AG-04T0-S-17-0045Solicitation.pdf
PDF 1 MB Posted
- Attached to
- McKenzie River Ranger Station Office Security Federal contract opportunity
- Solicitation number
- AG-04T0-S-17-0045
About this file
Complete Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AG-04T0-S-17-0045Amendment2.pdf | ||
| AG-04T0-S-17-0045Amendment1.pdf | ||
| AG-04T0-S-17-0045ReturnPacket.pdf | ||
| AG-04T0-S-17-0045WageRates-Service.pdf | ||
| AG-04T0-S-17-0045Drawings.pdf | ||
| SF25A-PaymentBond.pdf | ||
| AG-04T0-S-17-0045Lennel_Supplier_List.pdf | ||
| AG-04T0-S-17-0045WageRates-Construction.pdf | ||
| AG-04T0-S-17-0045Project_Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
AG-04T0-S-17-0045
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
May 3, 2017
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
852704
6. PROJECT NO.
7. ISSUED BY CODE 8. ADDRESS OFFER TO
U.S. FOREST SERVICE
SIUSLAW NATIONAL FOREST
3200 SW JEFFERSON WAY
CORVALLIS, OREGON 97331
ATTN: CONTRACTING
SIUSLAW NATIONAL FOREST
3200 SW JEFFERSON WAY
CORVALLIS, OREGON 97331
9. FOR INFORMATION
CALL:
A. NAME
CONTRACTING OFFICE
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
(541) 750-7116
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
McKenzie River District Office Security McKenzie River Ranger District Willamette National Forest Lane County, Oregon
FAR 36.204 DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECT:
The Government's estimate is between $100,000 and $250,000 (for all line items in Schedule of Items)
Note: Quotes exceeding $150,000.00 will not be accepted.
11. The Contractor shall begin performance within 10 calendar days and complete it within _90_ calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by 4:00 PM local time 5/18/17 . If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)
AG-04T0-S-17-0045
McKenzie Ranger Station Office Security
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
Invoice Processing Platform www.ipp.gov
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85) http://www.ipp.gov/
PART I – THE SCHEDULE
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
McKenzie River District Office Security McKenzie River Ranger District
Willamette National Forest Lane County, Oregon
B-1 SCHEDULE OF ITEMS
NOTE: The offeror must price all line items. Award will be on an all or none basis to the offeror whose proposal represents the best value to the Government, price and other factors considered (see Section M). If offeror does not intend to charge for an item, a “0” or “No Cost” shall be shown.
Offers shall be submitted for the total item. Offers for less than the total item will not be considered.
ITEM
NO.
DESCRIPTION
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
PAY ITEMS
1.1 BASE BID ITEMS
As specified in Section 01 11 00 and in accordance with the specifications:
a. New and replacement doors and door hardware
b. New wall and door #7.
c. An access control system including control system equipment, devices, wiring and conduit/pathways, programming, cards.
d. Electrical devices circuits, wiring and conduit/pathways.
e. Patching, painting, sealant and firestopping.
LSQ All
OPTION ITEMS (Optional Item pricing shall be guaranteed through 11/30/2017)
2.1 Option 1
and in accordance with the specifications Replace the motor and push-button actuators on doors 2, 5, 8 and 9.
LSQ All $__________
2.2 Option 2
and in accordance with the specifications Replace existing Doors 2 and 5 with hollow metal doors and frames and the appropriate new door hardware
2.3 Option 3
and in accordance with the specifications
Installation of badge printer
Total Price $___________
DUNS Number________________________ EMAIL ______________________________
B-2 NOTES:
Lump Sum Quantities (LSQ) denote one complete unit of work as required by or described in the contract including necessary materials, equipment, labor, overhead, and profit to complete the job. They will not be measured.
The estimated start work date is September 11th 2017. All work shall be completed within 90 calendar ays after the effective date of the Notice to Proceed.
For additional information, please contact Kenny Gabriel at 541-822-7221 or cell 541-915-2598.
NOTE: Contractor MUST register in the System for Award Management (SAM):
https://www.sam.gov/portal/public/SAM/ and have an “Active” registration at time of quote submission.
The contract awardee must register at the https://www.ipp.gov/vendors/enrollment-vendors.htm in order to submit invoices for payment. See page 34 for more information.
PRE-BID/PRE-PROPOPOSAL SITE VISIT SCHEDULED FOR MAY 10, 2017, 10 a.m.
The conference will be held at: McKenzie River Ranger Station, 57600 McKenzie Hwy, McKenzie Bridge, OR 97413
RSVP requested by May 9, 2017, 3.p.m.
Contact: Kenny Gabriel, Phone: (541) 822-7221 Email: kgabriel@fs.fed.us
FAR 52.215-5 FACSIMILE PROPOSALS (OCT 1997)
(a) Definition. "Facsimile proposal," as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via facsimile machine.
(b) Offerors may submit facsimile proposals as responses to this solicitation. Facsimile proposals are subject to the same rules as paper proposals.
(c) The telephone number of receiving facsimile equipment is: ______541-750-7236______________
(d) If any portion of a facsimile proposal received by the Contracting Officer is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained from the document--
(1) The Contracting Officer immediately shall notify the offeror and permit the offeror to resubmit the proposal.
(2) The method and time for resubmission shall be prescribed by the Contracting Officer after consultation with the offeror; and
(3) The resubmission shall be considered as if it were received at the date and time of the original unreadable submission for the purpose of determining timelines, provided the offeror complies with the time and format requirements for resubmission prescribed by the Contracting Officer.
(e) The Government reserves the right to make award solely on the facsimile proposal. However, if requested to do so by the Contracting Officer, the apparently successful offeror promptly shall submit the complete original signed proposal.
AG-04T0-S-17-0045
McKenzie Ranger Station Office Security https://www.sam.gov/portal/public/SAM/ https://www.ipp.gov/vendors/enrollment-vendors.htm mailto:kgabriel@fs.fed.us
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1 STATEMENT OF WORK/SPECIFICATIONS - AGAR 452.211-72 (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
Work includes but is not limited to the installation of an USDA ePACS certified and interoperable access control system including control system equipment, electrical devices circuits, wiring, conduit/pathways, programming, and cards. Installation of new and replacement doors and door hardware. Patching, painting, sealant, firestopping and miscellaneous carpentry. Cerification of equipment and software and contractor cerification as a VAR of the proposed equipment will be required at time of bid, as stated in section M “EVALUATION FACTORS FOR AWARD”. Detailed compatibility and certification requirments are detailed in section 28 13 00.
C-2 PROJECT LOCATION
The project is located on the U.S. Forest Service Administrative site, McKenzie River Ranger Station. From Springfield Oregon, head east on State Highway 126 towards McKenzie Bridge. The ranger station is loacted at approximately mile point 53.5.
C-3 PRICE RANGE
The Government's estimate is between $100,000 AND $250,000 (for all Schedule line items)
C-4 SPECIFICATIONS
AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL
SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS FPMR PART 101-29 (FAR
52.211-1) (AUG 1998)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Description, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to--
GSA Federal Supply Service Specifications Section, Suite 8100 470 East L'Enfant Plaza SW Washington, DC 20407 Telephone (202) 619-8925 Facsimile (202) 619-8978.
(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.
(End of provision)
AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF
FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM
DESCRIPTIONS (FAR 52.211-3) (JUN 1988)
AG-04T0-S-17-0045
The specifications cited in this solicitation may be obtained from:
ASTM Standards American Society for Testing and Materials 1916 Race Street Philadelphia, PA 19103
(215) 199-5462
OSHA http://www.osha.com Occupational Safety & Health Administration
ICC/IMC http://www.iccsafe.org International Code Council/International Mechanical Code
National Electric Codes http://www.nfpa.org
UL http://www.ul.com Underwriters Laboratories
The request should identify the solicitation number and the specification requested by date, title, and number, as cited in the solicitation.
(End of clause)
C-5 USE OF BIOBASED PRODUCTS
The Contractor must comply with Section 9002 of the Farm Security and Rural Investment Act of 2002 (FSRIA), Excecutive Order (EO) 13423, “Strengthening Federal Evnironmental, Energy, and Transportation Management, “ and the Federal Acquisition Regulation to provide biobased products.
The Contractor shall utilize prodcuts and material made from biobased materials to the maximum extent possible without jeopardizing the intended end use or detracting form the overall quoality delivered ot the end user. All supplies and materials shall be of a type and quality that conform to applicalbe Federal Specifications and standards.
All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer’s Representative.
The following is an example list of products that may be used in this contract for minor construction for which biobased products or recovered materials are available. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.
Construction Materials
The Contractor shall comply with the provision at FAR 52.223-1, Biobased Product Certification, clause FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts http://www.iccsafe.org/ http://www.nfpa.org/ http://www.ul.com/
C-6 SUBMITTALS
Submittals shall include the following unless otherwise required in the specification:
1. Date and revision dates.
2. Project name and contract number.
3. Names of Contractor, subcontractor, supplier, and manufacturer.
4. Specifications section number.
5. Field dimensions and relation to adjacent structures.
6. Applicable standards such as ASTM or Federal Specifications.
7. Contractor's stamp, initial or signature, certifying the review of submittal, verification of field measurements and compliance with contract documents. Provide all submittals within 14 calendar days of contract award unless otherwise required by the specification.
C-7 PROJECT SUBMITTALS
The submittals, shop drawings, material certifications and/or testing reports refrenced in the following specifications are required for this project:
Referenced by Specification No
Time of Government Approval After Submittal
01 29 00 PER 01 33 00
01 74 19 PER 01 33 00
01 77 00 PER 01 33 00
01 78 39 PER 01 33 00
01 79 00 PER 01 33 00
07 84 13 PER 01 33 00
07 92 00 PER 01 33 00
08 11 13 PER 01 33 00
08 14 16 PER 01 33 00
08 70 00 PER 01 33 00
08 71 13 PER 01 33 00
09 91 23 PER 01 33 00
26 00 10 PER 01 33 00
26 00 50 PER 01 33 00
26 00 60 PER 01 33 00
27 00 00 PER 01 33 00
28 13 00 PER 01 33 00
C-8 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS - AGAR 452.211-73 (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION D – PACKAGING AND MARKING
(For this Soliciation, there are NO clauses in this Section)
AG-04T0-S-17-0045
SECTION E--INSPECTION AND ACCEPTANCE
E-1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2)(FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
E-2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at the project location.
E-3 INSPECTION AND TESTING PERFORMED BY GOVERNMENT
The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Supplemental Specifications.
E-4 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
http://www.arnet.gov/far/
SECTION F--DELIVERIES OR PERFORMANCE
F-1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2)(FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
F-2 SUSPENSIONS OF WORK FOR OTHER THAN GOVERNMENT'S CONVENIENCE
The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of:
(1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to be muddy or unsuitable; or
(2) Failure of the Contractor to comply with specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements or when conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by its operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242-14, Suspension of Work, and shall not qualify for an equitable adjustment.
F-3 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10)(APR 1984)
The Contractor shall be required to (a) commence work under this contract within 14 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 days after issuance of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
F-4 FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion
AG-04T0-S-17-0045
McKenzie Ranger Station Office Security http://www.arnet.gov/far/ of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
(End of clause)
F-5 AGAR 452-236-75 MAXIMUM WORKWEEK – CONSTRUCTION SCHEDULE (NOV 1996)
Within five (5) calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following in writing for approval:
(a) A schedule as required by FAR clause 52.236-15 “Schedules for Construction Contracts” and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work.
SECTION G--CONTRACT ADMINISTRATION DATA
G-1 DESIGNATION OF CONTRACTNG OFFICER’S REPRESENTATIVE
The Contracting Officer’s Representative (COR) is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order or other matter deviating from the terms of this contract be effective or binding upon the government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract. The Contracting Officer should be informed as soon as possible or any actions, or inactions, by the Contractor, or the Government, which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual assignments which were issued by the COR provided they do not affect the delivery schedule or the performance period stated in the contract.)
