Specifications_UnionCkWater.pdf
PDF 2 MB Posted
- Attached to
- Union Creek Water System Improvements Federal contract opportunity
- Solicitation number
- AG-04N7-S-16-0012
About this file
Project Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| DRAWINGS.pdf | ||
| Construction_RFP_UnionCkWater.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA Forest Service Project Specifications
November 2015 TABLE OF CONTENTS 1 Union Creek Water System Improvements
TABLE OF CONTENTS
SECTION TITLE PHASE
I II
00 30 10 DEFINITION OF BID ITEMS X X
00 30 20 SUMMARY OF WORK X X
01 33 00 SUBMITTAL PROCEDURES X X
01 41 00 QUALITY CONTROL X X
01 56 00 ACCOMMODATIONS FOR PUBLIC TRAFFIC X X
01 57 00 TEMPORARY CONTROLS X X
01 73 20 MOBILIZATION / DEMOBILIZATION X X
01 77 00 PROJECT CLOSEOUT X X
01 78 23 OPERATION AND MAINTENANCE DATA MANUALS X X
02 41 19 SELECTIVE DEMOLITION X X
03 10 00 CONCRETE FORMS AND ACCESSORIES X
03 30 00 CAST-IN-PLACE CONCRETE X X
06 10 00 ROUGH CARPENTRY X
07 21 00 BUILDING INSULATION X
07 41 13 PREFORMED METAL ROOF PANELS X
07 46 00 SIDING X
07 62 00 SHEET METAL FLASHING AND TRIM X
07 92 00 JOINT SEALANTS X
08 11 13 HOLLOW METAL DOORS AND FRAMES X
08 71 00 DOOR HARDWARE X
09 91 00 PAINTING X
22 05 19 WATER METERS AND GAUGES FOR PLUMBING PIPING X X
22 11 13 FACILITY WATER DISTRIBUTION PIPING X X
22 11 15 HIGH DENSITY POLYETHYLENE PIPE X X
November 2015 TABLE OF CONTENTS 2
SECTION TITLE PHASE
I II
22 11 16 PLASTIC WATERLINES AND APPURTENANCES X
22 11 40 UNDERGROUND BORING FOR UTILITY LINES X
22 11 50 WATER HYDRANTS & PLUMBING APPURTENANCES X X
22 12 16 VALVES X X
22 12 17 VALVE BOXES X X
26 04 00 UNDERGROUND CONTROL CABLE X
26 05 00 ELECTRICAL X
26 05 01 ELECTRICAL COMPONENTS X
26 05 73 OVERCURRENT PROTECTIVE DEVICE COORDINATION
STUDY
X
26 27 00 POWER DISTRIBUTION AND MOTOR CONTROL X
31 11 00 CLEARING AND GRUBBING X X
31 22 00 GRADING X X
31 23 16 EXCAVATION AND BACKFILL FOR STRUCTURES X
31 23 17 EXCAVATION AND BACKFILL FOR UTILITIES X X
31 25 00 SEDIMENT AND EROSION CONTROL MEASURES X X
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 1
SECTION 00 30 10
DEFINITION OF BID ITEMS
PART 1 – GENERAL
1.01 SUMMARY
A. The intent of this section is to explain, in general; what is and what is not included in a bid item; the limits or cut-off points where one bid item ends and another begins; and method of measurements and basis of payment for work items listed in the Schedule of Items.
B. The summation of all bid items under the Schedule of Items shall equal all work required by the Drawings and Specifications regardless of whether individual items of work are described under the bid item descriptions or not.
C. Work:
1. Furnishing all labor, supervision, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the Contractor.
D. Payment:
1. For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these Specifications, as shown on the Drawings, and as staked in the field.
2. Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.
1.02 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 2
4. For items that are measured by the linear foot, such as pipe, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For standard manufactured items (such as wire, pipe) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
1.03 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery. Vehicles shall be loaded to at least their water level capacity.
Leveling of the loads may be required when vehicles arrive at the delivery point.
2. Each (EA): One complete unit, which may consist of one or more parts.
3. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 3
4. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
5. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
6. Lump Sum (LS): One complete unit, not directly measured. The bid amount is complete payment for all work described in the contract and necessary to complete the work for the item.
