Atth_J_SOW_for_Y-2_Building_Remodel.docx
DOCX document 27 KB Posted
- Attached to
- Y2K BLDG Federal contract opportunity
- Solicitation number
- AG-6197-S-17-0014
About this file
SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30a00003.pdf | ||
| SF30a00002.pdf | ||
| a0002REVISED_Sheet_E001_-from_Y2_Drawings_FINAL_SUBMITTAL.pdf | ||
| a0002Bldg_22_and_Bldg_Y2_area_map.pdf | ||
| A0001drawing.pdf | ||
| A0001signin.pdf | ||
| A0001Question.docx | DOCX document | |
| A0001bidsch.docx | DOCX document | |
| SF30a00001.pdf | ||
| AG-6197-S-17-0014_Y2K.docx | DOCX document | |
| Y-2_Construction_Specifications.pdf | ||
| Attch_J_General_Decision_NumberIA170145_07282017.docx | DOCX document | |
| 1442.pdf | ||
| Y-2_Construction_Renovation_Drawings.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Y-2 Building Remodel USDA, Ames 07/25/2017
Project Requirements:
Background:
Building Y-2 is a steel building built in 1980 which is used to house and stage existing equipment that has been decontaminated that is to be sold, reused, or recycled. The existing building has very little electrical in it, has two large, manual roll-up doors and two man-doors at both the West and East ends of the building to receive and send out shipments of equipment. The building is one large open room and has insulation only on the roof that is deteriorating. The walls are not un-insulated. There are vents and skylights in the roof. There is no heating or air conditioning in the building and very little electrical (the only electrical serves exterior lighting and a camera located on the exterior of the building).
Scope:
In fiscal year 2016, Johnson McAdams was contracted out to provide design documents for the construction of fixes to the Y-2 Building. This project will be to construct the fixes that are included in the design documents (Drawings and Specifications attached) provided by Johnson McAdams and the requirements noted below.
General Requirements
1.01 Work Restrictions & Conditions
A. Site Security Access
1. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/subcontractor employees shall sign-in and out at the main site entrance gate and wear a contractor/visitor identification badge at all times while on the site. The ID badges will be turned in at the end of the work day. A current government-issued identification with a picture ID is required for entry.
2. Access to each individual site shall be arranged by the Contracting Officer's Representative according to the schedule submitted by the contractor and approved by the Contracting Officer’s Representative. The contractor shall coordinate and schedule his/her work under this contract to cause the least interference with the normal flow of visitor and employee traffic.
3. Construction vehicles will be allowed access adjacent to the work; contractor employee’s personal vehicles shall be parked in the facility parking lots.
4. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.
5. Work shall be confined to the areas identified on the Drawings. Unless accompanied by a NCAH/USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.
6. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.
7. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals.
B. Work Hours: Regular work hours for the site are 8:00am to 4:30PM, Monday through Friday, excluding Government holidays. Requests for exceptions to this schedule shall be made in writing forty-eight (48) hours in advance and approved by the Contracting Officer's Representative.
C. Work Outside Regular Work Hours: Work scheduled outside regular work hours including late hours, Saturdays, Sundays, and Government holidays requires Contracting Officer’s Representative (COR) approval in advance. Make application to the COR at least 5 calendar days prior to such work to allow arrangements to be made by the Government for access to the work area and inspection & monitoring arrangements. Requests shall include the exact dates, hours, location, and purpose of the exception. If approved, the COR will coordinate access with the site security office.
D. Construct Work in stages to accommodate Owner’s use of premises during construction period. Coordinate construction schedule and operations with Contracting Office’s Representative (COR).
1. Access Schedule Work to minimize use of street barricades and detours.
2. Access Phases of construction are those indicated in Drawings.
E. Coordinate use of premises under direction of the COR. Contractor shall confine construction equipment, storage of materials and equipment and operations of workers to areas permitted by law, ordinances, permits, or requirements of Contract Documents, and shall not unreasonably encumber premises with construction equipment or other material or equipment.
1. Assume full responsibility for protection and safekeeping of items under this Agreement, stored on site.
2. Move any stored items, under Contractor’s control, which interfere with operations of Owner or separate contractor.
3. Obtain and pay for use of additional storage or Work areas needed for operations.
F. Owner will occupy premises during entire period of construction for conduct of its normal operations. Coordinate with Owner’s Representative/COR in all construction operations to minimize conflict, and to facilitate Owner usage. Contractor shall at all times conduct its operations as to ensure least inconvenience to Owner.
1.02 Special Agreement Checks (SAC)
A. Use of Premises
1. Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the work is approved.