On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting Officer.
Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractural coverage, the Contracting Officer should be notified immediately, preferably in writing, if time permits. Proceeding with work without proper contractural coverage could result in nonpayment or necessitate submittal of a contract claim.
G-2 POST AWARD CONFERENCE (AGAR 452.215-73) (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within 14 days after the date of contract award. The conference will be held at: the Headquarters of the Willamette National Forest, 3106 Pierce Parkway, Suite D, Springfield, OR or at the McKenzie River Ranger Station, 57600 McKenzie Hwy, McKenzie Bridge, Oregon.
G-3 NOTIFICATION OF SUBCONTRACTING
The Contractor shall promptly notify the Contracting Officer upon entering into any subcontract arrangement. The written notification shall include as a minimum:
(a) The name, address, and telephone number of the subcontractor.
(b) The date upon which the subcontract was entered into and its duration.
(c) A detailed description of the work being subcontracted, including a listing of contract items, units, etc., as appropriate.
(d) Documentation of the subcontractor's representative authority.
G-4 NOTIFICATION OF SUBCONTRACTING CHANGES
Contractor shall promptly notify the Contracting Officer and request written consent before making any substitution of outside consultants, associates or subcontractors differing from those specifically initially identified.
G-5 GOVERNMENT-FURNISHED PROPERTY (GFP)
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the FAR clauses “52.245-1 -- Government Property”, or “52.245-9 -- Use and Charges” as applicable.
Description Quantity Delivery Date
See Section 26 00 10, Subsection1.03 ALL After notice to proceed See Section 27 00 00, Subsection1.10 ALL After notice to proceed See Section 28 13 00, Subsection1.05 ALL After notice to proceed
Note: The Contractor shall confirm with the Forest Service that the GFP is compatible with associated hardware/software planned for installation.
G-6 AGAR 452.232-70 REIMBURSEMENT FOR BOND PREMIUMS – FIXED-PRICE CONSTRUCTION
CONTRACTS (NOV 1996)
The Contract Price includes the total amount for premiums that the Contractor attributes to the furnishing of performance and payment bonds required by the contract. Reimbursement for bond premiums under the clause at FAR 52.232-5, Payments Under Fixed Price Construction Contracts, shall not cover any amount not included in the contract price.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H-1 POTENTIAL SAFETY HAZARDS
(a) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
This list shall not be deemed to be all-inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite.
(b) The following checked activities have been identified by the Government as potential safety hazards.
[X ] Confined space entry.
[ ] Temporary excavation/deep trenching/slope stability.
[ ] Tree falling.
[X ] Fall hazard from work heights exceeding six feet.
[ ] Blasting.
[ ] Traffic control on high-volume and/or high-speed and/or limited visibility roads.
[ ] Heavy equipment operation.
[ ] Tree climbing and/or tower climbing.
[ ] Fire hazards.
[ ] Hazardous materials handling.
[X ] Electrical hazard.
[ ] Hydraulic and/or pneumatic and/or other high pressure hazards.
[X ] Mechanical hazards such as pulleys, springs, etc.
[ ] Other __________________________________
H-2 INDUSTRIAL CAMPS
Forest Service regulations for Use of Campgrounds prohibit occupancy of developed recreation sites for other than primarily recreation purposes. No industrial camping will be authorized at these sites.
A special use permit is required on National Forest land for industrial camps. These permits are to be obtained by the Contractor through the Contracting Officer. Such permission, if granted, will be without charge to the Contractor but may include use restrictions.
One self-contained camp unit will be allowed at each staging area and equipment or supply dump for use by a watchman.
H-3 SALVAGE RIGHTS
No Contractor salvage rights exist under the contract unless specifically provided elsewhere herein.
H-4 PHYSICAL DATA (FAR 52.236-4) (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the Drawings and in the specifications are the result of site investigations by visual inspection and observation
(b) Weather conditions are typical West Cascade conditions at 1000’ to 1500’ elevations
(c) Transportation facilities consists of a paved maintained state highway
H-5 AVAILABILITY AND USE OF UTILITY SERVICES (FAR 52.236-14) (APR 1984)
(a) The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.
