Specifications Culvert Reconstruction PDF.pdf
PDF 621 KB Posted
- Attached to
- Recovery-Culvert Reconstruction Federal contract opportunity
- Solicitation number
- AG-4419-S-10-0365
About this file
PDF file for Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment No. 1 page 2x.pdf | ||
| Amendment 1 page 1 sf-30.pdf | ||
| Past Perf Questionnarie PDF.pdf | ||
| Specifications Culvert Reconstruction.docx | DOCX document | |
| EXPERIENCE AND PAST PERFORMANCE QUESTIONNAIRE.docx | DOCX document | |
| Project Plans.pdf | ||
| Final AG-4419-S-10-0365 1 .pdf | ||
| SF-1442 0365.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Supplemental Specifications December 2009
CIM-0920-17EW-416-0920-03 GMNF Aquatic Passage
FR54-0.2 Culvert Page 1 of 38 Reconstruction Project
SECTION C – FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS
The U.S. Department of Transportation, Federal Highway Administration, Standard
Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03, U.S.
Customary Units and its revisions are included by reference only. Also applicable, but not listed, is any other section or subsection of the included Specification(s) or any specific standard or specification referenced therein. The requirements contained in these specifications are hereby made a part of this Solicitation for Bid and any resulting contract.
A copy of the U.S. Department of Transportation, Federal Highway Administration, Standard
Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03, U.S.
Customary Units can be obtained at the following locations:
Superintendent of Documents
U.S. Government Printing Office
Internet: bookstore.gpo.gov
Phone: (toll free) 866.512.1800
Fax: 202.512.2250
Mail: Stop SSOP, Washington, DC 20402-0001
They can also be downloaded directly at the following website:
http://flh.fhwa.dot.gov/resources/pse/specs/
The following Forest Service Supplemental Specifications are revisions to the Standard
Specifications that incorporate specification changes or additions that are specific requirements and unique to this particular project. The specifications are herein modified as follows:
FR54-0.2 Culvert Page 2 of 38 Reconstruction Project
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
FR54-0.2 Culvert Page 3 of 38 Reconstruction Project
152 - Construction Survey and Staking
152.02 General
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations
Table 152-2 Cross section and slope stake tolerances
155 - Schedules for Construction Contracts
155 Delete
157 - Soil Erosion Control
157.03 General
203 - Removal of Structures and Obstructions
203.01 Description
203.04 Removing Material
204 - Excavation and Embankment
204.09 Preparing Foundation for Embankment Construction
204.10 Embankment Construction
204.11 Compaction
204.13 Sloping, Shaping, and Finishing
Table 204-2 Construction tolerances
204.13 Sloping, Shaping, and Finishing
204.14 Disposal of Unsuitable or Excess Material
204.15 Acceptance
Table 204-1 Sampling and Testing Requirements
208 - Structure Excavation and Backfill for Selected Major Structures
208.04 General
251 - Riprap
251.03 General
301 - Untreated Aggregate Courses
301 Title Change
301.01 Work
301.02 Material
301.03 General
301.04 Mixing and Spreading
FR54-0.2 Culvert Page 4 of 38 Reconstruction Project
301.05 Compacting
301.06 Surface Tolerance
301.08(b) Plasticity Index
Table 301-1 Field Density Requirements
Table 301-1—Acceptance Sampling and Testing Requirements
301.09 Measurement
552 - Structural Concrete
554 - Reinforcing Steel
603 - Structural Plate Structures
603.03 General
603.04 Erecting
627 – Sod
705 - Rock
705.02 Riprap Rock
718 - Traffic Signing and Marking Material
718.05 Aluminum Panels
713 – Roadside Improvement Material
713.09 Grubbing Material
FR54-0.2 Culvert Page 5 of 38 Reconstruction Project
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of
National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
FR54-0.2 Culvert Page 6 of 38 Reconstruction Project
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition
Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or
“design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96
Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36
CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
FR54-0.2 Culvert Page 7 of 38 Reconstruction Project
Figure 101-1—Illustration of road structure terms.
FR54-0.2 Culvert Page 8 of 38 Reconstruction Project
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
FR54-0.2 Culvert Page 9 of 38 Reconstruction Project
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
FR54-0.2 Culvert Page 10 of 38 Reconstruction Project
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
FR54-0.2 Culvert Page 11 of 38 Reconstruction Project
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
152 - Construction Survey and Staking
152.00_nat_us_08_05_2005
Description
152.01(c) Material.
