AG-05K3-S-14-0013-Attachments.pdf
PDF 6 MB Posted
- Attached to
- Swift Creek Bridge Maintenance Federal contract opportunity
- Solicitation number
- AG-05K3-S-14-0013
About this file
Solicitation Attachments
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment1.pdf | ||
| AG-05K3-S-14-0013.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-05K3-S-14-0013 Attachments stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text Dwg. 2 of 11
Typewritten Text
Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text
Typewritten Text Dwg. 4 of 11
Typewritten Text Dwg. 5 of 11
Typewritten Text Dwg. 6 of 11
Typewritten Text Dwg. 7 of 11
Typewritten Text Dwg. 8 of 11 stbecker Typewritten Text
Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text stbecker Typewritten Text Dwg. 9 of 11 stbecker Typewritten Text msodaro Text Box Brush clean deck and clean bridge drain system.
Typewritten Text Dwg. 10 of 11 msodaro Text Box Note: This plan sheet is for information purposes. Note existing bridge drainage system to be cleaned.
UNITED STATES DEPARTMENT OF AGRICULTURE
FOREST SERVICE- REGION 6
GIFFORD PINCHOT NATIONAL FOREST
MOUNT ST HELENS NATIONAL VOLCANIC MONUMENT
GP TEMPORARY SIGN PLAN DETAIL
USFS 90 ROAD MP 4.2 SWIFT CREEK BRIDGE REPAIR 2013
AG-05K3-S-14-0013 Attachments stbecker Typewritten Text Dwg. 11 of 11
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
155 - Schedules for Construction Contracts
155 Delete
157 - Soil Erosion Control
157.03 General
203 - Removal of Structures and Obstructions
203.01 Description
203.04 Removing Material
322 - Minor Aggregate Courses
404 - Minor Hot Asphalt Concrete
404.02 Composition of Mix (Job-Mix Formula)
404.04 Weather Limitations
404.06 Placing
404.07 Compacting (a)
404.09 Acceptance
Table 404-1. Sampling and Testing Requirements
552 - Structural Concrete
Table 552-3 Required Average Compressive Strength
554 - Reinforcing Steel
555 - Steel Structures
617 - Guardrail
635 - Temporary Traffic Control
635.03 General
701 - Cement
701.02 Masonry and Mortar Cement
703 - Aggregate
703.05 Subbase, Base, Surface Course, and Screened Aggregate
Table 703-2 Correction
Table 703-2 Correction
703.10(e) Flakiness Index
703.10(i) Adherent Coating
709 - Reinforcing Steel and Wire Rope
712 - Joint Material
712.01 Sealants, Fillers, Seals, and Sleeves
712.01 Sealants, Fillers, Seals, and Sleeves
717 - Structural Metal
717.01 Structural Steel
718 - Traffic Signing and Marking Material
718.02 Reserved
718.02 Protective Overlay Film and Edge Film
718.05 Aluminum Panels
718.08 (b)(2)(c)Signpost - Square tubular steel posts
718.14 (g)Waterborne Traffic Paint - Daylight reflectance
718.15 (a)Epoxy Markings Pigments
718.15 (g)Epoxy Marking - Drying Time
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
157 - Soil Erosion Control
157.03_nat_us_02_24_2005
157.03 General
Delete the entire subsection and replace with the following:
Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction.
Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted 30 days before intended use.
Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.
When erosion control measures are not functioning as intended, immediately take corrective action.
203 - Removal of Structures and Obstructions
203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
203.04_nat_us_02_18_2005
203.04 Removing Material.
Replace the fourth and fifth paragraphs with the following:
Where part of an existing culvert is removed, remove the entire culvert upstream from the removal. The remaining downstream culvert may be left in place if no portion of the culvert is within 12 inches of the subgrade, embankment slope, or new culvert or structure; and the culvert ends are sealed with concrete.
Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation.
Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.
322 - Minor Aggregate Courses
322.00_nat_us_10_14_2011
Description
322.01 This work consists of constructing one or more courses of aggregate on a prepared surface. Work includes producing aggregate by grid rolling, screening, or crushing methods, or placing pit-run or Government-furnished aggregate.
Surface aggregate grading is designated as shown in Table 703-3.
Subbase and base aggregate grading is designated as shown in Table 703-2.
Screened aggregate grading is designated as shown in Table 703-16.
Material
322.02 Conform to the following Subsections:
Aggregate 703.05 Water 725.01
Construction Requirements
322.03 General. Prepare the surface on which the aggregate course is placed according to Section 204 or 303 as applicable.
Request approval of the roadbed in writing before placing aggregate.
Develop, haul, and apply water in accordance to Section 170.
Submit target values within the gradation ranges shown in Table 703-2 or 703-3 for the required grading. After reviewing the proposed target values the CO will determine the final values for the gradation and notify the Contractor in writing.
No quality requirements or gradation other than maximum size will be required for pit run and grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size.
