Sol_AG-4756-S-16-0045.pdf
PDF 528 KB Posted
- Attached to
- Tellico Waterline Replacement Federal contract opportunity
- Solicitation number
- AG-4756-S-16-0045
About this file
Request for Proposal. Retain for your records.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_1.pdf | ||
| SF_24_Bid_Bond_2016.pdf | ||
| TellicoWaterLineDrawings_7_26_16.pdf | ||
| Business_Proposal.pdf | ||
| TellicoWaterSystemSpecs_7_2016.pdf | ||
| Experience_questionnaire.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
807400
USDA FOREST SERVICE
CHEROKEE NATIONAL FOREST
2800 NORTH OCOEE STREET
CLEVELAND TN 37312
See Block 7
NINA BARROW 423-476-9706
1x 07/26/2016
AG-4756-S-16-0045
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Tellico Waterline Replacement, AG-4756-S-16-0045. Date issued: July 26, 2016
Contractor shall furnish all labor, supervision, materials, transportation, and equipment to replace the existing water distribution system with approximately 1000
LF of 3" diameter HDPE pipe, approximately 150 LF of 2" diameter HDPE pipe, and 50'
1" HDPE diameter pipe. Project includes well house renovation and underground gutter drain replacement. Project is located at the Tellico Ranger District Office site, Cherokee National Forest, in Monroe County, Tennessee.
This procurement is 100% set aside for Small Business.
Price Range: $150,000 to $250,000.
DUNS #: ________________________
Registered in System for Award Management (SAM)? ____ yes ____ no
Pre-bid meeting (not mandatory) is scheduled; see Section L.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 134 calendar days and complete it within ________________ ________________ calendar days after receiving
08/25/2016
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USDA FOREST SERVICE
CHEROKEE NATIONAL FOREST
2800 NORTH OCOEE STREET
CLEVELAND TN 37312
NINA BARROW
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 46
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
AG-4756-S-16-0045
Delivery: 134 Days After Notice to Proceed
Delivery Location Code: 4756
USDA FOREST SERVICE
CHEROKEE NATIONAL FOREST
2800 NORTH OCOEE STREET
CLEVELAND TN 37312 US
FOB: Destination
001 Tellico Ranger Station Water System Replacement:
replace the water distribution system with approximately 1,000 ft of 3" diameter HDPE pipe, fittings and other related items. Project includes well house renovation.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Construction RFP AG-4756-S-16-0045
Tellico Waterline Replacement, CNF
PART I – SECTION B - Supplies or Services and Prices/Costs
Schedule of Items
ITEM 1: Tellico Ranger Station Water System Replacement. Provide all materials, equipment, labor, supervision and incidentals to replace the water distribution system with HDPE pipe and related work, in accordance with contract terms, specifications and drawings. Project includes well house renovation and office drain installation as option items. Contractor is responsible for maintaining water supply to District offices at project site during construction.
Item Description Qty Unit MM Unit Cost Total Cost
A
Selective Demolition and Repair, Building
LS
LSQ
B
Pavement Removal and Patching, Asphalt and
Concrete
C
Yard Hydrant
EA
AQ
D
Fire Hydrant
E
1” Ball Valve & Cast Iron Valve Box
F
2” Ball Valve & Cast Iron Valve Box
G
3” Ball Valve & Cast Iron Valve Box
H
1” Water Meter
I
2” Reduced Pressure Zone Back Flow Preventer
Assembly & Precast Concrete Vault
J
3” HDPE Water Line
LF
DQ
K
3” HDPE Water Line by Pipe Bursting Method
(L-1 and WM-2)
L
2” HDPE Water Line
M
1” HDPE Water Line
N
6” Steel Pipe Bollards
O
Crushed Aggregate Backfill
TON
P
Reservoir Repair
TOTAL, ITEM 1, A – P: $____________________________
ALTERNATE ITEM 1: You may submit an alternate method for Item K, 3” HDPE water line. State the method that you intend to use, and the price.
K-Alt
3” HDPE Water Line (L-1 and WM-2).
Method: _________________________
Alternate method will be discussed in your proposal. See Section M.
