GenDec 6-24-16 RFQ.docx
DOCX document 21 KB Posted
- Attached to
- Kitchen exhaust and HVAC distribution system Federal contract opportunity
- Solicitation number
- AG-32SD-S-16-0032
About this file
wage determination applicable to this project
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S-16-0032 clz-prov rev7-19-16a.doc | DOC document | |
| S-16-0032 clz-prov rev7-19-16.doc | DOC document | |
| S-16-0032 clz-prov _rev_7-15-16.doc | DOC document | |
| SF18 _S-16-0032 _rev_7-15-16.pdf | ||
| Sensory_Lab_specifications.pdf | ||
| S-16-0032 clz-prov 7-14-16.doc | DOC document | |
| Sensory_Lab_drawing.pdf | ||
| SF18 _S-16-0032.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ No. AG-32SD-S-16-0032 Kitchen Exhaust & HVAC Air Distribution System Clay Center, NE
General Decision Number: NE160080 06/24/2016 NE80
Superseded General Decision Number: NE20150080
State: Nebraska
Construction Type: Building
Counties: Blaine, Clay, Franklin, Garfield, Greeley, Hamilton, Harlan, Kearney, Loup, Merrick, Nance, Nuckolls, Phelps, Sherman, Valley, Webster and Wheeler Counties in Nebraska.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/08/2016 1 01/22/2016 2 04/01/2016 3 06/24/2016
BOIL0083-002 01/01/2015
Rates Fringes
BOILERMAKER......................$ 34.76 27.06
ELEC0265-003 03/01/2016
Rates Fringes
ELECTRICIAN
Zone 1......................$ 27.52 10.77 Zone 2......................$ 27.82 10.77 Zone 3......................$ 28.12 10.77 Zone 4......................$ 28.52 10.77
ZONE DEFINITIONS:
Zone 1: 0 to 35 miles from the main Post Office in Lincoln Zone 2: 36 to 50 miles from the main Post Office in Lincoln Zone 3: 51 to 75 miles from the main Post Office in Lincoln Zone 4: 76 miles and over from the main Post Office in Lincoln
ELEV0028-001 01/01/2016
Rates Fringes ELEVATOR MECHANIC................$ 40.94 29.985+a+b
FOOTNOTE:
a. Vacation Pay: 8% for persons with 5 or more years of service, 6% for persons with less than 5 years of service.
b. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.
IRON0021-006 06/01/2015
CLAY, FRANKLIN, GREELEY, HAMILTON, HARLAN, KEARNEY, MERRICK, NANCE, NUCKOLIS, PHELPS, SHERMAN, VALLEY AND WEBSTER COUNTIES Rates Fringes
IRONWORKER, STRUCTURAL...........$ 27.20 14.37
IRON0021-007 05/01/2015
BLAINE, GARFIELD, LOUP AND WHEELER COUNTIES
Rates Fringes
IRONWORKER, STRUCTURAL...........$ 22.21 13.93
LABO1140-010 01/01/2015
Rates Fringes LABORER (Mason Tender, Brick & Hod)...........................$ 17.98 9.40
PLUM0016-009 08/09/2015
Rates Fringes PLUMBER (Excludes HVAC Pipe and System Installation).........$ 33.33 13.31
* PLUM0464-017 05/29/2016
Rates Fringes PIPEFITTER (Includes HVAC Pipe and System Installation)....$ 35.04 16.44
SHEE0003-006 07/01/2015
Rates Fringes SHEET METAL WORKER (Includes HVAC Duct Installation)..........$ 32.89 14.93
SUNE2012-017 04/19/2012
Rates Fringes
BRICKLAYER.......................$ 26.74 1.83
CARPENTER........................$ 17.53 2.21
CEMENT MASON/CONCRETE FINISHER...$ 17.80 1.34
LABORER: Common or General......$ 12.39 2.40
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 21.82 2.22 OPERATOR: Loader.................$ 16.58 0.94
ROOFER...........................$ 14.52 0.65
SPRINKLER FITTER (Fire Sprinklers)......................$ 19.07 4.15 TRUCK DRIVER: Dump, Lowboy and Tandem.......................$ 14.56 1.68 WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey.
Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for thisclassification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including request for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
File details come from the government source that posted it. Updated .