Use required stake dimensions and materials. Pre-paint the top 2 inches of all stakes and lath, or mark them with plastic flagging. Use designated colors for paint or flagging. Mark all stakes with a stake pencil that leaves a legible imprint, or with waterproof ink.
Do not use aerosol spray paints.
Use moisture-resistant paper for survey notes. Keep notes in books with covers that will protect the contents and retain the pages in numerical sequence.
Construction Requirements
152.02 General.
Delete the first two sentences.
Add the following:
When indicated on the plans, a preliminary survey line has been established on the ground. The project location line is established by offsets from this preliminary line.
FR54-0.2 Culvert Page 12 of 38 Reconstruction Project
Delete second sentence in second paragraph and replace with the following:
Reestablish missing reference, control lines, or stakes as necessary to control subsequent construction staking operations
152.03 Survey and Staking Requirements.
(b) Roadway cross-sections.
Replace the first two sentences with the following:
Take roadway cross-sections normal to centerline. When the centerline curve radius is less than or equal to 200 feet, take cross-sections at a maximum centerline spacing of 25 feet. When the centerline curve radius is greater that 200 feet take cross-sections at a maximum centerline spacing of 80 feet.
c) Slope Stakes & References:
Replace section with the following:
Slope stakes and references. When required, locate slope stakes on designated portions of the road. Locate the slope stake catch points and use them to establish clearing limits and slope stake references.
Mark slope stakes with the station, the amount of cut or fill, the horizontal distance to centerline, and the slope ratios.
Place slope reference stakes at least 10 feet outside the clearing limit and mark with the offset distance to the slope stake. Place sight stakes when required.
Prior to clearing and grubbing operations, move the slope stake outside the clearing limit to the slope reference stake. After clearing and grubbing and before excavation, reset the slope stakes in their original position.
Use the designated method to establish the slope stake catchpoint.
• Method I—Computed Method. Use the template information shown in the plans or other
Government-provided data to calculate the actual location of the catchpoint. The slope stake “catchpoint distance” provided may be used as a trial location to initiate slope staking. Recatch slope stakes on any section that does not match the staking report within the tolerances established in Table 152-2.
• Method II—Catchpoint Measurement Method. Determine the location of slope stake catchpoints by measuring the catchpoint distances shown in the plans or other
Government-provided data.
(d) Clearing and grubbing limits.
FR54-0.2 Culvert Page 13 of 38 Reconstruction Project
Establish clearing limits on each side of the location line by measuring the required horizontal or slope distances shown in the stake notes. Mark the clearing limits with flagging or tags on trees to be left standing, or on lath. Make markings intervisible, and no more than 90 feet apart.
After establishing clearing limits, move the location line stake outside the clearing limits for station identification purposes, and mark it with horizontal distance to location line
(e) Centerline reestablishment.
Replace with the following:
Reestablish centerline from instrument control points. The maximum spacing between centerline points is 25 feet when the centerline curve radius is less than or equal to 200 feet. When the centerline curve radius is greater than 200 feet, the maximum distance between centerline points is 80 feet.
(g) Culverts.
Replace subsection with the following:
Set culvert reference stakes at all culvert locations. Set a culvert reference stake on the centerline of the culvert 10 feet from each end or beyond the clearing limit, whichever is greater. Record the following on culvert reference stakes:
(1) Diameter, actual field measured length, and type of culvert.
(2) The vertical and horizontal distance from the reference stake to the invert at the ends of the culvert.
(3) Station of actual point where culvert intersects centerline.
When required, stake headwall for culverts by setting a hub with a guard stake on each side of the culvert on line with the face of the headwall. Perform this work after clearing is completed.
152.03 (l) Miscellaneous Survey and Staking.
(11) Cattleguards
(12) Drain Dips
(13) Erosion Control Measures
FR54-0.2 Culvert Page 14 of 38 Reconstruction Project
Replace Table 152-1 with the following two tables:
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations.
Precision
Class
Minimum
Position
Closure Angular Accuracy (±)
L-Line Tangent
Control Points a
Vertical Closure b
A
(Bridges) 1/10,000
2 sets, direct/reverse
10 second rejection limit
N/A
0.02 ft or
0.02ft/1000ft c
B 1/5,000
2 sets, direct/reverse
20 second rejection limit
0.1 ft
0.02 ft or
0.02ft/1000ft
C 1/1,000 1 set, direct/reverse
1 minute rejection limit
0.2 ft 0.5ft/1000ft
D 1/300
Foresight and backsight;
15 minute rejection limit
0.4 ft 1.0ft/1000ft
E 1/100
Foresight and backsight;
30 minute rejection limit
0.8 ft 1.0ft/1000ft
a. Accuracy of offset measurement.
b. Determine vertical closures at intervals not to exceed 2000 ft as measured along centerline.
c. Use greater value.
