Attachment3-ProjectPlans-Drawings1-16.pdf
PDF 714 KB Posted
- Attached to
- Legacy Roads-Road 2234 Reconstruction Federal contract opportunity
- Solicitation number
- AG-04R4-S-10-0023
About this file
Attachment 3
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment4-SpecificationList.pdf | ||
| Attachment5-SupplementalSpecification.pdf | ||
| PacketToReturn.PDF | ||
| Solicitation-LegacyRoads.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL NOTES
1. Salvage existing aggregate during culvert installation and use as bedding and initial backfill material.
2. Designated disposal site(s) are identified on the plans. The Contracting Officer will flag the disposal areas prior to placement of material. Smooth, shape and compact to drain with spreading equipment as approved by the Contracting Officer.
3. All culvert installations/replacements with flowing water are considered stream channels. Perform work in streams between June 1st through October 15th.
4. All new culvert installations require partial bevel cut (indirect cost to corresponding culvert installation).
5. Minor excavation is required to bevel cut existing culverts and to place riprap for armoring culverts inlets and outlets (indirect cost to items 25101, and 20358B).
6. Anchors, bolts and nuts, wire, and turner elbow construction are an indirect cost to the corresponding outlet pipe installation.
7. Construction tolerance class D.
Legacy Roads- Road 2234 Reconstruction Page 3 of 16
ESTIMATE OF QUANTITIES
ITEM
NUMBER
DESCRIPTION UNIT QUANTITIES REMARKS
15101 Mobilzation Lump Sum
All Includes fire protection, temporary traffic control and equipment cleaning.
15713 Soil erosion & pollution control Lump Sum
All
20358A Removal of corrugated metal pipe, disposal method A Each 28
20358B Removal of corrugated metal pipe by cutting, disposal method A Each 1
20415 Unsuitable excavation Cubic Yard*
20419 Drainage excavation, type outlet ditch Foot 170
20479 Drainage excavation, type roadway ditch Mile 2.15
20462 Unclassified borrow, compaction method B Cubic Yard*
Government furnished material; located at South Bruno rock pit, road 2234 MP 8.61.
25101 Placed riprap, class 4 Cubic Yard*
Government furnished material; located at South Bruno rock pit, and road 2234 MP 8.61.
Generating and sorting required.
32232 Haul and place stockpiled aggregate, compaction method B Cubic Yard*
Government furnished material; located at Minto rock pit, road 2253, MP 0.30.
60256 18-inch corrugated steel pipe, 0.064-inch thickness, method B Foot 4
60278A 18-inch corrugated polyethylene pipe, type S, method B Foot 720
60278B 24-inch corrugated polyethylene pipe, type S, method B Foot 182
60278C 36-inch corrugated polyethylene pipe, type S, method B Foot 102
60278D 60-inch corrugated polyethylene pipe, type S, method B Foot 56
60654A 18-inch full-circle polyethylene outlet pipe, type S Foot 20
60654B 24-inch full-circle polyethylene outlet pipe, type S Foot 10
60708 Cleaning culverts in place Each 3
60710 Reconditioning drainage structures, culvert inlet/outlet Each 1
63501 Temporary traffic control Lump Sum
All
* Denotes contract quantity
Legacy Roads- Road 2234 Reconstruction Page 4 of 16
RECONSTRUCTION SUMMARY
MILE
POST
ITEM
NUMBER
QUANTITY UNIT DESCRIPTION OF WORK
8.93 Road 2234-170 left.
Beginning of project.
Remove stump from ditch and place on fill slope (indirect to item 20419).
8.96 Existing 18-inch CMP.
8.98 20358A 1 Each Remove existing 18-inch CMP.
60278A 40 Foot Install 18-inch HDPE pipe at same skew and grade.
20419 10 Foot Construct culvert outlet ditch.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.04 Road 2234-170 left.
9.06 20358A 1 Each Remove existing 18-inch CMP.
60278A 30 Foot Install 18-inch HDPE pipe at same skew and grade.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.11 20358A 1 Each Remove existing 18-inch CMP.
60278A 32 Foot Install 18-inch HDPE pipe at same skew and grade.
20462 3 Cubic Yard* Place select borrow to add width to right shoulder.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.17 20358A 1 Each Remove existing 12-inch aluminum metal pipe.
60278A 40 Foot Install 18-inch HDPE pipe at 900 skew and 15% grade (as staked).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
20479 0.06 Mile Begin reconstructing roadway ditch.
9.21 20358A 1 Each Remove existing 24-inch CMP.
60278C 30 Foot Install 36-inch HDPE pipe at same skew.
Lower outlet 1 ft to ground.
20419 20 Foot Construct culvert outlet ditch.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.23 End reconstructing roadway ditch.
9.30 20358A 1 Each Remove existing 18-inch CMP.