After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at approved locations.
322.04 Mixing and Spreading. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for the specified compaction method. Spread and shape the mixture on the prepared surface in a uniform layer with no segregation of size, and to a loose depth that will provide the required compacted thickness.
Do not place in layers exceeding 6 inches in compacted thickness for aggregate base and surface courses or twice the maximum particle size for screened aggregate. When more than one layer is necessary, compact each layer according to Subsection 322.05 before placing the next layer. Route hauling and leveling equipment uniformly over the full width.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
322.05 Compacting. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Removed.
Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
Compaction G. Removed.
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
322.06 Construction Tolerance. If grade finishing stakes are required, finish the surface to within ±0.10 feet from staked line and grade elevation.
If grade finishing stakes are not required, shape the surface to the required template and check the surface with a 10-foot straightedge. Defective areas are surface deviations in excess of 1/2 inch in 10 feet between any two contacts of the straightedge with the surface.
Correct all defective areas by loosening the material, adding or removing material, reshaping, and compacting.
Ensure that the compacted thickness is not consistently above or below the specified thickness.
The maximum variation from the compacted specified thickness is ½ inch.
Ensure that the compacted width is not consistently above the specified width. The maximum variation from the specified width will not exceed +12 inches at any point.
322.07 Maintenance. Maintain the aggregate course to the correct line, grade, and cross-section by blading, watering, rolling, or any combination thereof until placement of the next course.
Correct all defects according to Subsection 322.06.
322.08 Acceptance. See Table 322-1 or Table 322-2 as applicable, for sampling and testing requirements.
Aggregate gradation and surface course plasticity index will be evaluated under Subsection 106.04.
If the aggregate is obtained from a Government stockpile then the above characteristics will be evaluated under Subsection 106.02. Other aggregate quality properties will be evaluated under Subsections 106.02 and 106.04. Placement of aggregate courses will be evaluated under Subsections 106.02 and 106.04.
The allowable upper and lower aggregate gradation limits are the Target Value plus or minus the allowable deviations shown in Tables 703-2 and 703-3.
The allowable upper and lower Plasticity index limits for surface courses are stated in 703.05(b).
Preparation of the surface on which the aggregate course is placed will be evaluated under Section 204 or 303 as applicable.
Measurement
322.09 Measure the Section 322 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.
Measure square yard width horizontally to include the top of aggregate width including designed widening. Measure the square yard length horizontally along the centerline of the roadway.
If the measurement for aggregate is by cubic yard using contract quantities then measure aggregate by the cubic yard in-place once compacted, otherwise measurement for aggregate by the cubic yard is measured by the cubic yard in the hauling vehicle.
Measure thickness perpendicular to the grade of the travelway.
Measure width perpendicular to the centerline.
Payment
322.10 The accepted quantities will be paid at the contract price per unit of measurement for the Section 322 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
T ab le
-1
Sa m pl in g an d
T es tin g
R eq ui re m en ts
R ep or tin g T im e
B ef or e us in g in w or k h ou rs
Sp lit pl e
Y es
, w he n re qu es te d
“ “ “ Y es
Po in t o f
Sa m pl in g
So ur ce o f m at er ia l
Fr om w in dr ow o r ro ad be d af te r pr oc es si ng o r fro m a pp ro ve d cr us he r s am pl in g de vi ce pl in g Fr eq ue nc y pe r t yp e so ur ce o f m at er ia l pe r d ay t M et ho ds ec ifi ca tio ns
A
SH
TO
T
A A
SH
TO
T
SH
TO
T
ST
M D
A A
SH
TO
C at eg or y ha ra ct er is tic
LA
a br as io n
(c oa e)
So di um su lfa te so un dn es s l os s
(c oa rs e fi ne
D ur ab ili ty in de x
(c oa rs e fi ne
Fr ac tu re d fa ce s
Sa m pl e
T yp of cc ep ta nc e (S ub se ct io n)
M ea su re d an d te st ed fo r c on fo rm an
(1
.0
M ea su re d an d te on fo rm
.0
4) er ia l o r
Pr od uc t
A gg re ga te so ur ce q ua lit y
3.