FR54-0.2 Culvert Page 15 of 38 Reconstruction Project
Table 152-2 Cross section and slope stake tolerances.
Item Tolerances
A B C D E
Allowable deviation of cross-section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves
(±)2 o (±)3 o (±)3 o (±)5 o (±)5 o
Take cross-sections topography measurements so that variations in ground from a straight line connecting the cross-section points will not exceed
0.5 ft 1.0 ft 2.0 ft 2.0 ft 3.0 ft
Horizontal and vertical accuracy for cross-sections, in feet or percentage of horizontal distance measured from traverse line, whichever is greater.
0.1 ft or
0.4%
0.15 ft or 0.6%
0.2 ft or
1.0%
0.2 ft or
1.0%
0.3 ft or
1.0%
Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured from centerline or reference stake, whichever is greater.
Slope reference stakes and slope stakes. 0.1 ft or
0.4%
0.15 ft or 0.6%
0.2 ft or
1.0%
0.2 ft or
1.0%
0.3 ft or
1.0%
Clearing limits 1.0 ft 1.0 ft 1.0 ft 1.5 ft 2.5 ft
FR54-0.2 Culvert Page 16 of 38 Reconstruction Project
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
157 - Soil Erosion Control
157.03_nat_us_02_24_2005
157.03 General
Delete the entire subsection and replace with the following:
Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction.
Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted 30 days before intended use.
Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.
When erosion control measures are not functioning as intended, immediately take corrective action.
203 - Removal of Structures and Obstructions
203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
203.04_nat_us_02_18_2005
203.04 Removing Material.
Replace the fourth and fifth paragraphs with the following:
Where part of an existing culvert is removed, remove the entire culvert upstream from the removal. The remaining downstream culvert may be left in place if no portion of the culvert is within 12 inches of the subgrade, embankment slope, or new culvert or structure; and the culvert ends are sealed with concrete.
FR54-0.2 Culvert Page 17 of 38 Reconstruction Project
Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation.
Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.
204 - Excavation and Embankment
204.05_nat_us_02_18_2005
204.05 Conserved Topsoil
Delete the entire paragraph.
204.09_nat_us_03_02_2005
204.09 Preparing Foundation for Embankment Construction.
Delete subsection (a) and replace it with the following:
(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying.
Compact the ground surface according to Subsection 204.11.
204.10_nat_us_03_02_2005
204.10 Embankment Construction.
Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline.
(a) General.
Delete the third paragraph and add the following:
Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.
204.11_nat_us_04_11_2005
204.11 Compaction.
Delete the first paragraph and replace it with the following:
For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d) or (e) no sieve test is required.
Add the following compaction methods:
(d) Layer Placement Method (Hauling and Spreading Equipment). Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate
FR54-0.2 Culvert Page 18 of 38 Reconstruction Project compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.
(e) Layer Placement (Roller Compaction) Method. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, in when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
Delete section (d) and add the following:
(d) Finishing. For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed. For all roads, finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the tolerance class shown in table 204-2.
Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
For unsurfaced roads, use one of the following methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons. Roll at least 5 full-width passes or until visible displacement ceases.
(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.
Add Table 204-2—Construction Tolerances:
Table 204-2 Construction tolerances.
Tolerance Class (a)
A B C D E F G H I J K L M
Roadbed width (ft) +0.5 +0.5 +1.0 +1.0 +1.0 +1.0 +1.5 +1.0 +2.0 +2.0 +2.0 +2.0 +2.0
Subgrade elevation
(ft)
+0.1 +0.2 +0.2 +0.5 +0.5 +1.0 +1.0 +1.5 +2.0 +3.0 +2.0 +3.0 (c)
Centerline alignment
(ft)
+0.2 +0.2 +0.5 +0.5 +1.0 +1.0 `+1.5 +1.5 +2.0 +3.0 +3.0 +5.0 (c)
Slopes, excavation, and embankment (%
+3 +5 +5 +5 +5 +5 +10 +10 +10 +10 +20 +20 +20
FR54-0.2 Culvert Page 19 of 38 Reconstruction Project slope(b)
a. Maximum allowable deviation from construction stakes and drawings.
b. Maximum allowable deviation from staked slope measured from slope stakes or hinge points.
c. Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
(a) Sloping.