OPTION ITEM 1:
Q
Well House Renovation, Including Pitless
Adaptor and Electric Service Relocation
OPTION ITEM 2:
R
Gutter Drains, 4” and 6” Sch. 40 PVC
Note to Contractors:
Hardcopy proposals must be delivered to the address shown on the front of the SF-1442 in block
7 by the receipt date and time as stated in Block 13A. Faxed proposals or changes to proposals will not be accepted. Emailed proposals or changes to proposals will not be accepted.
Recommended format for bid bonds is the SF-24. Original bid bond must be submitted with the bid. Failure to submit an original bid bond may result in your bid being found non-responsive.
Construction Wage Rates (formerly Davis-Bacon Wage Rates) applicable to this project are attached. Successful contractor is required to pay these rates at a minimum for the category of worker that will be used on this job. Contractor is required to submit weekly payrolls to project
COR, and to keep payrolls filed for three years subject to DOL review.
Registration in the System for Award Management (SAM) is not required for submission of a proposal; however registration must be completed within 5 days of notification of award. (See
FAR 52.204-7(d)). Access SAM at www.sam.gov/; registration is free.
http://www.sam.gov/
PART I - SECTION C - Description/Specifications/Statement of Work
DIVISION 100 – GENERAL SPECIFICATIONS
PROJECT DESCRIPTION: Tellico Ranger Station Water System Replacement. Replace the water distribution system with approximately 1000 LF of 3” diameter HDPE pipe, approximately 150 LF of 2” diameter HDPE pipe, and approximately 50 LF of 1” diameter HDPE pipe. Project includes well house renovation and underground gutter drain installation. Provide all materials, equipment, labor, transportation, supervision and incidentals to complete work according to project drawings and specifications. Contractor is responsible for maintaining water supply to District offices at project site during construction.
PRICE RANGE: $150,000 - $250,000.
SET-ASIDE: This project is 100% set-aside for Small Business
PROJECT LOCATION: Tellico Ranger District Office, 250 Ranger Station Road, Tellico Plains, TN
37385. From the intersection of Highway 68 and 165, drive approximately 5 miles east. Turn right onto
NFSR 210, drive approximately 0.25 miles. Ranger station entrance will be on left. Cell phone service may not be available at this location.
DIVISION 200 – TECHNICAL SPECIFICATIONS
(See Attached Specifications)
DIVISION 300 – INSPECTION AND ACCEPTANCE
A Contracting Officer’s Representative (COR) shall be designated in writing for this project. Inspection and acceptance will be made by the COR in accordance with Clause 52.246-12, Inspection of
Construction (see Section E).
DIVISION 400 – BASIS OF PAYMENT
Measurement will be based on quantities named in the schedule of items. Payment shall be made in accordance with Clause 52.232-27, Payments, at the established unit prices for work based on units completed by the contractor and accepted by the government. Submit invoice to the Project COR through the Invoice Processing Platform (IPP), registration required: https://www.ipp.gov/
Biobased Products
The Contractor shall utilize products and materials made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR).
Biobased products that are designated for preferred procurement under USDA’s BioPreferred program must meet the required minimum biobased content as stated at www.biopreferred.gov.
https://www.ipp.gov/ http://www.biopreferred.gov/
452.211-72 Statement of Work/Specifications. (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
452.211-73 Attachments to Statements of Work/Specifications. (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION D - Packaging and Marking
(for this solicitation, there are no clauses in this section)
SECTION E - Inspection and Acceptance
52.246-12 Inspection of Construction. (APR 1996)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not -
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the
Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the
Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes re-inspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may -
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the
Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting
Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
SECTION F - Deliveries or Performance
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 134 days after the effective date of the Notice to
Proceed. The time stated for completion shall include final cleanup of the premises.
52.242-14 Suspension of Work. (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting
Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
SECTION G - Contract Administration Data
452.215-73 Post-award Conference. (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled within 10 days after the date of contract award. The conference will be held at: Cherokee National Forest Supervisor’s Office, 2800 North Ocoee Street, Cleveland TN.