60278A 34 Foot Install 18-inch HDPE pipe at same skew and grade.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.35 Existing 18-inch CMP.
9.40 Existing 18-inch CMP.
Legacy Roads- Road 2234 Reconstruction Page 5 of 16
POST
ITEM
NUMBER
QUANTITY UNIT DESCRIPTION OF WORK
9.52 20358A 1 Each Remove existing 18-inch CMP.
60278A 30 Foot Install 18-inch HDPE pipe at 900 skew and 7% grade (as staked).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
20479 0.03 Mile Begin reconstructing roadway ditch.
9.55 20358A 1 Each Remove existing 18-inch CMP.
60278B 34 Foot Install 24-inch HDPE pipe at same skew and grade.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
End reconstructing roadway ditch.
9.64 20358A 1 Each Remove existing 18-inch CMP.
60278B 42 Foot Install 24-inch HDPE pipe at same skew and grade.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.68 20358A 1 Each Remove existing 18-inch CMP.
60278A 32 Foot Install 18-inch HDPE pipe at same skew and grade.
25101 1 Cubic Yard* Construct splash apron (5' L x 3' W x 2' D).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.69 20358A 1 Each Remove existing 24-inch CMP.
60278C 38 Foot Install 36-inch HDPE pipe at same skew and grade.
20462 20 Cubic Yard* Place select borrow to add width to right shoulder.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.73 20358A 1 Each Remove existing 18-inch CMP.
60278A 30 Foot Install 18-inch HDPE pipe at same skew and grade.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.81 20358A 1 Each Remove existing 18-inch CMP.
60278A 32 Foot Install 18-inch HDPE pipe at same skew and grade.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
9.88 Road 2234-255 right.
10.01 20358A 1 Each Remove existing 18-inch CMP.
60278A 34 Foot Install 18-inch HDPE pipe at same skew.
Lower outlet 1 ft to ground.
20419 20 Foot Construct culvert outlet ditch.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
10.08 Existing 18-inch CMP.
20462 1 Cubic Yard* Place select borrow to raise catch basin elevation.
Legacy Roads- Road 2234 Reconstruction Page 6 of 16
POST
ITEM
NUMBER
QUANTITY UNIT DESCRIPTION OF WORK
10.19 Existing 18-inch CMP.
20462 1 Cubic Yard* Place select borrow to raise catch basin elevation.
20419 20 Foot Construct culvert outlet ditch.
10.32 Existing 18-inch CMP.
10.42 Existing 18-inch CMP.
10.43 20479 0.03 Mile Begin reconstructing roadway ditch.
10.46 End reconstructing roadway ditch.
10.53 Existing 24-inch CMP.
20415 2 Cubic Yard*
Remove built up sediment and debris from culvert inlet and haul to nearest designated disposal area.
10.54 Road 2234-173 left.
10.63 20479 0.11 Mile Begin reconstructing roadway ditch.
10.74 Existing 18-inch CMP.
End reconstructing roadway ditch.
10.76 20479 0.05 Mile Begin reconstructing roadway ditch.
10.81 20358A 1 Each Remove existing 36-inch CMP.
60278D 56 Foot Install 60-inch HDPE pipe at same skew and grade.
25101 14 Cubic Yard* Construct head wall (9' L1 x 15' L2 x 7' H x 3' D).
32232 20 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
End reconstructing roadway ditch.
10.90 20358A 1 Each Remove existing 18-inch CMP.
60278B 36 Foot Install 24-inch HDPE pipe at same skew and grade.
25101 3 Cubic Yard* Construct head wall (6' L1 x 9' L2 x 4' H x 2' D).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
10.96 20479 0.06 Mile Begin reconstructing roadway ditch.
11.02 20358A 1 Each Remove existing 18-inch CMP.
60278B 40 Foot Install 24-inch HDPE pipe at same skew and grade.
25101 2 Cubic Yard* Construct splash apron (7' L x 4' W x 2' D).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
End reconstructing roadway ditch.
11.16 20479 0.09 Mile Begin reconstructing roadway ditch.
11.25 End reconstructing roadway ditch.
Legacy Roads- Road 2234 Reconstruction Page 7 of 16
POST
ITEM
NUMBER
QUANTITY UNIT DESCRIPTION OF WORK
11.34 20358A 1 Each Remove existing 18-inch CMP.
60278A 40 Foot Install 18-inch HDPE pipe at same skew and grade.
60654A 20 Foot Install 18-inch HDPE outlet pipe.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
20479 0.05 Mile Begin reconstructing roadway ditch.
11.39 20358A 1 Each Remove existing 18-inch CMP.
60278A 50 Foot Install 18-inch HDPE pipe at same skew and grade.
25101 1 Cubic Yard* Construct splash apron (5' L x 3' W x 2' D).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
End reconstructing roadway ditch.