2. Keep driveways and entrances serving premises clear and available to the Government, employees, visitors and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
3. Limited parking may be available on the site away from each facility.
4. All contractor staff shall pass an appropriate APHIS designated background investigation before performing any work. The contractor personnel who will perform work at the USDA, NCAH facilities will be required to complete and have a favorable determination of suitability for OFI Form 86C, Special Agreement Checks (SAC) prior to starting work under this contract.
a. The contractor shall provide a list of intended employees to the Contracting Officer’s Representative within three (3) calendar days of task order award.
b. The contractor shall keep the list of employees up to date throughout the project in the event of employee separation and transfer.
B. Adherence to Security Policies and Procedures
1. The Contractor shall adhere to all Site, APHIS and USDA security policies and procedures including Code of Federal Regulations Requirements, Standard Operating Procedures, Security Directives, Security Procedures, General Orders, Post Orders and any applicable Government Policies and Procedures.
a. Failure to adhere to or violation of any above listed requirements, procedures, directives, orders and/or policies may result in criminal prosecution or contractor representative or contractor employee (violator) removal.
1.03 Quality Control Requirements
A. The Contractor shall maintain a Construction Quality Control (CQC) Plan for the project that is generally in conformance with the Corp of Engineers (COE) Quality Control process.
B. The Contractor’s CQC Plan manager shall be trained in the COE system and shall maintain the project CQC Plan records and documents.
C. The Contractor shall maintain an up-to-date “Conformed” set of drawings and specifications on the jobsite that documents all changes, RFIs, and field conditions encountered during the work.
1.04 Intent of Contract Drawings
A. Government provided drawings, henceforth referred to as “Contract Drawings”, do not attempt to show complete details of building construction that may affect installation. Government provided diagrams of proposed systems are for reference only and do not necessarily show physical arrangement of all equipment and/or maximum number of devices. Minimum system requirements are shown.
B. Devices are shown diagrammatically only. System layout does not necessarily show maximum number of system components and should not be used for obtaining quantities for linear runs of conduits and wires. The contractor shall provide all conduits and wire wherever needed to complete installation of specific equipment required and provided by the contractor.
C. Locations of existing and Government concept devices are approximate and may be distorted for clarity in representation.
1.05 Regulatory Requirements
A. The equipment materials, installation, workmanship, and operation shall conform to the most stringent applicable requirements of the most recent editions of the associated publications, in the below section and in the attached specifications unless otherwise noted:
1. National Fire Protection Association (NFPA)
a. NFPA 101 – Safety to Life from Fire in Buildings and Structures.
b. NFPA 1 – Uniform Fire Code
c. NFPA 5000 – Building Construction and Safety Code
2. Underwriters Laboratories, Inc. (UL)
a. Appropriate UL Standards
3. State and Local Building Codes as adopted by the Authority Having Jurisdiction (AHJ).
4. The Uniform Federal Accessibility Standards (UFAS)
5. Occupational Safety and Health Administration (OSHA)
6. Equipment Manufacturer Printed Instructions
7. Architectural Barriers Act (ABA)
1.06 Coordination
A. The contractor shall coordinate all work with the Contracting Officer's Representative.
B. The contractor shall submit an installation schedule for review and approval by the Contracting Officer's Representative within ten (10) days of task order award.
C. The contractor shall be solely responsible for coordinating work with all subcontractors and ensuring that all items of joint use in conjunction with installations are completed.
1.07 Special Provisions
A. There are buildings on campus that are bio-security facilities and contains biohazard materials; therefore, the contractor must complete any area specific training before entry and follow bio-security procedures for entering and exiting any such facility. In addition, any tools or equipment carried into the facility must be decontaminated before they can be removed from the facility.
B. The Contractor shall confine all operations to within the work limits of the project and exercise special care to maintain natural surroundings undamaged. All surfaces that have been altered for the installation of the concrete shall be refinished to match original condition by skilled personnel of the trades involved at no additional expense to the Government.
C. Finished surfaces of existing facilities that are affected, marred, scratched, or damaged by the contractor shall be refinished to match original condition.
1. Patching material shall be of the same type, style, and thickness, and shall be finished to match existing adjacent surface construction in color and texture.
2. Patching material, paint color, paint material and paint application methods shall be approved in advance by the Contracting Officer’s Representative.
D. No building structural members shall be cut or altered without prior approval of the Contracting Officer's Representative.
E. Any damage resulting from contractor's operation shall be brought to the attention of the Contracting Officer's Representative immediately.
F. The contractor shall take all necessary and reasonable measures to keep the work site clean of trash and debris. Work areas shall be cleaned immediately as work in that area is completed, and before moving to a new work site. Place all trash and debris in OSHA approved containers, remove, and dispose of trash off site daily.
G. The contractor shall move all materials and equipment, including ladders and scaffolding from the site at the completion of each day's operation unless otherwise approved by the Contracting Officer's Representative.
H. The contractor shall provide proper safety equipment to workmen and ensure a safe environment for employees and the general public at all times. The contractor shall work to ensure free, unobstructed, and safe access to and about the work area.