SECTION H - Special Contract Requirements
PART II – SECTION I - Contract Clauses
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/?q=browsefar
52.202-1 Definitions. (NOV 2013)
52.203-3 Gratuities. (APR 1984)
52.203-5 Covenant Against Contingent Fees. (MAY 2014)
52.203-6 Restrictions on Subcontractor Sales to the Government. (SEP 2006)
52.203-7 Anti-Kickback Procedures. (MAY 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (MAY 2011)
52.204-7 System for Award Management. (JUL 2013)
(a) Definitions. As used in this provision-
Data Universal Numbering System (DUNS) number means the 9-digit number assigned by Dun and
Bradstreet, Inc. (D&B) to identify unique business entities.
Data Universal Numbering System +4 (DUNS+4) number means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional System for Award Management records for identifying alternative Electronic Funds
Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.
Registered in the System for Award Management (SAM) database means that-
(1) The offeror has entered all mandatory information, including the DUNS number or the
DUNS+4 number, the Contractor and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14) into the
SAM database;
(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and
Points of Contact sections of the registration in the SAM database;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer
Identification Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and
(4) The Government has marked the record "Active".
(b)(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
https://www.acquisition.gov/?q=browsefar
(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "DUNS" or "DUNS +4" followed by the DUNS or DUNS +4 number that identifies the offeror's name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the SAM database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number-
(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the
United States; or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office.
The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information: (i) Company legal business. (ii) Tradestyle, doing business, or other name by which your entity is commonly recognized. (iii) Company Physical Street Address, City, State, and Zip Code. (iv) Company
Mailing Address, City, State and Zip Code (if separate from physical). (v) Company Telephone
Number. (vi) Date the company was started. (vii) Number of employees at your location. (viii)
Chief executive officer/key manager. (ix) Line of business (industry). (x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the SAM database in the time prescribed by the
Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering.
Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) Offerors may obtain information on registration at https://www.acquisition.gov.
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015)
52.211-18 Variation in Estimated Quantity. (APR 1984)
52.215-2 Audit and Records - Negotiation. (OCT 2010)
52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997)
Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:
1) The Schedule (excluding the specifications)
2) Representations and Other Instructions
3) Contract Clauses
4) Other Documents, Exhibits, and Attachments
5) The Specifications
52.217-5 Evaluation of Options (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the
Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
52.217-7 Option for Increased Quantity—Separately Priced Line Item (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 60 days from date of contract award. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011)
52.219-8 Utilization of Small Business Concerns. (OCT 2014)
52.219-14 Limitations on Subcontracting. (NOV 2011)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Applicability. This clause applies only to--
(1) Contracts that have been set aside or reserved for small business concerns or 8(a) concerns;
(2) Part or parts of a multiple-award contract that have been set aside for small business concerns or 8(a) concerns; and
(3) Orders set aside for small business or 8(a) concerns under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F).
(c) By submission of an offer and execution of a contract, the Offeror/Contractor agrees that in performance of the contract in the case of a contract for-
(1) Services (except construction). At least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the concern.
(2) Supplies (other than procurement from a non-manufacturer of such supplies). The concern shall perform work for at least 50 percent of the cost of manufacturing the supplies, not including the cost of materials.
(3) General construction. The concern will perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees.
(4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees.
52.222-3 Convict Labor. (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards - Overtime Compensation. (MAY 2014)
52.222-6 Construction Wage Rate Requirements. (MAY 2014)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (MAY 2014)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2017_2.html#wp1078150
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (MAY 2014)
52.222-21 Prohibition of segregated facilities. (APR 2015)
52.222-26 Equal Opportunity. (APR 2015)
52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)
52.222-35 Equal Opportunity for Veterans. (OCT 2015)
(a) Definitions. As used in this clause-
"Active duty wartime or campaign badge veteran," "Armed Forces service medal veteran," "disabled veteran," "protected veteran," "qualified disabled veteran," and "recently separated veteran" have the meanings given at FAR 22.1301.
(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-300.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified protected veterans, and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.
(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts of $150,000 or more unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the
Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
52.222-37 Employment Reports on Veterans. (FEB 2016)
52.222-50 Combating Trafficking in Persons. (MAR 2015)
52.222-55 Minimum Wages Under Executive Order 13658. (DEC 2015)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. (SEP
2013)
52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)
52.223-6 Drug-Free Workplace. (MAY 2001)
52.223-14 Acquisition of EPEAT(R)-Registered Televisions. (JUN 2014)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)
52.225-9 Buy American - Construction Materials. (MAY 2014)
Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Construction material means an article, material, or supply brought to the construction site by the
Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if-
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which non-availability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)).