11.45 20358A 1 Each Remove existing 18-inch CMP.
60278A 50 Foot Install 18-inch HDPE pipe at same skew and grade.
25101 1 Cubic Yard* Construct splash apron (5' L x 3' W x 2' D).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
11.48 Existing 18-inch CMP.
60710 1 Each Repair (jack open) existing culvert inlet; straighten and reform circular opening.
11.54 Existing 18-inch CMP.
11.64 Existing 18-inch CMP.
11.70 20358A 1 Each Remove existing 18-inch CMP.
60278A 40 Foot Install 18-inch HDPE pipe at same skew and grade.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
20479 0.14 Mile Begin reconstructing roadway ditch.
11.84 End reconstructing roadway ditch.
11.88 Existing 18-inch CMP.
12.03 Existing 18-inch CMP.
12.09 Existing 18-inch CMP.
20419 10 Foot Construct culvert outlet ditch.
12.16 20479 0.12 Mile Begin reconstructing roadway ditch.
12.28 Existing 18-inch CMP.
End reconstructing roadway ditch.
12.36 Existing 18-inch CMP.
12.49 Road 2234-215 left.
Legacy Roads- Road 2234 Reconstruction Page 8 of 16
POST
ITEM
NUMBER
QUANTITY UNIT DESCRIPTION OF WORK
12.55 Existing 18-inch CMP.
20479 0.07 Mile Begin reconstructing roadway ditch.
20419 30 Foot Construct culvert outlet ditch.
12.62 End reconstructing roadway ditch.
12.70 Road 2234-260 right.
12.72 Existing 18-inch CMP.
20479 0.16 Mile Begin reconstructing roadway ditch.
20419 20 Foot Construct culvert outlet ditch.
12.77 Road 2223-225 left.
12.83 Existing 18-inch CMP.
20419 20 Foot Construct culvert outlet ditch.
12.88 End reconstructing roadway ditch.
13.01 Existing 36-inch CMP.
13.02 Road 2234-270 right.
13.03 Existing 18-inch CMP.
60708 1 Each Clean existing culvert.
13.04 Road 2234-278 right.
13.05 20358A 1 Each Remove existing 12-inch CMP.
60278A 38 Foot Install 18-inch HDPE pipe at same skew and grade.
20419 20 Foot Construct culvert outlet ditch.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
13.24 Existing 18-inch CMP.
20358B 1 Each Remove 4 ft of culvert from inlet end.
60256 4 Foot Install 18-inch CMP to inlet end.
13.34 Existing 18-inch CMP.
13.42 Existing 18-inch CMP.
13.50 Existing 18-inch CMP.
20479 1.18 Mile Begin reconstructing roadway ditch.
13.57 20358A 1 Each Remove existing 18-inch CMP.
60278A 36 Foot Install 18-inch HDPE pipe at 1100 skew and 15% grade (as staked).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
13.65 20358A 1 Each Remove existing 18-inch CMP.
60278A 36 Foot Install 18-inch HDPE pipe at same skew and grade.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
Legacy Roads- Road 2234 Reconstruction Page 9 of 16
POST
ITEM
NUMBER
QUANTITY UNIT DESCRIPTION OF WORK
13.72 20358A 1 Each Remove existing 18-inch CMP.
60278A 32 Foot Install 18-inch HDPE pipe at same skew.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
13.77 Existing 18-inch CMP.
20415 1 Cubic Yard* Clean catch basin.
13.83 20358A 1 Each Remove existing 18-inch CMP.
60278A 32 Foot Install 18-inch HDPE pipe at 1100 skew and 15% grade (as staked).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
13.89 Existing 18-inch CMP.
13.94 60278A 32 Foot Install 18-inch HDPE pipe at 1100 skew and 15% grade (as staked).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
13.99 Existing 18-inch CMP.
60708 1 Each Clean existing culvert.
14.09 Existing 18-inch CMP.
20415 1 Cubic Yard* Clean catch basin.
14.22 Existing 96-inch CMP (Bugaboo creek).
Water source.
14.31 Existing 36-inch CMP.
14.36 20358A 1 Each Remove existing 18-inch CMP.
60278B 30 Foot Install 24-inch HDPE pipe at same skew and grade.
60654B 10 Foot Install 24-inch HDPE outlet pipe.
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
14.43 20358A 1 Each Remove existing 18-inch CMP.
60278C 34 Foot Install 36-inch HDPE pipe at same skew and 10% grade.
Move inlet 10 ft toward road centerline (as staked).
32232 10 Cubic Yard*
Place 6-inch depth of crushed aggregate over culvert installation. Blend to adjacent surfaces and widths to provide for smooth transition.
20415 40 Cubic Yard*
Remove built up sediment and construced earth berm from culvert inlet area and haul to nearest designated disposal area.