Su bb as e, B as e, a nd S ur fa co se s le
-1
(c on tin ue d) pl in g an d T es tin g R eq ui re m or tin g T im e
B ef or e us in g w or k
B ef or e pl ac in g ne xt la ye r pl e
Y es
, w he n re qu es te d t o f
Sa m pl in g
So ur ce o f m at er ia l
In -p la pl in g Fr eq ue nc y pe r t yp e an d so ur ce o f m at er ia l pe r da y
T es t M et ifi ca
SH
TO
T
SH
TO
0(1
SH
TO
T or o th er a pp ro ve d pr oc ed eg or ra ct er oi st ur e-de ity et ho
D oi st ur e-de ity et ho
F
In -p la ce d en si ty oi st ur e co nt en t
T yp ep ta nc e (S ub se ct su re d an d te on fo rm
.0
4) er ia l o r
Pr od uc t
Su bb as e, B as e, a nd S ur fa le
-2 pl in g an d
T es tin g
R eq ui re m or tin g T im e h ou pl e
Y t o f
Sa m pl in g
Fr om w in dr ow o r ro ad be d af te r pr oc es si ng o r fro m a pp ro ve d cr us he r s am pl in g de vi pl in g Fr eq ue nc y pe r da y
T es t M et ifi ca
SH
TO
eg or ra ct er pl e
T yp ep ta nc e (S ub se ct su re d an d te on fo rm
.0
M at er ia l o r
Pr od uc t
Sc re en ed
A gg re ga te
404 - Minor Hot Asphalt Concrete
404.02_nat_us_06_09_2006
404.02 Composition of Mix (Job-Mix Formula).
Delete the second paragraph and replace with the following:
Submit a job-mix formula and supporting documentation, test results, and calculations for the material to be incorporated into the work. Include copies of laboratory test results and mix design data that demonstrate that the properties of the aggregate, additives, and mixture meet the current requirements and criteria of Federal or state agencies. Ensure that the job-mix formula was performed no more than one year prior to placing the hot asphalt concrete. After reviewing the Contractor’s proposed job-mix formula, the CO will determine the final values for the job-mix formula to be used and notify the Contractor in writing.
404.04_nat_us_03_02_2005
404.04 Weather Limitations.
Change 35o F to 45o F:
404.06_nat_us_03_02_2005
404.06 Placing.
Add the following:
Do not place asphalt until the CO has approved in writing the area where it will be placed.
Delete the last sentence and replace with the following:
Offset the longitudinal joint of one layer at least 6 inches from the joint in the layer immediately below. Make the longitudinal joint in the top layer along the centerline of two-lane roadways or at the lane lines of roadways with more than two lanes. Offset transverse joints in succeeding layers and in adjacent lanes at least 10 feet, where possible.
404.07_nat_us_03_02_2005
404.07 Compacting (a).
Delete and replace with the following:
(a) Roadway paving. Thoroughly and uniformly compact the surface a minimum of three passes with rollers that meet one of the following requirements:
(1) Steel-wheeled rollers, other than vibratory type, capable of exerting a force of not less than
1.5 ton/feet of width of the compression roll or rolls.
(2) Vibratory steel-wheel rollers with a minimum mass of 5 ton, equipped with amplitude and frequency controls, and designed to compact asphalt concrete.
(3) Pneumatic-tire rollers with smooth tread tires of equal size that provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 lbf/in2.
Perform initial compaction while the mixture is above 250 °F. Perform finish rolling with steel-wheel rollers and continue until no roller tracks remain.
404.09_nat_us_03_02_2005
404.09 Acceptance.
Add the following to the second paragraph:
See Table 404-1 for sampling and testing requirements.
Table 404-1. Delete and replace with the following:
Table 404-1. Sampling and Testing Requirements.
Material or Product
Type of Acceptance (Subsection)
Characteristic Category Sampling Methods
Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Asphalt Mixture (404.09)
- - - AASHTO T
Three minimum per project and at least one per 500 Cubic yards
Roadway prior to compaction yes As soon as sampled
552 - Structural Concrete
552.02_nat_us_06_20_2007
Material
552.02 Add the following:
Anchor bolts 717.01 Dowels 717.17 Epoxy resin adhesives 725.21 High strength non-shrink grout 701.02 Mortar 701.02 Portland cement 701.01 Sealants, fillers, seal, and sleeves 712.01
552.03 Composition (Concrete Mix Design).
Delete Tables 552-1, 2, and 3 and replace with the following:
Table 552-1 Composition of Concrete
Class of Concrete
Minimum Cement Content
(pound per cubic yard)
Maximum W/C Ratio
Slump (1) (inches)
Maximum Nominal Coarse
Aggregate Size (5)
(inches) A 611 0.49 2 to 4 1½
A(AE) 611 0.44 1 to 4 1½ B 517 0.58 2 to 4 2½
B(AE) 517 0.58 2 to 4 2½ C 658 0.49 2 to 4 ¾
C(AE) 658 0.44 1 to 3 ¾ D(AE)(2) 611 0.40 1 to 3 1½ E(AE)(3) 611 0.40 4 to 6 (4) ¾
P (Prestressed) 658 0.44 0 to 4 1
P(AE) 658 0.44 0 to 4 1 Seal 658 0.54 4 to 8 1½
(1) Maximum slump is 8 inches if approved mix design includes a high-range water reducer.
(2) Concrete with a water reducing and retarding admixture conforming to AASHTO M 194, type D.
(3) A latex modified concrete with 0.037 gallons of modifier per pound of cement.
(4) Measure the slump 4 to 5 minutes after the concrete is discharged from the mixer.