The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph
(b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy
American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United
States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including- (A) A description of the foreign and domestic construction materials; (B) Unit of measure; (C) Quantity; (D) Price; (E) Time of delivery or availability; (F) Location of the construction project; (G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material.
However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of
Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material
Description
Unit of
Measure Quantity
Price
(Dollars)*
Item 1:
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
Item 2:
Foreign construction material ________ ________ ________
Domestic construction material ________ ________ ________
* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to
Iran-Representation and Certifications. (OCT 2015)
52.227-1 Authorization and Consent. (DEC 2007)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement. (DEC 2007)
52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007)
52.228-1 Bid Guarantee. (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.228-2 Additional Bond Security. (OCT 1997)
The Contractor shall promptly furnish additional security required to protect the Government and persons supplying labor or materials under this contract if -
(a) Any surety upon any bond, or issuing financial institution for other security, furnished with this contract becomes unacceptable to the Government;
(b) Any surety fails to furnish reports on its financial condition as required by the Government;
(c) The contract price is increased so that the penal sum of any bond becomes inadequate in the opinion of the Contracting Officer; or
(d) An irrevocable letter of credit (ILC) used as security will expire before the end of the period of required security. If the Contractor does not furnish an acceptable extension or replacement ILC, or other acceptable substitute, at least 30 days before an ILC's scheduled expiration, the Contracting officer has the right to immediately draw on the ILC.
52.228-11 Pledges of Assets. (JAN 2012)
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)
52.228-14 Irrevocable Letter of Credit. (NOV 2014)
52.228-15 Performance and Payment Bonds - Construction. (OCT 2010)
(a) Definitions. As used in this clause -
"Original contract price" means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection. (i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the U.S. Department of the Treasury, Financial Management Service, Surety Bond Branch, 3700 East
West Highway, Room 6F01, Hyattsville, MD 20782. Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
52.229-3 Federal, State, and Local Taxes. (FEB 2013)
52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2014)
52.232-17 Interest. (MAY 2014)
52.232-18 Availability of Funds. (APR 1984)
52.232-23 Assignment of Claims. (MAY 2014)
52.232-27 Prompt payment for construction contracts. (MAY 2014)
52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013)
52.233-1 Disputes. (MAY 2014)
52.233-3 Protest after Award. (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)
52.236-1 Performance of Work by the Contractor. (APR 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 15 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting
Officer determines that the reduction would be to the advantage of the Government.
52.236-2 Differing Site Conditions. (APR 1984)
(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the
Contracting Officer of -
(1) Subsurface or latent physical conditions at the site which differ materially from those indicated in this contract; or
(2) Unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.
(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.
(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in paragraph (a) of this clause for giving written notice may be extended by the Contracting Officer.
(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site;
(4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
(b) The Government assumes no responsibility for any conclusions or interpretations made by the
Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
52.236-5 Material and Workmanship. (APR 1984)
(a) All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the Contracting Officer, is equal to that named in the specifications, unless otherwise specifically provided in this contract.
(b) The Contractor shall obtain the Contracting Officer's approval of the machinery and mechanical and other equipment to be incorporated into the work. When requesting approval, the Contractor shall furnish to the Contracting Officer the name of the manufacturer, the model number, and other information concerning the performance, capacity, nature, and rating of the machinery and mechanical and other equipment. When required by this contract or by the Contracting Officer, the Contractor shall also obtain the Contracting
Officer's approval of the material or articles which the Contractor contemplates incorporating into the work.
When requesting approval, the Contractor shall provide full information concerning the material or articles.
When directed to do so, the Contractor shall submit samples for approval at the Contractor's expense, with all shipping charges prepaid. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection.
(c) All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting
Officer may require, in writing, that the Contractor remove from the work any employee the Contracting
Officer deems incompetent, careless, or otherwise objectionable.
52.236-6 Superintendence by the Contractor. (APR 1984)
At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
52.236-7 Permits and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .