docx | DOCX document | |
| Attachment_II_-_Davis_Bacon_Wage_Rate-AG-6538-S-17-0034.docx | DOCX document | |
| Attachment_III_-_Bond_Forms-AG-6538-S-17-0034.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Visit Questions & Answers
Could we use 2 3/8” or 27/8” used steel well pipe for h-braces?
Yes, you can use either size or you can use wood.
Staple vs. grooving on hedge post?
Grooving will be acceptable Is dead man required on hedge posts?
No What do you need for gate stays and how far between?
6 stays per 24 foot gate How much old hog wire?
3 miles Do you want a gate every ¼ mile?
Yes Section 23 has no demolition Fence goes to north end of depot east of the southeast quarter of section 83. Fence will not exceed one mile.