(5) Meeting the processing requirements of AASHTO M43, Table 1 – Standard Sizes of Processed Aggregate.
(6) Use Class P (AE) concrete in the entire depth of the top flange of all multi-beam bridge girders. In lieu of this, Class P (AE) concrete may be used for fabrication of the entire girder, and throughout the entire depth of prestressed slabs. In all cases, furnish concrete meeting the 28 day specified minimum concrete strength requirements for the prestressed members as shown on the plans, unless otherwise specified.
Table 552-2
Minimum Air Content for Air Entrained Concrete
Nominal Maximum Aggregate Size (1)
As Delivered Minimum Air
Content (2) (3) (%) 2½ inch 3.5 2 inch 3.5
1½ inch 4.0 1 inch 4.5 ¾ inch 4.5 ½ inch 5.5
(1) Meeting the processing requirements of AASHTO M 43, Table 1 – Standard Sizes of Processed Aggregate.
(2) These air contents apply to the total mix. When testing these concretes, aggregates larger than 1½ inches are removed by handpicking or sieving, and air content is determined on the minus 1½-inch fraction of the mix. Air content of the total mix is computed from the value determined on the minus 1½-inch fraction.
(3) For P(AE) concrete, the as delivered minimum air contents may be reduced 1.0 % and the maximum air content is 6.0 %
Table 552-3
Required Average Compressive Strength (1)
Specified Compressive Strength (f’c)
(psi)
Required Average Compressive Strength
(f’cr) (psi)
Less than 3000 f’c + 1000 3000 to 5000 f’c + 1200
Over 5000 1.10f’c + 700
(1) Use this table when there is not enough data available to establish a standard deviation
Delete the first paragraph after Table 552-2 and replace with the following:
Submit written concrete mix designs for approval at least 30 calendar days before production.
Add the following under the list of items to be included in the mix design submittal:
(y) Evaluation of potential aggregate reactivity
552.08 Delivery.
(a) Truck mixer/agitator.
Add the following:
Do not exceed 130 total revolutions at mixing speed, including both initial mixing and remixing. Do not exceed 300 total revolutions, including both mixing and agitating speed.
552.09 Quality Control of Mix.
Add the following after the first paragraph:
At least 2 weeks prior to the start of concrete placement operations, arrange a pre-concrete placement conference. Coordinate attendance with the CO and any applicable subcontractors.
Be prepared to discuss and/or submit the following:
(1) Proposed concrete placement schedule.
(2) Review approved concrete mix design and determination of batch weights.
(3) Discuss Section 153, Contractor Quality Control, minimum frequency schedule for process control sampling and testing (to be performed by the Contractor).
(4) Discuss batching, mixing, placing, and curing requirements.
(5) Discuss Subsections 106.03, Certification, and 106.05, Statistical Evaluation of Material for Acceptance.
552.11 Handling and Placing Concrete.
Add the following after the forth paragraph:
Use an approved form release agent to produce a minimum of staining, air holes, and hydration discoloration.
552.12 Construction Joints.
Add the following at the end of the first paragraph:
Provide form cleanout ports at construction joints.
552.18 Loads on New Concrete Structures.
Add the following paragraph:
Do not allow public traffic on the bridge until approaches, curbs, and bridge rail are completed and in-place. Erect barricades at each end of bridge spans when road approaches allow vehicles to drive directly onto the structure.
552.13_nat_us_08_12_2004
Delete Table 552-3 and substitute the following:
Table 552-3 Required Average Compressive Strength
Table 552-3
Required Average Compressive Strength When Data
Are Not Available to Establish a Standard Deviation
Specified Compressive
Strength (f’c)
(pounds per square inch)
Required Average Compressive Strength (f’cr)
(pounds per square inch)
Less than 3000 f’c + 1000
3000 to 5000 f’c + 1200
Over 5000 1.10f’c + 700
554 - Reinforcing Steel
554.03_nat_us_06_20_2007
Construction Requirements
554.03 Order Lists.
Delete the first paragraph and replace with the following:
Do not submit order lists or bending diagrams for approval.
554.08 Placing & Fastening.
Delete the first sentence and replace with the following:
Place, fasten, and support the bars according to the CRSI Manual of Standard Practice. Use precast concrete blocks or metal supports, but only use precast mortar blocks in areas permanently hidden from view in the completed structure.
Measurement
554.11 Method.
Add the following to the end of the second paragraph:
Do not measure or include reinforcing steel fabricated into the prestressed member.
555 - Steel Structures
555.18_nat_us_07_03_2007
555.18 Welding.
Add the following at the start of the first sentence.