Add the following:
Slope rounding is not required on tolerance class D though M roads.
204.14_nat_us_03_02_2005
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material at designated sites or legally off of the project.
204.15_nat_us_02_07_2007
204.15 Acceptance
Table 204-1 Sampling and Testing Requirements.
Add the following note to the table:
(2) When compaction methods (d) or (e) are used AASHTO M 145, T 99, T 180, and T 310 are not required for earth embankment test methods.
FR54-0.2 Culvert Page 20 of 38 Reconstruction Project
208 - Structure Excavation and Backfill for Selected Major Structures
208.04_nat_us_08_05_2009
208.04 General.
Add the following to the end of the second sentence of the third paragraph:
"... to the CO a minimum of 5 days prior to beginning excavation work."
Add the following to the end of the third sentence of the third paragraph:
"...to the CO a minimum of 15 days prior to installation."
208.09 Foundation Preparation.
Add the following after the first paragraph:
The foundation elevation is defined as the bottom of footings, for spread footing placement; the bottom of the pile cap, for construction of pile foundations; and the toe of the wall, for construction of retaining walls, except wingwalls at bridges.
Replace all material from any over-excavation below the designated footing elevation with concrete, compacted gravel, or foundation fill at the direction of the CO.
When boulders or irregular, fractured, or seamed bedrock precludes excavation to the designated footing elevation without further loosening of previously solid material, the CO may order removal of such loose material and allow payment for concrete, gravel, or structural backfill that is required to restore foundation material to the designated elevation
208.13 Measurement.
Add the following to the second paragraph:
(f) Material excavated to construct end walls or wing walls which lie outside the excavation limits specified above.
Add the following paragraph:
Foundation over-excavation and the resulting replacement material will not be measured for payment unless the CO determines the over-excavation was unavoidable because of the nature of the material.
FR54-0.2 Culvert Page 21 of 38 Reconstruction Project
251 - Riprap
251.03_nat_us_08_05_2009
251.03 General.
Place riprap under or adjacent to structures before placing prefabricated superstructure units or constructing superstructure falsework unless otherwise approved by the CO.
The color of the stone shall be either earth tones or medium to dark gray. White stone is not acceptable.
251.08 Measurement.
Payment for excavation and embankment required for placement of riprap is indirectly included in the pay item for riprap.
301 - Untreated Aggregate Courses
301.00_nat_us_03_03_2005
301 Title Change.
Change the title to: Section 301 Aggregate Courses
301.01_nat_us_03_03_2005
301.01 Work.
Add the following:
Work includes producing aggregate by pit-run, grid rolling, screening, or crushing methods, or placing Government-furnished aggregate. Work may include additive mineral filler, or binder.
301.02_nat_us_05_16_2005
301.02 Material.
Bentonite 725.30
FR54-0.2 Culvert Page 22 of 38 Reconstruction Project
Calcium Chloride Flake 725.02
Lignon Sulfonate 725.20
Magnesium Chloride Brine or Calcium Chloride Liquid 725.02
301.03_nat_us_09_14_2005
301.03 General.
Add the following:
Written approval of the roadbed is required before placing aggregate.
For pit run or grid-rolled material, furnish material smaller than the maximum size. No gradation other than maximum size will be required for pit-run or grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size. After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
Provide additives or binder, if required, at the proportions specified.
Develop and use Government furnished sources according to Section 105.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to
Section 320. Establish stockpile sites at locations approved. Clear and grub stockpile sites according to Section 201.
301.04_nat_us_03_03_2005
301.04 Mixing and Spreading.
Delete the first sentence of the first paragraph and add the following:
Ensure that aggregate and any required additives, water, mineral filler, and binder are mixed by the specified method except, if crushed aggregate products are being produced and mineral filler, binder, or additives are required, uniformly blend following crushing. Control additive proportions to 0.5 percent dry weight.
(a) Stationary Plant Method. Mix the aggregate with other required materials in an approved mixer. Add water during the mixing operation in the amount necessary to provide the moisture content for compacting to the specified density. After mixing, transport the aggregate to the jobsite while it contains the proper moisture content, and place it on the roadbed or base course using an aggregate spreader.
(b) Travel Plant Method. After placing the aggregate for each layer with an aggregate spreader or windrow-sizing device, uniformly mix it with other required materials using a traveling mixing plant. During mixing, add water to provide the necessary moisture content for compacting.
(c) Road Mix Method. After placing the aggregate for each layer, mix it with other required materials at the required moisture content until the mixture is uniform throughout. Mix aggregate, water, and all other materials until a uniform distribution is obtained.