7. Square Foot (SF): Measured on a plane parallel to the surface being measured.
8. Square Yard (SY): Measured on a plane parallel to the surface being measured.
9. Ton: Measured on volume based on truck tickets.
1.04 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. CONTRACT QUANTITIES (CQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design, and cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 4 materials, equipment, and labor to complete the job. They shall not be measured.
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 5
DEFINITION OF BID ITEMS
BASE ITEMS: PHASE I
(A Items below)
A-1 Mobilization / Demobilization
a. Measurement for payment for mobilization shall be on a lump sum all required basis. This work shall consist of preparatory work and operations necessary for the movement of personnel equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
Measurement and payment: Payment shall be made on a lump sum basis as follows: When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less shall be paid. When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, shall be paid. Upon completion of all on the project, any unpaid amount for mobilization shall be paid.
b. Payments shall be made at the lump sum price stated in the Schedule of Items for "Mobilization/Demobilization."
A-2 Accommodations for Public Traffic
a. Measurement for payment of Accommodations for Public Traffic shall be measured on a lump sum basis and shall include maintaining facilities to accommodate public traffic through and within the project area.
b. Payment shall be made at the lump sum price stated in the Schedule of Items for "Accommodations for Public Traffic."
A-3 Erosion Control
a. Measurement for payment of Erosion Control shall be measured on a lump sum basis and shall include all erosion control measures, monitoring of erosion control, replacement of the erosion control measures as necessary, removal of the erosion control measures at the completion of the project, restoration of the area, and other items.
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 6
b. Payment shall be made at the lump sum price stated in the Schedule of Items for "Erosion Control."
A-4 8” HDPE Water Line
c. Work includes installation of pipe, including but not limited to clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, thrust block installation, backfilling and disposal of excess excavated materials, compaction, testing, flushing and disinfecting the pipeline and cleanup. Pipe shall be measured along the centerline of the pipe. There will be no measurement or payment for fittings, appurtenances, isolation valves and valve boxes, temporary blow-off, connection to the existing water main, plugging ends of abandoned water lines, or such materials covered by other bid items. All other materials, labor and equipment needed to complete the main line installation shall be incidental to the items which they relate.
d. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made under item “8” HDPE Water Line” as shown in the Schedule of Items.
A-5 6” HDPE Water Line
a. Work includes installation of pipe, including but not limited to clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, thrust block installation, backfilling and disposal of excess excavated materials, compaction, testing, flushing and disinfecting the pipeline and cleanup. Pipe shall be measured along the centerline of the pipe. There will be no measurement or payment for fittings, appurtenances, isolation valves and valve boxes, temporary blow-off, connection to the existing water main, plugging ends of abandoned water lines, or such materials covered by other bid items. All other materials, labor and equipment needed to complete the main line installation shall be incidental to the items which they relate.
b. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made under item “6” HDPE Water Line” as shown in the Schedule of Items.
A-6 4” HDPE Water Line
a. Work includes installation of pipe, including but not limited to clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, thrust block installation, backfilling and disposal of excess excavated materials, compaction, testing, flushing and disinfecting the
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 7 pipeline and cleanup. Pipe shall be measured along the centerline of the pipe, excluding water main bore under the highway. There will be no measurement or payment for fittings, appurtenances, isolation valves and valve boxes, temporary blow-off, connection to the existing water main, plugging ends of abandoned water lines, or such materials covered by other bid items. All other materials, labor and equipment needed to complete the main line installation shall be incidental to the items which they relate.
b. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made under item “4” HDPE Water Line” as shown in the Schedule of Items.
A-7 4” HDPE Bore with Casing under Highway
a. Work includes installation of pipe and casing, including but not limited to clearing and grubbing, pit excavation and backfilling, compaction, testing, flushing and disinfecting the pipeline and cleanup. Pipe shall be measured along the centerline of the bore casing. All other materials, labor and equipment needed to complete the bore shall be incidental to the items which they relate.
b. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made under item “4” HDPE Bore with Casing under Highway” as shown in the Schedule of Items.