"Unless otherwise provided for in the supplemental specifications or shown on the plans, ... "
617 - Guardrail
617.02_nat_us_07_03_2007
Material 617.02
Galvanized coating repair 717.07
617.03 Posts.
Replace the first paragraph with the following:
Fabricate all timber components of guardrail as detailed in Subsection 557.04. Pressure treat all timber as detailed in Subsection 716.03, using creosote, pentachlorophenol (any solvent), ammoniacal copper zinc arsenate (ACZA), or chromated copper arsenate (CCA – Type A, B, or C) in conformance with AASHTO M 133. Provide grading certification and pressure treatment test results, and meet the Best Management Practices (BMP’s) requirements of Subsection
716.03. Field treat cuts or abrasions made in fabricated timber after treatment in accordance with Subsection 557.04.
617.04 Rail Elements.
(a) Steel rail.
Replace the third paragraph with the following:
Repair all scrapes, cuts and other damaged coating areas on galvanized surfaces that are through to the base metal with galvanized coating repair.
617.05 Terminal Sections.
Add the following to the end of the second sentence:
"... unless otherwise shown on the plans."
635 - Temporary Traffic Control
635.03_nat_us_05_13_2004
635.03 General.
Install temporary traffic control signs to temporary posts or approved temporary sign mounts.
701 - Cement
701.02_nat_us_08_05_2009
701.02 Masonry and Mortar Cement.
(b) Mortar Cement.
Add the following:
Use this mortar in bridge deck and prestressed multi-beam girder keyways instead of high strength non-shrink grout; and, when approved, as a structural repair mortar.
Keep mortar in the original manufacturer's labeled containers until used. Protect as specified for Portland cement in 701.01. Do not use mortar after the expiration date shown on the container or 1 year from date of purchase, whichever date occurs first.
Store, mix, place and cure in accordance with the manufacturer's instructions; submit a copy in advance of use to the CO.
Furnish mortar that is a chemical action concrete of the magnesium ammonium phosphate family and requires no curing under ambient temperatures of 36° - 100° F. Require recommendation by its manufacturer specifically for use in prestressed concrete bridge member keyways that are to be part of the finished wearing and running surface of the bridge, subjected to normal roadway contaminants and conditions promoting wear of normal bridge deck concrete.
Typical properties of the mortar, when tested neat without aggregate, are as follows, except when noted:
· Compressive strength (ASTM C 109 modified) of 6000 psi at 24 hours at 72° F or above, and when used below 50° F, 5000 psi.
· Modulus of elasticity (ASTM C 469) at 7 and 28 days of 4177 ksi and 4554 ksi.
· Freeze-thaw durability (ASTM C 666, Procedure A Modified) of a relative dynamic modulus greater than 80 percent after 300 cycles.
· Scaling resistance to deicing chemicals (ASTM C 672) after 5 and 25 cycles at a rating of
0, shall show no surface scaling; after 50 cycles at a rating of 1.5 shall show only slight surface scaling.
· Sulfate resistance (ASTM C 1012) length change after 52 weeks shall be no greater than
0.9 percent.
· Coefficient of thermal expansion (CRD-C 39-81) when run with 1inch x 1 inch x 11 inch bars and neat mixes without aggregate, shall be within 10 percent of 7150 psi/degree Fahrenheit.
· Flexural strength (ASTM C 78 Modified) of 3 inch x 4 inch x 16 inch prisms shall be 3.8 550 psi at 24 hours for the mortar only, and 670 psi with 3/8 inch pea gravel.
Submit independent tests for the mortar recommended for use from 50° - 100° F, when used to fill test specimens conforming to the Government's bridge box beam test keyway, showing the following results:
· Lateral (horizontal) shear between adjacent members: Range of 14 k/ft of keyway
· Vertical shear between adjacent members: 16 k/ft of keyway
· Direct tension between adjacent members: 6 k/ft of keyway.
Submit independent tests for the mortar recommended for use from 36° - 50° F, when used to fill test specimens conforming to the Government's bridge box beam test keyway, showing the following results:
· Lateral (horizontal) shear between adjacent members: Range of 2.4 k/ft of keyway
· Vertical shear between adjacent members: 6 k/ft of keyway
· Direct tension between adjacent members: 4 k/ft of keyway.
Two products that meet these requirements are BASF/Master Builders Technologies Regular Set-45 [for use below 50° F] and Set-45 Hot Weather Formula [for use from 50° - 100° F].
Use Set-45 Hot Weather Formula in air temperatures from 50° - 100° F. Use Regular Set-45 only in air temperatures below 50° F. When used in temperatures below 36° F, use approved weather precautions designed to prevent the mortar from freezing. Except when used in bridge deck keyways and blockouts, Regular Set-45 may be extended by the addition of 20 pounds of washed and clean 3/8 inch minus pea gravel per 50 pound bag when placed in thicknesses over
1.5 inches, or when approved by the CO.
Unless using one of the two products described above, submit products proposed for use to the CO for approval, and accompany them with the manufacturer’s submittals substantiating all requriements in this section, including (1) graphs or charts showing the time, temperature, humidity, and curing requirements to achieve mortar strengths equal to the adjacent concrete;
and (2) complete recommendations for storage, mixing, application and curing procedures.