H-6 PRODUCT SUBSTITUTION
Any modification of items, designs, materials, products or equipment (including Government-Furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made.
No approvals will be made prior to award.
H-7 CONSTRUCTION STAKES, LINES, AND GRADES
(a) The Contractor shall do all further surveying, staking, and engineering to establish the horizontal and vertical control necessary to result in having the finished work comply with the lines and grades shown on the Drawings or stated in the specifications. This work is incidental to the pay items.
(b) If any construction control points have been destroyed or displaced, or are erroneous, the Contractor shall promptly notify the Contracting Officer’s Representative (COR). If these points are destroyed or displaced due to Contractor's negligence or operation, the cost for replacing them will be charged to the Contractor.
(c) In case of any construction changes, the Contractor shall cooperate with the (COR) and facilitate the prompt reestablishment of the field control for the adjusted work.
H-8 PROSECUTION OF WORK
(a) Construction activity shall be limited to the hours between 0730 a.m. and 1630 p.m., Monday through Friday, unless other hours are approved in writing by the COR. The Contractor shall conduct activities so that interference with the public and Government employees shall be kept at a minimum. Work required for the Installation of the new security door located in the front office shall only take place Monday through Thursday to reduce public interference during higher visitor volumes that occur on Friday and Saturdays. The project site shall remain free of hazards at all times. Any activities requiring closure to the public and/or employees shall be scheduled with the COR at least 7 days in advance.
(b) The Contractor shall use measures and precautions necessary to warn and protect the public and Government personnel during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site and roping off the area.
H-9 AGAR 452.237-74 KEY PERSONNEL (FEB 1988)
a. The Contractor shall assign to this contract the following key personnel:
• Door hardware specialist;
• USDA-certified software installer
b. During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
c. The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutions, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H-10 FINAL CLEANUP
Contractor shall remove and dispose all of its own trash and refuse from the project area. Material to be removed includes, but is not limited to camp refuse such as tin cans, aluminum foil, glass, paper, garbage, used engine oil, oil filters, oil cans, grease cartridges, etc. The Contractor shall also remove and dispose of upon completion and final approval, all tape, marking material, flagging, and similar debris within the project area. This Cleanup is a subsidiary item for which no special payment will be made. All debris shall be disposed off National Forest Land and in accordance with State and Local disposal requirements.
H-11 PROTECTION OF CULTURAL RESOURCES
Location of known historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C. 470) and the Archaeological Resources Protection Act of 1979 (PL 96-95 and 36 CFR 261.9(e)) shall be identified on the ground by Forest Service. Forest Service may unilaterally modify or cancel this contract to protect an area, object of antiquity, artifact, or similar object which is or may be entitled to protection under these Acts regardless of when the area, object or artifact is discovered or identified. Discovery of such areas or objects by either party shall be promptly reported to the other party.
Contractor shall protect all known and identified historic or prehistoric sites, buildings, objects and properties related to American history, architecture, archaeology and culture against destruction, obliteration, removal or damage during Contractor's Operations. In accordance with 36 CFR 296.14(c), Contractor shall bear costs of restoration, provided that such payment shall not relieve Contractor from civil or criminal remedies otherwise provided by law.
Wheeled or track-laying equipment shall not be operated within such areas except on roads. Unless agreed otherwise, trees will not be felled into such areas. (End of clause)
AG-04T0-S-17-0045
H-12 METHODS OF MEASUREMENT
One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:
(a) Designed Quantities (DQ). These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:
(1) As a result of changes in the work authorized by the Contracting Officer.
(2) As a result of the Contracting Officer determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
(3) As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
(b) Staked Quantities (SQ). These quantities are determined from staked measurements prior to construction.
(c) Actual Quantities (AQ). These quantities are determined from measurement of completed work.
(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.
(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract including necessary materials, equipment, and labor to complete the job. They will not be measured.