1.08 Temporary Facilities
A. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any utility connections.
B. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project.
C. Construction Trailer: The Contractor may locate a job trailer to the site. Location and services shall be coordinated with the COR.
D. Toilet Facilities: The Contractor shall provide and maintain portable toilet facilities for the project workmen.
1.09 Confined Space Program
A. The Contractor and/or subcontractor employees who will be entering Confined Spaces shall be adequately trained and equipped for access and extraction. The Contractor shall provide all ventilation equipment, air quality monitoring, harnesses, and other safety equipment as appropriate for OSHA compliance. The Contractor’s Confined Space program shall substantially conform to the NCAH plan.
B. The Contractor shall submit a written copy of their plan(s) for acceptance by the COR prior to entry into any confined spaces.
C. The Contractor shall provide copies of entry logs and monitoring to the Owner’s Representative at any time requested during the project effort.
1.010 Lock-out/Tag-out Program
A. The Contractor and/or subcontractor employees who will be working on the job will apply a lockout/tagout (LOTO) process to control dangerous energy sources. The Contractor/subcontractor shall have a LOTO program established and use Contractor LOTO locks, tags, and procedures.
B. The Contractor/subcontractor shall review their LOTO program with NCAH FEU personnel to coordinate LOTO programs before implementing LOTO.
1.011 Hot Work Plan
A. The Contractor/subcontractor shall have a written plan in place to manage the safety and fire hazards associated with hot work. The Plan shall include fire watch and all other requirements in accordance with OSHA. The Contractor/subcontractor shall maintain written records of hot work until final acceptance of the project and shall provide copies to the Owner’s Representatives at any time requested.
1.012 Submittal & Shop Drawings Procedures
A. Submittal Register: At the beginning of the project, the Contractor will provide a Submittal Register identifying all the items called out in the Specifications for submittal to the COR for approval (in consultation with the project AE). The Contractor will update and maintain the Submittal Register to show the current status of all required submittals.
B. Submittal Requirements
1. Format: There is no formal submittal transmittal or format for this project other than the documents shall be submitted as PDF files, scanned or created in documents that can be easily read when printed on 11x17 sheets. Exceptions for larger sheet sizes will be considered by the COR. Failure of the Contractor to provide legible submittals will be adequate grounds for rejection.
2. Identification: Submittals shall be labeled and marked for this project. The identification shall include: Contractor/subcontractor’s name, date of submittal, description of item, specification section, and details on product data that are marked clearly for this project.
C. Submittal Procedures: All submittals will be posted in PDF by the Contractor to the USDA ARS Sharepoint website that has been established for this project. The submittal reviewing authority/AE will download the submittals for review and post approvals to the Sharepoint site. This same submittal process will be used for RFIs, Change Bulletins, etc.
D. Approved Submittals: The approval/acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist.
E. Submittal items for this project at a minimum shall be:
1. All envelope materials, including Architectural Wall Panels, roofing, sealants, and structural materials
2. All Doors and operators
3. Finish materials (including but not limited to drywall, paint, epoxy, etc…)
4. All lighting used on this project (including emergency).
5. Any electrical power equipment, conduits, and feeders on project.
6. All security access equipment on this project
7. All mechanical equipment and utilities serving equipment on this project
1.013 Close-out Submittals
A. Warranty Documentation
1. Warranty List: Provide a warranty summary sheet in spreadsheet format with all the warranties listed by section, description, supplier, warranty contact, start date, end date. Provide electronic copy to the COR and place printed copy in the front of the Warranty Binder.
2. Warranty Copies in Binder: Provide one signed & dated copy of all warranties for products and equipment installed on the project. The Warranty binder shall be divided by Specification Section and shall be provided to the COR. An electronic (scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.
B. Operation & Maintenance Manuals: Contractor shall provide a printed copy of all Operation & Maintenance documentation provided with equipment and systems installed in the project and place the manuals in an organized binder. The O&M Manuals shall be organized by specification section and shall have an index at the front of the binder. The Contractor shall also provide a PDF version of the Manuals to be submitted with the close-out documentation.
C. Record Drawings
1. Redline Specifications: During the construction period the Contractor shall keep an updated & marked-up or “redline” copy of the project specifications on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline specifications and provide an electronic copy in PDF to the Owner along with the close-out documentation.
2. Redline Drawings: During the construction period the Contractor shall keep an updated “redline” or “conformed” copy of the project drawings on the jobsite. The redline set shall include notes on changes, RFI responses, and other field notes. At the end of the project the Contractor shall electronically scan the redline drawings at full-size and in color, and provide an electronic copy in PDF to the Owner along with the close-out documentation.
3. AE Review: The Owner’s AE representative will review the redline specifications & drawings and advise the COR if the documentation appears to be full and complete. If the documentation is not complete, the Contractor will be required to provide complete redline documents before final payment is recommended.
END OF SECTION