A-8 2 1/2” Galvanized Water Line
a. Work includes installation of pipe, including but not limited to clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, thrust block installation, backfilling and disposal of excess excavated materials, compaction, testing, flushing and disinfecting the pipeline and cleanup. Pipe shall be measured along the centerline of the pipe and will stop at the building limits of water system structures - five
(5) feet from buildings foundation. There will be no measurement or payment for fittings, appurtenances, isolation valves and valve boxes, temporary blow-off, connection to the existing water main, plugging ends of abandoned water lines, or such materials covered by other bid items. All other materials, labor and equipment needed to complete the main line installation shall be incidental to the items which they relate.
b. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 8 under item “2 1/2” Galvanized Water Line” as shown in the Schedule of Items.
A-9 2” Sch. 40 PVC Water Line
a. Work includes installation of pipe, including but not limited to clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, thrust block installation, backfilling and disposal of excess excavated materials, compaction, testing, flushing and disinfecting the pipeline and cleanup. Pipe shall be measured along the centerline of the pipe from the new water main to the point of connection to the existing water main. There will be no measurement or payment for fittings, appurtenances, isolation valves and valve boxes, temporary blow-off, connection to the existing water main, plugging ends of abandoned water lines, or such materials covered by other bid items. All other materials, labor and equipment needed to complete the waterline installation shall be incidental to the items which they relate.
b. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made under item “2” Sch. 40 PVC Water Line” as shown in the Schedule of Items.
A-10 3/4” Sch. 40 PVC Service Line
a. Work includes installation of pipe, including but not limited to clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, backfilling and disposal of excess excavated materials, compaction, testing, flushing and disinfecting the pipeline and cleanup.
Pipe shall be measured along the centerline of the pipe from the new water main to the new water meter/backflow prevention device & associated appurtenances for each building. There will be no measurement or payment for fittings, appurtenances, isolation valves and valve boxes, temporary blow-off, connection to the existing water main, plugging ends of abandoned water lines, or such materials covered by other bid items. All other materials, labor and equipment needed to complete the service line installation shall be incidental to the items which they relate.
b. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made under item “3/4” Sch. 40 PVC Service Line” as shown in the Schedule of Items.
A-11 Air Release / Air Vacuum Valve Assembly
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 9
a. Measurement for payment of the Air Release / Air Vacuum Valve Assembly shall be measured on a per each basis and shall include clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, vault, valve, post, backfilling, compaction, testing, flushing and disinfecting the pipeline and cleanup. All other materials, labor and equipment needed to complete the installation shall be incidental to the item.
b. Payment shall be at the unit price stated in the Schedule of Items for “Air Release / Air Vacuum Valve Assembly.”
A-12 Water Meter with Backflow Preventer to Existing Building
a. Measurement for payment of the Water Meter with Backflow Preventer to Existing Buildings shall be measured on a per each basis and shall include meter, backflow preventer, curb stop valve, clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, box, connecting to the existing waterline at each building, backfilling, compaction, testing, flushing and disinfecting the pipeline and cleanup. All other materials, labor and equipment needed to complete the installation shall be incidental to the item.
b. Payment shall be at the unit price stated in the Schedule of Items for “Water Meter with Backflow Preventer to Existing Building.”
A-13 Yard Hydrant with Backflow Preventer
a. Measurement for payment of the Yard Hydrant with Backflow Preventer shall be measured on a per each basis and shall include hydrant, backflow preventer, clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, box, valve, post, drain rock, fabric, backfilling, compaction, testing, flushing and disinfecting the pipeline and cleanup. All other materials, labor and equipment needed to complete the installation shall be incidental to the item.
b. Payment shall be at the unit price stated in the Schedule of Items for “Yard Hydrant with Backflow Preventer.”
A-14 Well House #2 Construction, Piping & Appurtenances
a. Measurement for payment for constructing Well House #2 Construction, Piping & Appurtenances shall be measured on a lump sum basis and shall include but not be limited to site preparation, excavation, foundation, concrete slab, building, all plumbing appurtenances/connections to provide for an integrated and completely
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 10 functioning system with the existing well #2 and reservoir floats.
Piping to distribution system shall be to a point 5 feet outside the building. All other materials, labor and equipment needed to complete the installation shall be incidental to the items to which they relate.
b. Payment shall be at the unit price stated in the Schedule of Items for “Well House #2 Construction, Piping & Appurtenances.”
A-15 Well House #2 Electrical, Instrumentation and Controls
a. Measurement for payment of Well House #2 Electrical, Instrumentation and Controls shall be measured on a lump sum basis and shall include but not be limited to control systems, electrical systems and connections, telephone alarm system, control cable, building lighting, grounding, and heating for an integrated and completely functioning system with the existing well #2 and reservoir floats. All other materials, labor and equipment needed to complete the installation shall be incidental to the items to which they relate.
b. Payment shall be at the unit price stated in the Schedule of Items for “Well House #2 Electrical, Instrumentation and Controls.”
A-16 Gravel Surface Restoration
c. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Any gravel restoration necessary due to the Contractor's operation, but outside the specified trench widths, shall be done at the Contractor's own expense and at no cost to the Government.
d. Payment will be made at the unit bid prices as designed and as stated in the Schedule of Items, for "Gravel Restoration." There will be no separate payment for topsoil replacement, seeding, mulching, etc. These items shall be considered incidental to the work.
A-17 Existing Reservoir Repairs
a. Measurement for payment of Existing Reservoir Repairs shall be made on a lump sum basis and shall include repairing leaking joints, replacing roof access hatch gasket, and regrading ditch from drain outlet for improved drainage.
b. Payment shall be at the unit price stated in the Schedule of Items for “Existing Reservoir Repairs.”
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 11
A-18 Selective Demolition
a. Measurement for payment of “Selective Demolition” shall be on a lump sum basis and shall include:
i. Existing Fire Hydrants – All excavation, removal and disposal of fire hydrants, wood constructed enclosures and foundations, removal of isolation valves, removal of pipe and fittings to a minimum depth of three feet below the ground surface, capping of the existing water service, backfill, compaction, and surface restoration.
ii. Chlorinator Building – All excavation, removal and disposal of an existing building, foundations, removal of piping and valves from building to existing water main, backfill, compaction, and surface restoration.
iii. Well #2 – All excavation, removal and disposal of an existing concrete slab, fiberglass enclosure, piping, valves, and electrical controls.
b. Payment shall be at the lump sum unit price stated in the Schedule of Items for “Selective Demolition.” Damage to the existing utilities which results from this work shall be repaired at the Contractor's own expense and at no cost to the Government.
A-19 Project Closeout and Operations and Maintenance Manuals
a. Measurement and payment for the Project Closeout and Operations and Maintenance Manuals shall be made on a lump sum basis shall include all project closeout items including the punchlist, as-built drawings, all operations and maintenance manuals for the new Well House at existing Well #2 including, but not limited to control systems, electrical systems, telephone alarm system, heating, all valves and plumbing appurtenances, and other O&M manuals as required.
b. Payment shall be made at the lump sum price stated in the Schedule of Items for “Project Closeout and Operation and Maintenance Manuals".
OPTION ITEMS: PHASE II
(B Items below)
B-2 Accommodations for Public Traffic
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 12
c. Measurement for payment of Accommodations for Public Traffic shall be measured on a lump sum basis and shall include maintaining facilities to accommodate public traffic through and within the project area. This work applies only to option items as awarded.
d. Payment shall be made at the lump sum price stated in the Schedule of Items for "Accommodations for Public Traffic."
B-3 Erosion Control
e. Measurement for payment of Erosion Control shall be measured on a lump sum basis and shall include all erosion control measures, monitoring of erosion control, replacement of the erosion control measures as necessary, removal of the erosion control measures at the completion of the project, restoration of the area, and other items. This work applies only to option items as awarded.
f. Payment shall be made at the lump sum price stated in the Schedule of Items for "Erosion Control."
B-4 3” HDPE Water Line with 1-1/2” Sch. 40 PVC Electrical Conduit
a. Work includes installation of pipe and electrical conduit, including but not limited to clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, thrust block installation, backfilling and disposal of excess excavated materials, compaction, testing, flushing and disinfecting the pipeline and cleanup. Pipe shall be measured along the centerline of the pipe from Well #2 to Station 7+05 (alignment 2A) at Road 6230. There will be no measurement or payment for fittings, appurtenances, isolation valves and valve boxes, temporary blow-off, connection to the existing water main, plugging ends of abandoned water lines, or such materials covered by other bid items. All other materials, labor and equipment needed to complete the main line installation shall be incidental to the items which they relate.
b. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made under item “3” HDPE Water Line with 1-1/2” Sch. 40 PVC Electrical Conduit” as shown in the Schedule of Items.
B-5 3” & 8” HDPE Water Lines (Common Trench) with 1-1/2” Sch. 40 PVC Electrical Conduit
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 13
a. Work includes installation of multiple waterlines and an electrical conduit, including but not limited to clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings, thrust block installation, backfilling and disposal of excess excavated materials, compaction, testing, flushing and disinfecting the pipeline and cleanup.
Pipe shall be measured along the centerline of the pipe from Station 7+05 near Well #2 to Station 18+50 (alignment 2A, Road 6230). There will be no measurement or payment for fittings, appurtenances, isolation valves and valve boxes, temporary blow-off, connection to the existing water main, plugging ends of abandoned water lines, or such materials covered by other bid items. All other materials, labor and equipment needed to complete the main line installation shall be incidental to the items which they relate.
b. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made under item “3” & 8” HDPE Water Lines (Common Trench) with 1-1/2” Sch. 40 PVC Electrical Conduit” as shown in the Schedule of Items.
B-7 8” HDPE Water Line
c. Work includes waterline installation, including but not limited to clearing and grubbing, trench excavation, bedding, laying and jointing pipe and fittings thrust block installation, backfilling and disposal of excess excavated materials, compaction, testing, flushing and disinfecting the pipeline and cleanup. Pipe shall be measured along the centerline of the pipe along alignment 2A from Station 0+00 to 7+05.
There will be no measurement or payment for fittings, appurtenances, isolation valves and valve boxes, temporary blow-off, connection to the existing water main, plugging ends of abandoned water lines, or such materials covered by other bid items. All other materials, labor and equipment needed to complete the waterline installation shall be incidental to the items which they relate.
d. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Payment shall be made under item “8” HDPE Water Line” as shown in the Schedule of Items.
B-9 Gravel Surface Restoration
b. Measurement will not be made as payment will be based on contract quantities as shown in the schedule of items. Any gravel restoration necessary due to the Contractor's operation, but outside the specified trench widths, shall be done at the Contractor's own expense and at no cost to the Government.
November 2015 DEFINITION OF BID ITEMS 00 30 10 - 14
c. Payment will be made at the unit bid prices as designed and as stated in the Schedule of Items, for "Gravel Restoration." There will be no separate payment for topsoil replacement, seeding, mulching, etc. These items shall be considered incidental to the work.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION
December 2015 SUMMARY OF WORK 00 30 20 - 1 Union Creek Water System Improvements
SECTION 00 30 20
SUMMARY OF WORK
PART 1 – GENERAL
1.01 SUMMARY
A. Work for this project consists of construction of Phase I and portions of Phase II as shown on the drawings:
1. Installation of new (empty) conduit, waterlines and related valves, fittings and connections to existing service connections; cutting and capping of asbestos concrete piping
2. Site preparation and construction of 9’x15’ well house building over existing well
3. Installation of flow meters, valves and appurtenances for well house piping
4. Electrical work including installation of controls, panels and power connections
5. Repairs to existing 30,000 gallon steel tank reservoir
6. Demolition of structures: fire hydrants and enclosures
1.02 LOCATION
A. This project is located at the Union Creek Resort area and may be reached by traveling from Medford, Oregon, north on State Highway 62 approximately 55 miles to FSR 6230.
1.03 GENERAL SITE CONDITIONS AND WEATHER
A. The elevation of the project is approximately 3,300 feet above mean sea level. The construction site can experience snowfall and cold temperatures, with snow possible on the ground typically from November through March.
B. In-depth soil surveys have not been performed. Subsurface materials could include sands, gravels, silts/clays, boulders, rock etc.
C. In-depth water table surveys have not been performed; however, if water is encountered during excavation, the Contractor shall perform adequate dewatering to keep the excavation free from water and dispose of the water without damage to property. During fire season, additional restrictions may apply to the work.
December 2015 SUMMARY OF WORK 00 30 20 - 2 Union Creek Water System Improvements
1.04 USE OF PREMISES
A. General: Contractor shall have limited use of premises for construction operations, including use of project site, during construction period. Contractor’s use of premises is limited by the Government’s right to perform work or to retain other contractors on portions of project and by the use of the residents and workers at the site.
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees. Road closures will not be permitted without approval from the Contracting Officer (CO).
C. Confine storage of materials to areas as approved by the CO.
D. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all areas.
E. Preservation of Natural Features: Confine all operations to work limits of the project.
Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval.
Consult with the CO and remove agreed- on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Careful supervise excavating, grading, filling and other construction operations near trees to prevent damage.
F. Existing Utilities: Notify the CO and utility companies of proposed locations and times for excavation.
1. Contractor shall be responsible for locating and preventing damage to known utilities.
1.05 GENERAL CONSTRUCTION GUIDELINES
A. All water system construction will be in compliance with current State, Federal and Forest Service rules, regulations, and standards and shall be in accordance with industry “Best Practices”.
B. All trenching shall conform to Federal OSHA safety requirements including competent person supervision and cave-in protection.
C. Backfill trenches in roads and driveways within 4 hours.
D. Maintain orange safety fencing around open excavations when work is not actively in progress and during non-work hours.
December 2015 SUMMARY OF WORK 00 30 20 - 3 Union Creek Water System Improvements
E. Water systems shall be sanitized, fully tested, and functional before building services are connected to it. Notify the CO 72 hours in advance of any interruption of existing utilities. Utility shut off shall be limited to 6 hours per occurrence, or as approved by
CO.
F. Conduct activities so that interference with the public and / or Government personnel shall be kept to a minimum. Schedule activities requiring closures with the CO at least 7 days in advance.
G. Contractor shall contact Dig Alert (1-800-332-2344) for locating and marking.
Contractor shall field verify all utilities prior to excavation.
H. Existing construction indicated is based on limited field investigations and Government-supplied information available at time of design. Verify all existing conditions, including the elevations of existing utilities and other underground obstructions before installing new work. Potholing is incidental to the work; notify the CO if any discrepancies are discovered.
I. Protect existing work which is to remain in place, be reused, or remain the property of the Government.
J. Contractor is responsible for all temporary traffic control during construction, in accordance with approved, contractor-prepared traffic control plan.
K. Minimize construction impacts to soils, water, plants, animals, and other natural resources during construction. Confine construction operations to minimum practical area. In no case shall construction operations extend beyond limits of construction indicated without prior approval by the CO.
PART 2 – PRODUCTS (NOT USED)
November 2015 SUBMITTAL PROCEDURES 01 33 00 - 1 Union Creek Water System Improvements
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 – GENERAL
1.01 DESCRIPTION
A. The work of this section consists of submittal requirements before and during construction.
B. This section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Request for Information and other miscellaneous submittals.
1.02 RELATED REQUIREMENTS
A. Closeout submittals - Section 01 77 00.
1.03 SUBMITTAL AND APPROVAL PROCEDURES
A. All submittals shall be transmitted using Contractor form or one acceptable by the Forest Service. No action will be taken on a submittal item unless accompanied by the transmittal form.
B. The following is a list of submittals that may not consist of the complete list, and may be added to at the discretion of the Contracting Officer.
C. As specified in the individual sections, forward submittals to Contracting Officer at least 15 days before need for approval. Unless a different number is specified, submit two copies of each shop drawing, manufacturer's catalog sheets (cut sheets), two specimens of each sample, and two copies of all other submittals requested.
D. Shop Drawings: Include the following information with each copy of shop drawings:
1. Firm or entity that prepared each submittal clearly at the top of each submittal.
Name and address of the prime Contractor
2. Project name.
3. Date.
4. Date of revisions (when applicable).
5. Professional Engineer’s Stamp and Signature where required.
6. Contractor's certification that shop drawing has been checked for compliance with contract documents.
November 2015 SUBMITTAL PROCEDURES 01 33 00 - 2 Union Creek Water System Improvements
7. Number and title of appropriate Specification Section and drawing number and detail reference as appropriate.
8. Details of fabrication, assembly and erection including connections and engagement to contiguous work.
9. Materials used and manufacturer’s information.
10. All required dimensions.
11. The term "by others" shall not be used. All work to be performed by others shall be identified by Contractor or subcontractor name, discipline, or trade.
E. Samples: Samples shall be large enough to illustrate clearly the functional characteristics.
F. Manufacturers' Catalog Sheets: Submit only pertinent pages; mark each copy of standard printed data to identify specific products proposed for use.
G. Manufacturer's Installation Instructions: When contract documents require compliance with manufacturer's printed instructions, provide one complete set of instructions for Contracting Officer and keep another complete set of instructions at the project site until substantial completion.
H. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
I. Approved Equals:
1. For each item proposed as an "approved equal," submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
November 2015 SUBMITTAL PROCEDURES 01 33 00 - 3 Union Creek Water System Improvements
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waivers all claims for additional expenses that may be incurred as a result of the substitution.
J. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material.
K. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal shall contain only data specific to that individual submittal.
L. Submittal Identification:
All sets of shop drawings, manufacturer's catalog sheets, samples, and other documents submitted to the Contracting Officer must have the identification information uniquely identifying the submittal, manufacturer, date, specification section stamped on the submittal.
1. Identification information of the submittal and specification section shall be applied to the bottom right margin on each page. Identification information on samples shall be applied to the most readily visible area on the sample or on tags attached to sample.
M. Submittal Numbering:
1. Number each submittal consecutively.
2. For re-submittals use the original submittal number, plus a letter suffix beginning with A.
3. Additional re-submittals of the same item shall contain the original number with the next consecutive letter.
N. Contracting Officer's Review:
November 2015 SUBMITTAL PROCEDURES 01 33 00 - 4 Union Creek Water System Improvements
1. Submittals will be returned disapproved without technical review if identification information is missing, not filled in, the transmittal form is incorrectly filled out, submittals are not coordinated.
PART 2 – PRODUCTS (NOT USED)
PART 1- USDA Forest Service Project Specifications
QUALITY CONTROL
November 2015 01 41 00 - 1
SECTION 01 41 00
PART 1- GENERAL
1.01 DESCRIPTION
A. The work of this section consists of preparing and executing a quality control program and as-built drawings. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
B. This section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Request for Information and other miscellaneous submittals.
1.02 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control program that will ensure all services, supplies, and construction work required under this contract confom1s to the contract requirements.
B. The Contractor will employ certified independent laboratories to perform sampling and testing. The testing laboratory organization shall be certified for the type of testing work to be completed.
C. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals in accordance with the National Bureau of Standards Requirements.
1.03 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
D. As-Built Drawings
PART 2 -PRODUCTS (NOT USED)
November 2015 01 41 00 - 2
PART 3 - EXECUTION
3.01 CONTRACTOR QUALITY CONTROL PLAN
A. At a minimum, the plan shall include the following:
1. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
2. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
3. Methods of performing, documenting, and enforcing quality control of all work.
4. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.02 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer's records, submit copies of permits, licenses, certifications, inspection reports, and similar documents established for compliance with standards and regulations relevant to the on performance of the work.
3.03 TEST AND INSPECTION REPORTS
A. Submit a copy of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within two days of noted deficiency.
C. Testing and Inspection Reports shall include the following
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
November 2015 01 41 00 - 3
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and re-inspecting.
3.04 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions. These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.05 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specifications.
November 2015 ACCOMMODATIONS FOR PUBLIC TRAFFIC 01 56 00 - 1 Union Creek Water System Improvements
SECTION 01 56 00
ACCOMMODATIONS FOR PUBLIC TRAFFIC
1. PART 1 - GENERAL
1.01 SUMMARY
A. This section specifies maintaining facilities to accommodate public traffic through and within the Project for the life of the Contract. Public traffic includes motor vehicles, bicycles, and pedestrians.
1.02 RELATED SECTIONS
A. 31 23 17 – Excavation and Backfill for Utilities
1.03 PUBLIC SAFETY AND MOBILITY
A. Provide for the safety and mobility of the public and:
1. Conduct work at all times so that there is the least possible interference with or hazard to the traveling public and the affected community.
2. Locate stockpile materials and park construction equipment and vehicles that are not in active use a minimum of 30 feet from the traveled way. If this is not possible, protect the stockpile materials, equipment, and vehicles, with barrier or as directed.
3. Provide and maintain safe temporary access to business and residence driveways, temporary intersections, and temporary connections with roads, streets, and bicycle and pedestrian facilities.
4. Provide approved protection and delineation between each work area and public traffic.
5. Allow emergency vehicles immediate passage at all times.
6. Do not block driveways for more than two hours unless otherwise authorized in writing.
7. Do not perform work which would restrict or interrupt traffic movement on opposite sides of the traveled way at the same time.