FR54-0.2 Culvert Page 23 of 38 Reconstruction Project
Spread the aggregate in a uniform layer, with no segregation of size, and to a loose depth that will provide the required compacted thickness.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
Route and distribute hauling and leveling equipment over the width and length of each layer.
301.05_nat_us_05_17_2005
301.05 Compacting
Delete and replace with the following:
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box
7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box
7669, Missoula, MT 59807).
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
FR54-0.2 Culvert Page 24 of 38 Reconstruction Project
301.06_nat_us_03_03_2005
301.06 Surface Tolerance.
Add the following:
Thickness and Width requirements:
The maximum variation from the compacted specified thickness is ½ inch. The compacted thickness is not consistently above or below the specified thickness and the average thickness of
4 random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness.
The maximum variation from the specified width will not exceed +12 inches at any point. The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.
301.08_nat_us_03_30_2005
301.08(b) Plasticity Index.
Add the following to the first sentence:
“and under 703.05(c)(1)”.
FR54-0.2 Culvert Page 25 of 38 Reconstruction Project
301.08_nat_us_02_07_2007
Table 301-1 Field Density Requirements.
Table 301-1: Delete laboratory and field density requirements for base, subbase, and surfacing and replace with the following:
Material or Product
Type of
Acceptance
(Subsection)
Characteristi c
Category Test Methods
Specification s
Sampling
Frequency
Point of
Sampling
Split
Sample
Reporting
Time
Base and
Subbase
Measured and tested conformance (Subsection
106.04)
Moisture Density ---
Method C --- AASHTO T 99 1 per type and source of material
Source of material
Yes Before using in work
Method C-1 --- R-1 Marshall “ “ “ “
Method D --- AASHTO T 180 “ “ “ “
Method D-1 --- R-1 Marshall “ “ “ “
Compaction ---
Method C, C-1, D, D-1
--- AASHTO T 310 or other approved procedures
1 per 500 t In-place --- Before placing the next layer
Surfacing Measured and tested conformance (Subsection
106.04)
Moisture Density
Method C-1 --- R-1 Marshall “ “ “ Before using in work
Method D --- AASHTO T 180 “ “ “ “
Method D-1 --- R-1 Marshall “ “ “ “
Compaction
Method C, C-1, D, D-1
--- AASHTO T 310 or other approved procedures
1 per 500 t In-place --- Before placing the next layer
301.08_nat_us_03_03_2005
Table 301-1: Add the following:
FR54-0.2 Culvert Page 26 of 38 Reconstruction Project
Table 301-1—Acceptance Sampling and Testing Requirements.
Material or
Product
Type of
Acceptance
(Subsection)
Characteristi c
Category Test Methods
Specification s
Sampling
Frequency
Point of
Sampling
Split
Sample
Reporting
Time
Subbase & Base
Courses L, M, N, O, P, Q, R
Measured and tested conformance (Subsection 106.04)
Plastic Limit - AASHTO T 90 1 per each 1,000
T
From the windrow or roadbed after processing
Yes 4 Hours
Table 301-1—Acceptance Sampling and Testing Requirements.
Material or
Product
Type of
Acceptance
(Subsection)
Characteristi c
Category Test Methods
Specification s
Sampling
Frequency
Point of
Sampling
Split
Sample
Reporting
Time
Aggregate Width Measured and tested conformance
(Subsection 106.04)
Width - - 4 per each 0.5 mi
Roadbed after processing
- 4 Hours
Aggregate Thickness Measured and tested conformance (Subsection 106.04)
Thickness - - 4 per each 0.5 mi
Roadbed after processing
- 4 Hours
Additive Measured and tested conformance
(Subsection 106.04)
Amount of Additive - 1 per each 1,000
T
From the windrow or roadbed after processing
No 4 Hours
FR54-0.2 Culvert Page 27 of 38 Reconstruction Project
301.09_nat_us_07_07_2005
301.09 Measurement.
Replace the second paragraph with the following:
Measure aggregate by cubic yard compacted in place when payment is by contract quantities.