703 - Aggregate
703.05_nat_us_08_14_2009
Delete 703.05 and replace with the following:
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-2
(2) Liquid limit, AASHTO T 89 25 max.
(3) Plastic limit, AASHTO T 90 Nonplastic
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 50% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-3
(2) Liquid limit, AASHTO T 89 35 max.
(3) Plastic Index, AASHTO T 90
a) If the percent passing the No. 200 sieve is less than 12% 2 to 9
b) If the percent passing the No. 200 sieve is greater than 12% Less than 2
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 75% min.
(9) Free from organic matter and lumps or balls of clay
Do not furnish material that contains asbestos fibers.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:
(1) Gradation Table 703-16
(2) Plastic Index, AASHTO T 90 Less than 9
(3) Los Angeles abrasion, AASHTO T 96 55% max.
(4) Free from organic matter and lumps or balls of clay.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
Delete Table 703-2 and replace with the following:
le
-2 ar ge t V al ue
R an ge s f or S ub ba se a nd B as e
G ra da tio n Pe rc en t b y
M as s P as si ng
D es ig na te d
Si ev e (A
A
SH
T O
T an d T
1)
G ra di ng D es ig na tio n E
(B as
(6
(6
(4
4.
7.
(3
T he v al ue in th e pa re nt he se s i s t he a llo w ab le d ev ia tio n
) f ro m th e ta rg et v al s..
D (B
(6
(6
(6
(4
4.
7.
(3
C (B
(6
(6
4.
–7 .0
(3
B (S ub ba se
(8
4.
.0 (4
A (S ub ba se
(7
(6
(4
4.
8.
(3
Si ev e Si ze
2½ ch
1½
3/
1/
N o.
N o.
Delete Table 703-3 and replace with the following:
le
-3 ar ge t V al ue R an ge s f or
S ur fa ce
G ra da tio n Pe rc en t b y
M as s P as si ng
D es ig na te d
Si ev e (A
A
SH
T O
T an d T
1) ra di ng D es ig na tio n U
(6
(7
(5
8.
.0 (4
T he v al ue in th e pa re nt he se s i s t he a llo w ab le d ev ia tio n
) f ro m th e ta rg et v al s.
If th e pl as tic ity in de x
(P I) is gr ea te r t ha n 0, th e
TV
ra ng e fo r t he N o.
si ev e siz e is
-1
(4
(7
(5
8.
.0 (4
S 10
(6
(7
(5
8.
.0 (4
H
(6
(6
(5
9.
.0 (4
(6
(6
(5
.0
6.
(4
F 10
-1
-8
-6
(6
-5
-3
(6
-2
(5
.0
-1 6.
(4
Si ev e Si ze
N o.
N o.
Add Table 703-16:
Table 703-16
Gradation Requirements for Screened Aggregate
Sieve Size
Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation L M N O P Q R
6 inch 100 100
4 inch 100 100
3 inch 100 100
2 inch 100
No. 4 15-45 15-45 15-45
703.07_nat_us_03_02_2005
Table 703-2 Correction
Include the following substitution
In Table 703-2, delete the “436 – 74 (6)” percent by mass passing for grading E (base) No. 4 sieve size and substitute “36 – 74 (6).”
Table 703-2 Correction
Include the following substitution
In Table 703-2, delete the “436 – 74 (6)” percent by mass passing for grading E (base) No. 4 sieve size and substitute “36 – 74 (6).”
703.10_nat_us_04_11_2011
703.10(e) Flakiness Index.
Delete and replace with the following:
Flakiness Index, FLH T 508 30% max.
703.10(i) Adherent Coating.
Adherent coating on the aggregate, FLH T 512 0.5% max.
709 - Reinforcing Steel and Wire Rope
709.01_nat_us_07_03_2007
709.01 Reinforcing Steel.
(b) Reinforcing bars.
Delete paragraph one and replace with the following:
Furnish deformed, grade 60 bars conforming to AASHTO M 31.
(d) Tie bars.
Delete paragraph one and replace with the following:
Furnish deformed, grade 60 bars conforming to AASHTO M 31.
(e) Hook bolts.
Delete paragraph one and replace with the following:
Furnish plain, grade 60 bars conforming to AASHTO M 31 with M14 rolled threads or M16 cut threads. Furnish a threaded sleeve nut capable of sustaining a minimum axial load of 15,000 pounds.
709.02 Wire Rope Or Wire Cable.
Delete paragraph one and replace with the following:
Furnish wire rope or wire cable, and associated fittings, conforming to AASHTO M 30. Furnish
0.75 inch diameter Type II wire rope, with Class C zinc coating, unless otherwise shown on the plans.
709.03 Prestressing Steel.
Delete all to subsection (a) and replace with the following:
Fabricate from one of the following:
· Seven-wire uncoated strand conforming to AASHTO M 203, Grade 270, Supplement I, low relaxation strand, minimum ultimate tensile strength 270 ksi, unless shown otherwise on the plans.