November 2015 ACCOMMODATIONS FOR PUBLIC TRAFFIC 01 56 00 - 2 Union Creek Water System Improvements
2. PART 2 – PRODUCTS (NOT USED)
3. PART 3 - EXECUTION
3.01 GENERAL
Provide the following for public traffic in all construction areas:
A. Traffic Nuisance Abatement - If loose rock or dust exists on roadway surfaces, the Contractor may be required by the Contracting Officer to sweep paved surfaces with power brooms.
B. Detours and Stage Construction - Construct and remove, if required by the Contracting Officer, detours, stage construction of roadway crossings and shoulders.
C. Driveways - Provide reasonable access as follows:
1. Replace and maintain business accesses, driveways, approaches, and crossings.
2. Use reasonably well-graded aggregate material.
D. Adjacent to Excavations - Where pavement is adjacent to excavations, protect the traffic as follows:
1. At the end of each working day, backfill pavement edge excavations to the elevation of the existing pavement with permanent base material or temporary aggregate material.
2. Do not excavate along both edges of the pavement adjacent to traffic at the same time. Before excavating at the edge of the pavement on the opposite side of the roadway, complete the construction to existing pavement elevation on the side which was excavated first.
3. Remove the temporary aggregate material, if used, before placing permanent base material, and place it in the shoulder slope area or spread it uniformly over the subgrade.
3.02 MAINTENANCE
A. Provide adequately maintained accommodations at all times for public traffic through and within the Project according to this Section.
1. The Contractor is responsible for maintaining all surfaces during construction as follows:
a. Keep roads, driveways, and shoulders being used by public traffic, free of debris, aggregate, dirt, mud, and other materials that impede traffic.
b. Repair damage to surfaces caused by the Contractor's operations.
November 2015 ACCOMMODATIONS FOR PUBLIC TRAFFIC 01 56 00 - 3 Union Creek Water System Improvements
c. Maintain all detour or stage construction surfaces.
November 2015 TEMPORARY CONTROLS 01 57 00 - 1 Union Creek Water System Improvements
SECTION 01 57 00
TEMPORARY CONTROLS
1. PART 1 – GENERAL
1.01 DESCRIPTION
A. The work of this section consists of providing temporary controls.
1.02 SUBMITTALS
A. As specified in Section 01 33 00.
PART 2 – PRODUCTS (NOT USED)
2. PART 3 – EXECUTION
3.01 HOUSEKEEPING
A. Keep project neat, orderly, and in a safe condition at all times.
B. Wet down or cover stockpiles and dry materials with tarps to prevent blowing dust.
Covers shall be adequately anchored for all wind conditions.
C. Do not store rubbish or volatile waste on-site. Dispose of all waste materials as specified or according to State requirements.
D. Utilize excavated material as soon as possible.
3.02 DISPOSAL
A. Excess excavated material (including rocks and boulders) that cannot be used in construction may be hauled to the waste disposal site (see drawing at the end of this section) or removed from Government property.
B. Unless otherwise specified, all removed material becomes the property of the contractor and shall be disposed of off Government property.
C. Vegetative waste may be hauled to the vegetative waste disposal site (see drawing at end of this section) or chipped and spread evenly in areas adjacent to the clearing limits in depths no greater than 3 inches.
D. Immediately remove hazardous rubbish from project site. Place other construction debris in refuse containers at least daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the Forest Service property. Do not burn or bury refuse.
November 2015 TEMPORARY CONTROLS 01 57 00 - 2 Union Creek Water System Improvements
3.03 AIR AND WATER POLLUTION CONTROL
A. Provide and install all erosion control fencing and other measures as necessary.
B. All chlorinated water shall be de-chlorinated and other contaminants removed prior to discharging to any storm drainage or natural waterways. All discharges of water from this project shall be approved by the Contracting Officer.
C. Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.
D. Do not dispose of volatile wastes or oils in storm or sanitary drains.
E. Do not allow waste materials to be washed into streams or bodies of water.
4.
November 2015 TEMPORARY CONTROLS 01 57 00 - 3
Vegetative Waste Site
November 2015 TEMPORARY CONTROLS 01 57…