301.10_nat_us_03_03_2005
301.10 Payment
Delete the following:
adjusted according to Subsection 106.05
552 - Structural Concrete
552.02_nat_us_06_20_2007
Material
552.02 Add the following:
Anchor bolts 717.01
Dowels 717.17
Epoxy resin adhesives 725.21
High strength non-shrink grout 701.02
Mortar 701.02
Portland cement 701.01
Sealants, fillers, seal, and sleeves 712.01
552.03 Composition (Concrete Mix Design).
Delete Tables 552-1, 2, and 3 and replace with the following:
Table 552-1
Composition of Concrete
Class of
Concrete
Minimum
Cement
Content
(pound per cubic yard)
Maximum
W/C
Ratio
Slump (1)
(inches)
Maximum
Nominal Coarse
Aggregate
Size (5)
A 611 0.49 2 to 4 1½
A(AE) 611 0.44 1 to 4 1½
B 517 0.58 2 to 4 2½
B(AE) 517 0.58 2 to 4 2½
FR54-0.2 Culvert Page 28 of 38 Reconstruction Project
C 658 0.49 2 to 4 ¾
C(AE) 658 0.44 1 to 3 ¾
D(AE)
(2)
611 0.40 1 to 3 1½
E(AE)
(3)
611 0.40 4 to 6 (4)
¾
P
(Prestressed) 658 0.44 0 to 4 1
P(AE) 658 0.44 0 to 4 1
Seal 658 0.54 4 to 8 1½ (1) Maximum slump is 8 inches if approved mix design includes a high-range water reducer.
(2) Concrete with a water reducing and retarding admixture conforming to AASHTO
M 194, type D.
(3) A latex modified concrete with 0.037 gallons of modifier per pound of cement.
(4) Measure the slump 4 to 5 minutes after the concrete is discharged from the mixer.
(5) Meeting the processing requirements of AASHTO M43, Table 1 – Standard
Sizes of Processed Aggregate.
(6)
Use Class P (AE) concrete in the entire depth of the top flange of all multi-beam bridge girders. In lieu of this, Class P (AE) concrete may be used for fabrication of the entire girder, and throughout the entire depth of prestressed slabs. In all cases, furnish concrete meeting the 28 day specified minimum concrete strength requirements for the prestressed members as shown on the plans, unless otherwise specified.
Table 552-2
Minimum Air Content for Air Entrained Concrete
Nominal Maximum
Aggregate Size (1)
As Delivered
Minimum Air
Content
(2) (3)
2½ inch 3.5
2 inch 3.5
1½ inch 4.0
1 inch 4.5
¾ inch 4.5
½ inch 5.5 (1) Meeting the processing requirements of AASHTO
M 43, Table 1 – Standard Sizes of Processed
Aggregate.
(2) These air contents apply to the total mix. When testing these concretes, aggregates larger than 1½ inches are removed by handpicking or sieving, and air content is determined on the minus 1½-inch fraction of the mix. Air content of the total mix is computed
FR54-0.2 Culvert Page 29 of 38 Reconstruction Project from the value determined on the minus 1½-inch fraction.
(3) For P(AE) concrete, the as delivered minimum air contents may be reduced 1.0 % and the maximum air content is 6.0 %
Table 552-3
Required Average Compressive Strength (1)
Specified Compressive
Strength (f’c)
(psi)
Required Average
Compressive Strength
(f’cr)
(psi)
Less than 3000 f’c + 1000
3000 to 5000 f’c + 1200
Over 5000 1.10f’c + 700
(1) Use this table when there is not enough data available to establish a standard deviation
Delete the first paragraph after Table 552-2 and replace with the following:
Submit written concrete mix designs for approval at least 30 calendar days before production.
Add the following under the list of items to be included in the mix design submittal:
(y) Evaluation of potential aggregate reactivity
552.08 Delivery.
(a) Truck mixer/agitator.
Add the following:
Do not exceed 130 total revolutions at mixing speed, including both initial mixing and remixing. Do not exceed 300 total revolutions, including both mixing and agitating speed.
552.09 Quality Control of Mix.
Add the following after the first paragraph:
FR54-0.2 Culvert Page 30 of 38 Reconstruction Project
At least 2 weeks prior to the start of concrete placement operations, arrange a pre-concrete placement conference. Coordinate attendance with the CO and any applicable subcontractors.
Be prepared to discuss and/or submit the following:
(1) Proposed concrete placement schedule.
(2) Review approved concrete mix design and determination of batch weights.
(3) Discuss Section 153, Contractor Quality Control, minimum frequency schedule for process control sampling and testing (to be performed by the Contractor).
(4) Discuss batching, mixing, placing, and curing requirements.
(5) Discuss Subsections 106.03, Certification, and 106.05, Statistical Evaluation of
Material for Acceptance.
552.11 Handling and Placing Concrete.
Add the following after the forth paragraph:
Use an approved form release agent to produce a minimum of staining, air holes, and hydration discoloration.
552.12 Construction Joints.
Add the following at the end of the first paragraph:
Provide form cleanout ports at construction joints.
552.18 Loads on New Concrete Structures.
Add the following paragraph:
Do not allow public traffic on the bridge until approaches, curbs, and bridge rail are completed and in-place. Erect barricades at each end of bridge spans when road approaches allow vehicles to drive directly onto the structure.
FR54-0.2 Culvert Page 31 of 38 Reconstruction Project
554 - Reinforcing Steel
554.03_nat_us_06_20_2007
554.03 Order Lists.
Delete the first paragraph and replace with the following:
Do not submit order lists or bending diagrams for approval.
554.08 Placing & Fastening.
Delete the first sentence and replace with the following:
Place, fasten, and support the bars according to the CRSI Manual of Standard Practice. Use precast concrete blocks or metal supports, but only use precast mortar blocks in areas permanently hidden from view in the completed structure.
Measurement
554.11 Method.
Add the following to the end of the second paragraph:
Do not measure or include reinforcing steel fabricated into the prestressed member.
603 - Structural Plate Structures
603.03_nat_us_03_02_2005
603.03 General.
Add the following:
Do not place or backfill structure until the CO has approved in writing the excavation and foundation. Submit four sets of shop drawings of the long-span structure to the CO at least 21 days before planned construction. Accompany shop drawings with all calculations used to determine the size, shape, location, and spacing of stiffening ribs, thrust beams, or other special structural features.
603.04_nat_us_03_02_2005
603.04 Erecting.
Add to the third paragraph:
FR54-0.2 Culvert Page 32 of 38 Reconstruction Project
Torque all bolts before beginning the backfill.
627 – Sod
Section 627 shall remain in its entierty except as modified below:
627.02 – This section is modified as follows:
627.02 Conform to the following Subsections:
Agricultural limestone 713.02
Fertilizer 713.03
Grubbing Material 713.09
Pegs for sod 713.11
Sod 713.10
Water 725.01
627.06 – This section is modified as follows:
Add the following after section (c) Spot sod.
(d) Grubbing Material. Approved grubbing material shall be placed as shown on the Plans or as directed by the Engineer. Spreading shall not be done when grubbing material is frozen, excessively wet, or otherwise in a condition detrimental to the work. The grubbing material shall be spread evenly to a depth of approximately 300 mm (12 inches) or to the depth shown on the Plans or directed by the Engineer. All large stones and other unsuitable material shall be removed from the area, as directed by the Engineer. Grubbing material stockpile areas shall be graded, seeded, and left in a neat and presentable.
Stone and rock fill slopes to be covered with grubbing material shall be shaped in reasonably close conformity with the grades and typical cross-sections shown on the Plans or directed by the Engineer.
FR54-0.2 Culvert Page 33 of 38 Reconstruction Project
705 - Rock
705.02 Riprap Rock.
Delete Table 705-1 and replace it with the following:
Gradation Requirements for Riprap
Class Percent of
Rock by Mass
Mass
(pounds)
Approximate Cubic
Dimension b,c
20 22 to 33 6 to 8
30 11 to 22 5 to 6
40 1 to 11 2 to 5
0 to 1 0 to 2
20 55 to 110 8 to 10
30 22 to 55 6 to 8
40 2 to 22 3 to 6
0 to 2 0 to 3
20 220 to 330 14 to 16
30 110 to 220 10 to 14
40 11 to 110 5 to10
0 to 11 0 to 5
20 550 to 770 18 to 20
30 220 to 570 14 to 18
40 22 to 220 6 to 14
0 to 22 0 to 6
4a
20 770 to1353 20 to 24
30 330 to 770 16 to 20
40 33 to 330 7 to16
0 to 33 0 to 7
20 1540 to 2200 26 to 28
30 1100 to 1540 20 to 26
40 55 to 1100 8 to 20
0 to 55 0 to 8
20 1870 to 3520 28 to 34
30 1100 to 1870 22 to 28
40 110 to 1100 10 to 22
0 to 110 0 to 10
20 4400 to 5940 35 to 39
30 2200 to 4400 28 to 35
40 220 to 2200 14 to 28
0 to 220 0 to 14
20 7000 to 10000 42 to 47
30 4000 to 7000 35 to 42
40 400 to 4000 16 to 35
0 to 400 0 to 16
FR54-0.2 Culvert Page 34 of 38 Reconstruction Project
(a) Furnish spall and rock fragments graded to provide a stable dense mass.