14.54 Existing 18-inch CMP.
60708 1 Each Clean existing culvert.
14.59 Existing 24-inch CMP.
14.66 Begin asphalt pavement.
Legacy Roads- Road 2234 Reconstruction Page 10 of 16
POST
ITEM
NUMBER
QUANTITY UNIT DESCRIPTION OF WORK
14.68 Road 2234-280 right.
End reconstructing roadway ditch.
End of Project.
Legacy Roads- Road 2234 Reconstruction Page 11 of 16
DRAINAGE LISTING
D
IA
M E
T E
R
(I N
C H
LE
N
G T
H
F T
T H
IC
K
N E
S
C
H E
S
F U
LL
C
IR
C
LE
H A
LF
R
O U
N D
D
IA
M E
T E
R
LE
N
G T
H
F U
LL
C
IR
C
LE
H A
LF
R
O U
N D
IN
LE
T
C Y
O U
T
LE
T
C Y
2234 8.98 18 40 # # # 10
9.06 18 30 # # #
9.11 18 32 # # # Place select borrow to add width to right shoulder.
9.17 18 40 # 90° 15% New skew staked.
9.21 36 30 # # 20 Lower outlet 1 ft to ground.
9.30 18 34 # # #
9.52 18 30 # 90° 7%
9.55 24 34 # # #
9.64 24 42 # # #
9.68 18 32 # # # 1
9.69 36 38 # # # Place select borrow to add width to right shoulder.
9.73 18 30 # # #
9.81 18 32 # # #
10.01 18 34 # # 20 Lower outlet 1 ft to ground.
10.08 Placed select borrow to raise catch basin elevation.
10.19 Placed select borrow to raise catch basin elevation.
10.53 Remove 2 CY of built up sediment and debris from inlet.
10.81 60 56 # # # 14
10.90 24 36 # # # 3
11.02 24 40 # # # 2
11.34 18 40 20 # # #
11.39 18 50 # # # 1
11.45 18 50 # # # 1
11.48 Repair culvert inlet.
11.70 18 40 # # #
12.09 10
12.55 30
12.72 20
12.83 20
13.03 Clean existing culvert.
13.05 18 38 # # # 20
13.24 18 4 0.064
RIPRAP
REMARKS
S T
A T
IO
N
O R
M
IL
P O
S T
CMP
OUTLET
G R
A D
E
DESIGNED
CMP
MACHINE
PLACED
O U
T
LE
T D
IT
C
H
F T
T Y
P E
S K
W
AS BUILT
INSTALLATION
DETAILS
R O
A D
N U
M B
E R
S T
A T
IO
N
O R
M
S T
PIPE OUTLET PIPE
Some installations of culverts may require additional excavation below grade line.
# Skew, grade and type shall match removed installation unless otherwise noted.
Legacy Roads- Road 2234 Reconstruction Page 13 of 16
DRAINAGE LISTING
D
IA
M E
T
C H
LE
N
G T
H
F T
T H
IC
K
N E
C
H E
S
F U
LL
C
IR
C
LE
H A
LF
R
O U
N D
D
IA
M E
T E
R
LE
N
G T
H
F U
LL
C
IR
C
LE
H A
LF
R
O U
N D
IN
LE
T
C Y
O U
T
LE
T
C Y
2234 13.57 18 36 # 110° 15% New skew staked.
13.65 18 36 # # #
13.72 18 32 # # #
13.77 Clean catch basin.
13.83 18 32 # 110° 15% New skew staked.
13.94 18 32 3 110° 15% New installation (as staked).
13.99 Clean existing culvert.
14.09 Clean catch basin.
14.36 24 30 10 # # #
14.43 36 34 # # 10% Move inlet 10 ft toward road centerline (as staked).
Remove 40 CY of constructed earth berm.
14.54 Clean existing culvert.
S T
A T
IO
N
O R
M
S T
CMP
CMP
OUTLET
DESIGNED AS BUILT
# Skew, grade and type shall match removed installation unless otherwise noted.
Some installations of culverts may require additional excavation below grade line.
G R
A D
E
MACHINE
PLACED
S T
A T
IO
N
O R
M
S T
PIPE OUTLET PIPE
T Y
P E
S K
W
INSTALLATION
DETAILS
RIPRAP
O U
T
LE
T D
IT
C
H
F T
REMARKS
R O
A D
N U
M B
E
Legacy Roads- Road 2234 Reconstruction Page 14 of 16
| Title sheet with signatures.pdf |
| Vicninty map |
| General notes |
| Estimate of quantity |
| Reconstructin summary |
| Reconstruction details |
| Culvert listing |
| Drainage construction 1 |
| Drainage constructin 2 |
File details come from the government source that posted it. Updated .