· Epoxy coated seven-wire strand, ASTM A 882, Grade 270, low relaxation strand, minimum ultimate tensile strength 270 ksi, unless shown otherwise on the plans.
· High tensile strength wire, AASHTO M 204, Type BA or WA, Supplement I (low relaxation), unless shown otherwise on the plans.
· High strength steel bars, AASHTO M 275M, Type II, minimum ultimate tensile strength 150 ksi, unless shown otherwise on the plans.
712 - Joint Material
712.01_nat_us_03_02_2005
712.01 Sealants, Fillers, Seals, and Sleeves.
(a) Joint sealants and crack fillers.
Add the following:
(7) Low-Modulus Rubberized Asphalt. Conform to ASTM D 3405 and the following.
Cone Penetration, 75oF 100-150
Cone Penetration, -0oF 25 minimum
Flow, 140oF, 5h 3/8 in. maximum
Resilience 30-60%
Bond, -20oF, 200% extension Pass 3 Cycles
Recommended Pour Temperature 380oF
Safe Heating Temperature 410oF
Asphalt Compatibility Pass
712.01_nat_us_08_05_2009
712.01 Sealants, Fillers, Seals, and Sleeves.
(b) Preformed expansion joint fillers.
Add to the end of the first sentence:
except on abutment, pier cap or other bent more than one piece may be used.
717 - Structural Metal
717.01_nat_us_08_05_2009
717.01 Structural Steel
(e) High-Strength Bolts, Nuts, & Washers.
Delete the first paragraph and replace with the following:
Conform to either AASHTO M164 or AASHTO M253, as specified. Use Type 3 bolts in combination with unpainted weathering structure steel. Conform to AASHTO M293 (ASTM F 436) for hardened steel washers.
Add the following subsections:
(f) Load-Indicating Washers.
Furnish load-indicating washers (Compressible-washer-type DTI's) conforming to ASTM F 959, Type 8.8 or 10.9. Use Type 8.8 with AASHTO M 164 bolts and with ASTM F 568, Class 8.8 tie rods; use Type 10.9 with AASHTO M 253 bolts. When galvanizing is shown on the plans, furnish DTI's mechanically galvanized to conform to AASHTO M 298, Class 50, Type I. When used with other components that are weathering steel or are to be coated the color of weathering steel, furnish DTI's protectively coated with baked epoxy in a black color.
(g) Steel Anchor Bolts.
Furnish steel anchor bolts of the dimensions shown on the plans. Furnish steel anchor bolts that conform to AASHTO M314, Grade 40 unless otherwise shown on the plans. Ensure that the exposed portion of the bolt is zinc coated by hot dip or mechanical deposition.
(h) Structural Steel Tubing.
Furnish structural steel tubing that conforms to ASTM A500, grade B or ASTM A501 unless otherwise shown on the plans.
717.07 Galvanized Coatings
Furnish hot-dipped galvanized hardware and fasteners conforming to AASHTO M 232 and mechanically galvanized hardware and fasteners conforming to AASHTO M 298.
Repair damaged galvanized surfaces by power or hand tool cleaning, followed by 2 brush applications of zinc rich 2 component paint meeting FS TT-P-641, FS TT-P-1046A or MIL-P-
21035. Single component brush or spray-on zinc or galvanizing compounds are not permitted. A source for TT-P-641 paint is Far West Paint Company, Tukwila, WA 206-244-8844.
718 - Traffic Signing and Marking Material
718.02_nat_us_03_02_2005
718.02 Reserved.
Replace this section with the following:
718.02 Protective Overlay Film and Edge Film.
Protective overlay film will be a high performance flouropolymer film such as 3M Scotchlite Premium Protective Overlay Film Series 1160 or approved equal.
Edge film will be a pressure-sensitive, premium-quality, clear, ultraviolet-resistant, 3 inches wide vinyl film.
718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.
718.08_nat_us_03_27_2007
718.08 (b)(2)(c)Signpost - Square tubular steel posts
Delete the existing subsection and substitute the following:
(c) Galvanizing after punching ASTM A 653M, (inside and outside of post) coating Z275 designation
718.14_nat_us_03_02_2005
718.14 (g)Waterborne Traffic Paint - Daylight reflectance
Delete the existing subsection and substitute the following:
(g) Daylight reflectance. (Without glass beads)
(1) White, ASTM E 1347 84% relative to magnesium oxide standard
(2) Yellow, ASTM E 1347 55% relative to magnesium oxide standard
718.15_nat_us_03_27_2007
718.15 (a)Epoxy Markings Pigments
(2) Yellow.
(a) Chrome yellow (PbCrO4), 23% min.
ASTM D 126, type III.