(b) The volume of a rock with these cubic dimensions has a mass approximately equal to the specified rock mass.
(c) Furnish rock with breadth and thickness at least one-third its length.
(d) The color of the stone shall be either earth tones or medium to dark gray. White stone is not acceptable.
718 - Traffic Signing and Marking Material
718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.
713 – Roadside Improvement Material
713.09 Grubbing Material.
Delete section 713.09 and replace it with the following:
Grubbing Material for use on stone fill along streams shall consist of grubbed or stripped earth material containing roots of native stream bank vegetation. Material for use on rock fill slopes shall consist of grubbed or stripped earth material containing roots (not necessarily from native stream bank vegetation) which will promote the growth of vegetation.
FR54-0.2 Culvert Page 35 of 38 Reconstruction Project
Project Funding Source Sign Assembly American Recovery And Reinvestment Act Sign Layout
DetailsUSFS ProjectsFOR USE ON LOW SPEED
ROADS OR NON-ROAD PROJECTS
PROJECT FUNDING SOURCE SIGN
NOTE: SIGN SHALL NOT BE INSTALLED WITHOUT PROJECT FUNDING SOURCE PLAQUE (SEE SHEET 5).
* Increase character spacing 50% ** See Pictograph page 6 *** See Pictograph page 7
COLORS: LEGEND, BORDER — WHITE (RETROREFLECTIVE)
BACKGROUND — GREEN (RETROREFLECTIVE)
A B C D E F G H J K L M N P
60 36 0.75 3 3 C 2.25 4 C 1.625 3 C* NA NA
14.39
3 5.416
42 27 0.5 2.5 2 C 1.75 3 C 1.5 2 C* NA NA 9.60 2 3.681
Q R S T U V W X Y Z AA BB CC DD
7.044 4.02 5.78 24.71 1.371 2.629 23.45
3.406 23.38 11.23
4 8.144 2 10
4.742 2.68 3.85 15.86
1.207 1.792 15.27
2.271 15.45
7.369 3 5.087
1.5 7
EE FF GG
4 1.5 1.5
3 1.125 1.125
FR54-0.2 Culvert Page 36 of 38 Reconstruction Project
Project Funding Source Sign Assembly American Recovery And Reinvestment Act
Sign Layout Details USFS Projects
FOR USE ON LOW SPEED ROADS
OR NON-ROAD PROJECTS
PROJECT FUNDING SOURCE PLAQUE
NOTE: SIGN SHALL NOT BE INST ALLED * See Standard Highway Signs WITHOUT SIGN (SEE SHEET 4). Page 6-59 for symbol design
A B C D E F G H J K L M N P
60 12 0.312 0.437 2 3 C 11.174 10.18
8.640 6.64 3 17.11 3.25 4.382
42 9 0.187 0.312 1.67 2 C 8.303 7.843 4.853 5.334 2 11.40
2.5 2.922
Q R S T U V W X Y Z
10.50
1.5 12 0.375 0.5 0.75 5.5 4 1.5 6
7.005 1.125 9 0.375 0.5 0.5 3.5 3 1.5 4.5
COLORS
LEGEND, BORDER — BLACK
BACKGROUND — ORANGE (RETROREFLECTIVE)
FR54-0.2 Culvert Page 37 of 38 Reconstruction Project
Project Funding Source Sign Assembly American Recovery And Reinvestment Act
Sign Layout Details USFS Projects
RECOVERY
Vector-Based, Vinyl-Ready Pictograph
COLORS: LEGEND, OUTLINE — WHITE (RETROREFLECTIVE)
BORDER — BLUE (RETROREFLECTIVE)
BACKGROUND (UPPER) — BLUE (RETROREFLECTIVE)
BACKGROUND (LOWER RIGHT) — RED (RETROREFLECTIVE)
BACKGROUND (LOWER LEFT) — GREEN (RETROREFLECTIVE)
FR54-0.2 Culvert Page 38 of 38 Reconstruction Project
4/2/2009
Project Funding Source Sign Assembly American Recovery And Reinvestment Act
Sign Layout Details USFS Projects
FOREST SERVICE SHIELD
NOTE: Shield artwork supplied by Government.
Shield is also available in decals sizes 2, 2 ½, 3, 4, 5, 6, and 8 inches.
COLORS: LEGEND, OUTLINE — WHITE (RETROREFLECTIVE)
BORDER — WHITE (RETROREFLECTIVE)
BACKGROUND — BROWN (RETROREFLECTIVE)