Statement of Work AG-04T0-S-16-0032
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 5_Horsfall-ProjectSpecifications-AG04T0S160032.pdf | ||
| 1_Horsfall-SolicitationPacket-AG04T0S160032.pdf | ||
| 4_Horsfall-ProjectPlans-AG04T0S160032.pdf | ||
| 2_Horsfall-ReturnPacket-AG04T0S160032.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA Forest Service Project Specifications
March, 2016 Horsfall Beach Septic System Replacement Statement of Work ‐ 1
STATEMENT OF WORK
Siuslaw National Forest, Central Coast Ranger District
Oregon Dunes National Recreation Area, Horsfall Beach Day Use Area
Septic System Replacement
1.01 CURRENT CONDITONS
A. The project is located at Horsfall Beach Day Use Area, located about 5 miles northwest of the
City of North Bend, Coos County, Oregon.
B. The Horsfall Beach Campground and Day Use Area consist of 37 RV camping sites, 15 day use area parking spots, and 1 camp host site.
C. The original wastewater system at Horsfall Beach Campground was developed and constructed in 1972. In 1984, the restroom was replaced with a new structure (Men’s: 2 toilets, 1 urinal, and 2 sinks; Women’s: 3 toilets and 2 sinks).
D. The building’s sewer line is connected to two 1,500 gallon concrete septic tanks via gravity.
The camp host site is also connected to the septic system.
E. The existing gravity fed drain‐field (approximately 180 lineal feet) is believed to be undersized. Because of that, and repeated breakdowns, the restroom was closed a few years ago, and they have been using portable toilets since then.
F. A site visit is strongly encouraged prior to bidding, to get a firsthand look at the existing infrastructure, terrain, soil conditions, and general site characteristics that will affect the work.
1.02 PROJECT SUMMARY
A. The work of this project consists of upgrading the septic system at Horsfall Beach
Campground. The system will be treating the sewage from the existing flush toilet building and the host site. General requirements of the project include, but are not limited to, the following:
B. The installer of the new onsite wastewater treatment (septic) system shall be licensed in the
State of Oregon to construct onsite wastewater treatment systems. A list of licensed onsite system installers, and information on how to become certified, can be found on the Oregon
Department of Environmental Quality (ODEQ) website:
http://www.deq.state.or.us/wq/onsite/licensing.htm
C. Contractor shall construct a properly functioning onsite wastewater treatment system;
provide transportation, construction materials, labor, technical expertise, and incidentals to complete the work as specified in the Contract Package.
D. All equipment and materials shall be installed in accordance with manufacturers’ instructions, and in accordance with the Specifications and Project Plans.
E. Contractor shall comply with the Oregon Administrative Rules (OARs), Chapter 340, Divisions
52, 71 and 73.
March, 2016 Horsfall Beach Septic System Replacement Statement of Work ‐ 2
F. Contractor shall comply with all applicable Federal, State, and local regulations, including but not limited to the following: Environmental Protection Agency, Oregon Occupational Safety and Health Administration, Oregon Bureau of Labor and Industries, Oregon Department of
Transportation, Oregon Department of Environmental Quality, International Plumbing Code, and National Electrical Code.
G. In the event of any discrepancy between the manufacturer’s recommendations, Specifications and Project Plans (Drawings), OARs, or other regulations, the more stringent requirement shall apply.
H. Contractor shall prepare and submit a safety plan, and provide and maintain barricades and/or warning signals as needed to notify the public of the construction work. The campground will be open and in use for the duration of this Project. Visitors should be expected at all times in the vicinity of the work.
I. Contractor shall preserve existing roads, trails, buildings and facilities, underground utilities, landscapes, vegetation, and campground landmarks to remain undisturbed on Government land. In the event of damage to existing improvements to remain, the contractor shall repair damaged improvements as directed by the Contracting Officer (CO) at no additional expense to the Government.
1.03 PROJECT DETAILS
A. Construction work will take place in the footprint and immediate vicinity of the existing sewage treatment system. Remove components of the old septic system as needed to properly install the new components. Properly decommission the old septic system in accordance with OAR 340‐071‐0185, and submit documentation with the Final Inspection
Request.
B. Remove and dispose of two (2) existing concrete septic tanks in accordance with Section
02543 of the Specifications.
C. Contractor shall provide and install two new concrete septic tanks and one dosing tank, as shown on the Plans and specified in Section 02543. All new tanks shall be approved by ODEQ:
http://www.deq.state.or.us/wq/onsite/apptanks.htm and watertight tested per OAR 340‐73‐
0025(3). Refer to Section 02543 for additional details and requirements.
D. Contractor shall provide and install an effluent filter in the second tank, and a duplex pumping package in the dosing tank.
E. Contractor shall provide and install risers from the top of all new tanks to the ground surface.
A minimum 30” diameter riser is required on all new tanks to provide adequate serviceability.
F. Contractor shall provide and install an automatic distribution valve to distribute effluent equally to six separate zones within the sand filter.
G. Contractor shall provide and install a sewage control panel and alarm system for the wastewater treatment system, wired and connected to an electrical panel located inside the existing flush toilet building. Contractor shall provide and install complete electrical services to connect dual pump system, floats, external splice box, distribution valve, and electrical
March, 2016 Horsfall Beach Septic System Replacement Statement of Work ‐ 3 wiring to the new control panel. Underground electrical lines shall be installed using electrical conduits according to the Plans and Specifications. Ensure proper size wiring and connections. Contractor shall coordinate final location of this equipment with the CO.
Electrical work shall be done by an electrician licensed in the State of Oregon.
H. Contractor shall construct a bottomless sand filter as shown in the Project Plans and specified in Section 02530. The location of the sand filter will be staked on the ground by the Forest
Service. Any components of the existing wastewater treatment system that are encountered during the work of this project and not designated for re‐use shall be removed and legally disposed of off National Forest Land.
I. Contractor shall provide to the CO and ODEQ submittals of construction materials and equipment to be utilized and installed prior to commencement of work, and as stated in the specifications. Contractor shall receive approval from the CO and ODEQ prior to commencing any construction and installation work.
J. The Forest Service will submit all appropriate documentation, including design documents and required fee(s), to obtain a construction permit (a permit has already been issued) with the County/State for the upgrades of the sewer system at this site. Contractor shall keep the regulatory agency and the CO informed of construction progress and make arrangements for regulatory inspections. Costs derived from this work shall be indirectly included under
Mobilization.
K. Contractor shall submit to the CO a copy of all paper work submitted to, and received from, the regulatory agency.
L. Contractor shall test all materials, and electrical and mechanical equipment to ensure proper functioning and operation of the sewer system.
M. Contractor shall train the CO and Forest Service representative(s) on operation and maintenance (O&M) of the new wastewater treatment system. Contractor shall schedule the training with the CO at least one week in advance, and shall be prepared to provide up to four
(4) hours of training. The O&M shall be approved by the CO prior to the operator training, and the Contractor shall use the O&M manuals as training tools during the operator training.
N. Maintain up to date, accurate as‐built drawings throughout the course of the project, as specified in Section 01300. Contractor shall provide as‐built drawings to the regulatory agency and to the CO once construction work has been completed.
O. Contractor shall remove all spoils, including removed vegetation, and construction debris
(except sand) generated and excess unsuitable materials resulting from excavation work, and legally dispose of them off National Forest Land.
P. Contractor shall restore disturbed landscape to approximately match previous existing conditions. No planting or restoration of vegetation will be required.
END OF SECTION