(b) Epoxy resin 70 to 77%
718.15_nat_us_03_27_2007
718.15 (g)Epoxy Marking - Drying Time
(g) Drying time. 15 mil film thickness with beads.
(1) Laboratory at 72o F, ASTM D 711 30 minutes maximum to no-pick-up condition
(2) Field at 77 oF, viewed from 50 feet 10 minutes maximum to no-pick-up condition
General Decision Number: WA140001 02/21/2014 WA1
Superseded General Decision Number: WA20130001
State: Washington
Construction Type: Highway
Counties: Washington Statewide.
HIGHWAY (Excludes D.O.E. Hanford Site in Benton and Franklin Counties)
Modification Number Publication Date 0 01/03/2014 1 01/17/2014 2 01/24/2014 3 02/07/2014 4 02/21/2014
CARP0001-008 06/01/2013
Rates Fringes
Carpenters:
COLUMBIA RIVER AREA -
ADAMS, BENTON, COLUMBIA,
DOUGLAS (EAST OF THE 120TH
MERIDIAN), FERRY,
FRANKLIN, GRANT, OKANOGAN
(EAST OF THE 120TH
MERIDIAN) AND WALLA WALLA
COUNTIES
GROUP 1:...................$ 30.66 12.87
GROUP 2:...................$ 31.56 12.87
GROUP 3:...................$ 31.64 12.87
GROUP 4:...................$ 31.64 12.87
GROUP 5:...................$ 62.58 12.87
GROUP 6....................$ 30.29 12.87
GROUP 7....................$ 31.29 12.87
GROUP 8....................$ 28.54 12.87
GROUP 9....................$ 30.29 12.87
SPOKANE AREA: ASOTIN,
GARFIELD, LINCOLN, PEND
OREILLE, SPOKANE, STEVENS
AND WHITMAN COUNTIES
GROUP 1:...................$ 30.66 12.87
GROUP 2:...................$ 31.56 12.87
GROUP 3:...................$ 31.64 12.87
GROUP 4:...................$ 31.64 12.87
GROUP 5:...................$ 70.78 12.87
GROUP 6:...................$ 32.64 12.87
GROUP 7....................$ 35.39 12.87
GROUP 8....................$ 34.39 12.87
GROUP 9....................$ 34.39 12.87
CARPENTER & DIVER CLASSIFICATIONS:
GROUP 1: Carpenter
3/12/2014http://www.wdol.gov/wdol/scafiles/davisbacon/WA1.dvb?v=4AG-05K3-S-14-0013 Attachments
GROUP 2: Millwright, machine erector
GROUP 3: Piledriver - includes driving, pulling, cutting, placing collars, setting, welding, or creosote treated material, on all piling
GROUP 4: Bridge carpenters
GROUP 5: Diver Wet
GROUP 6: Diver Tender, Manifold Operator, ROV Operator
GROUP 7: Diver Standby, Bell/Vehicle or Submersible operator Not Under Pressure
GROUP 8: Assistant Tender, ROV Tender/Technician
GROUP 9: Manifold Operator-Mixed Gas
ZONE PAY:
ZONE 1 0-40 MILES FREE
ZONE 2 41-65 MILES $2.25/PER HOUR
ZONE 3 66-100 MILES $3.25/PER HOUR
ZONE 4 OVER 100 MILES $4.75/PER HOUR
DISPATCH POINTS:
CARPENTERS/MILLWRIGHTS: PASCO (515 N Neel Street) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
CARPENTERS/PILEDRIVER: SPOKANE (127 E. AUGUSTA AVE.) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
CARPENTERS: WENATCHEE (27 N. CHELAN) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
CARPENTERS: COEUR D' ALENE (1839 N. GOVERNMENT WAY) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
CARPENTERS: MOSCOW (302 N. JACKSON) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
DEPTH PAY FOR DIVERS BELOW WATER SURFACE:
50-100 feet $2.00 per foot 101-150 feet $3.00 per foot 151-220 feet $4.00 per foot 221 feet and deeper $5.00 per foot
PREMIUM PAY FOR DIVING IN ENCLOSURES WITH NO VERTICAL ASCENT:
0-25 feet Free 26-300 feet $1.00 per Foot
SATURATION DIVING:
The standby rate applies until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. the diver rate shall be paid for all saturation hours.
WORK IN COMBINATION OF CLASSIFICATIONS:
Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.
HAZMAT PROJECTS:
Anyone working on a HAZMAT job (task), where HAZMAT certification is required, shall be compensated at a premium, in addition to the classification working in as follows:
LEVEL D + $.25 per hour - This is the lowest level of protection. No respirator is used and skin protection is minimal.
LEVEL C + $.50 per hour - This level uses an air purifying respirator or additional protective clothing.
LEVEL B + $.75 per hour - Uses same respirator protection as Level A. Supplied air line is provided in conjunction with a chemical "splash suit".
LEVEL A +$1.00 per hour - This level utilizes a fully…