H-13 STATE ELECTRICAL INSPECTION AND COUNTY BUILDING PERMITS
The Contractor shall arrange for and provide the State Electrical inspection. When requesting the inspection inform the Building Permit Department of the federal limitation described below. The Contractor shall not obtain any building permits or inspections other than the State Electrical inspection.
Federal law [validated by the State Attorney General, Oregon Department of Justice] verify that the Federal Government and its Contractors may be exempted from State/Local Building Permits and Fees for projects located on Federal Installations [including all federal lands]. Contractor State Licenses will not be jeopardized by following this requirement to avoid the State/County permit system. This applies to the prime Contractor and all subcontractors.
H-14 AGAR 452.228-71 INSURANCE COVERAGE (NOV 1996)
Pursuant to FAR clause 52.228-5, Insurance - Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
(b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.
(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage or loss.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I-1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of
Whistleblower Rights (APR 2014) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (MAY 2011) 52.204-9 Personal Identity Verification of Contractor Personnel (JAN 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2016) 52.204-13 System for Award Management Maintenance (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (JUL 2013) 52.215-2 Audit and Records—Negotiation (OCT 2010) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (NOV 2016) 52.219-14 Limitations on Subcontracting (JAN 2017) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEP 2016) 52.222-35 Equal Opportunity for Veterans (OCT 2015) 52.222-36 Affirmative Action for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (FEB 2016)
AG-04T0-S-17-0045
52.222-40 Notification of Employee Rights under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts
(SEP 2013)
52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (JUL 2013) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.242-13 Bankruptcy (JUL 1995) 52.244-6 Subcontracts for Commercial Items (NOV 2016) 52.245-1 Government Property (JAN 2017) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012), Alternate I (SEP 1996) 52.253-1 Computer Generated Forms (JAN 1991) 452.236-72 Use of Premises (NOV 1996), Agriculture Acquisition Regulations (AGAR) 452.236-76 Samples and Certificates (FEB 1988), AGAR 452.237-75 Restrictions Against Disclosure (FEB 1988), AGAR 452.236-77 Emergency Response (NOV 1996), AGAR
Clauses that Pertain to Construction Line Items Only:
52.222-6 Construction Wage Rate Requirements (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-13 Compliance with Construction Wage Requirements and Related Regulations (MAY 2014) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-15 Performance and Payment Bonds – Construction (OCT 2010) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991)
AG-04T0-S-17-0045
52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991), Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997), Alternate I (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995) 52.243-4 Changes (JUN 2007) 52.246-21 Warranty of Construction (MAR 1994), Alternate I (APR 1984) 52.248-3 Value Engineering – Construction (OCT 2015) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996), AGAR
Clauses that Pertain to Service Line Items Only:
52.222-41 Service Contract Labor Standards (MAY 2014) 52.222-44 Fair Labor Standards Act and Service Contract Labor Standards—Price Adjustment (MAY 2014) 52.232-1 Payments (APR 1984) 52.232-11 Extras (APR 1984) 52.232-25 Prompt Payment (JAN 2017) 52.237-2 Protection of Government Buildings, Equipment, and Vegetation (APR 1984) 52.243-1 Changes – Fixed Price (AUG 1987) ALT I (APR 1984) 52.246-25 Limitation of Liability - Services (FEB 1997) 52.248-1 Value Engineering (OCT 2010) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012) 52.249-8 Default (Fixed-Price Supply and Service) (APR 1984)
I-2 FAR 52.215-8 ORDER OF PRECEDENCE—UNIFORM CONTRACT FORMAT
(OCT 1997)
Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:
(a) The Schedule (excluding the specifications).
(b) Representations and other instructions.
(c) Contract clauses.
(d) Other documents, exhibits, and attachments.
(e) The specifications.
I-3 FAR 52.217-7 OPTION FOR INCREASED QUANTITY—SEPARATELY PRICED
LINE ITEM (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within thirty (30) calendar days.
Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
I-4 FAR 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(JUL 2013)
(a) Definitions. As used in this clause— Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts—
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c)…