- AG-0489-S-10-0479
About this file
Solicitation Package (Sections B-M)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PacCrestTr Add'lMeasure 2 FireRqts.doc | DOC document | |
| PacCrestTr SpecList.doc | DOC document | |
| PacCrestTr PastPerf DataSheet.doc | DOC document | |
| PacCrestTr DwgsPlans.pdf | ||
| PacCrestTr Specs.pdf | ||
| PacCrestTr FireSptRqts.doc | DOC document | |
| PacCrestTr SF18 Soln.pdf | ||
| PacCrestTr WageDet.doc | DOC document | |
| PacCrest ARRA Trail SignDetails.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION RFQ
AG-04N0-S-07-0008
Ochoco National Forest
Re-Roofing
Recovery-Pacific Crest Trails Restoration
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
RECOVERY – PACIFIC CREST TRAILS RESTORATION
THREE SISTERS WILDERNESS
DESCHUTES NATIONAL FOREST
DESCHUTES COUNTY, OREGON
SCHEDULE OF ITEMS
PAY ITEM
| DESCRIPTION |
| MM |
| QTY |
| UNIT |
| UNIT PRICE |
| EXTENDED PRICE |
| 922(02) |
| Rock Waterbar |
| AQ |
| 177 |
| EA |
| $ |
| $ |
| 951(01) |
| Mobilization |
| LSQ |
| 1 |
| LS |
| $ |
| $ |
| 991(03) |
| Maintain Waterbars |
| AQ |
| 351 |
| EA |
| $ |
| TOTAL PRICE |
| $ |
NOTE: Payment for bond premiums in accordance with Clause FAR 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under
951.01 Mobilization. Payment will be made on actual work performed as described in Section 951.01 Work unless otherwise noted Please complete the following:
Name of Contractor:
Name and title of person authorized to sign offer:
Signature: ____________________________________________ Date: ________________________
TIN: _______________________________________ DUNS: ________________________________ E-mail Address:__________________________________
Telephone Number:_______________________________
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 Scope of Contract This project consists of hand construction on feeder trails to the Pacific Crest Trail located within the Three Sisters Wilderness Area, Deschutes National Forest. There are four trails included in this project to include: #2, Horse Lake Trail (1.5 miles long), #3, Island Meadows Trail (1.1 miles long), #14, Six Lakes Trail (5.2 miles long), and #20 Mirror Lakes Trail (3.9 miles long). Work consists of mobilization and constructing rock waterbars and maintaining existing rock and log waterbars. Only conventional wilderness hand construction methods are allowed on the trails.
C.2 Project Location From the Deschutes National Forest Service Supervisor’s Office in Bend Oregon:
Follow Century Drive to Cascade Lakes Highway (County Rd 46) approximately 26 miles to the Mirror Lakes trailhead (trail #20). Continue on Cascade Lakes Highway for approximately 3 miles to the Elk Lake trailhead (trail #2 & #3). Continue on Cascade Lakes Highway for approximately 2 miles to the Six Lakes trailhead (trail #14).
C.3 Price Range The magnitude of construction is estimated between $25,000 and $100,000.
C.4
SPECIFIC WORK REQUIREMENT
Trail construction in wilderness will be by hand tools only. See requirements as provided in the specifications and AS SHOWN ON THE DRAWINGS.
C.5
APPLICABLE SPECIFICATIONS
FOREST SERVICE STANDARD SPECIFICATION FOR CONSTRUCTION OF TRAILS Region 6 Customary Units July 2005 shown in the specification listing and attached to the contract are applicable to this contract. All specifications not included in the specification listing, but referenced by listed specifications, are applicable.
C.6 FAR 52.211-3 AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (JUN 1988)
The specifications cited in this solicitation may be obtained from:
| Specification |
| Address |
| USDA Forest Service - Region 6, U.S Customery Specifications for Construction and Maintenance of Trails, Pacific Northwest Region |
| http://www.fs.fed.us/database/acad/dev/trails/trails.htm |
| Specification |
| Address |
| AASHTO Standards |
| American Association of State Highway and Transportation Officials |
341 National Press Building
Washington, DC 20024
| ACI |
| American Concrete Institution |
Box 19150 Redford Station
Detroit, MI 48219
| ASTM Standards |
| American Society for Testing Materials |
1916 Race Street
Philadelphia, PA 19103
(215) 199-5462
| AWPA |
| American Wood Preservers Association |
PO Box 849
Stevensville, MD 21666
| FS |
| Federal Specifications (GSA) |
Building 197, Washington Navy Yard, SE
Washington, DC 20407
| MUTCD |
| Manual on Uniform Traffic Control Devices |
Superintendent of Documents
U.S. Government Printing Office
Washington, DC 20402
| WCLIB |
| West Coast Lumber Inspection Bureau |
PO Box 23145
Portland, OR 97223
| WWPA |
| Western Wood Products Association (Grading Rules) |
1500 Yeon Building
Portland, OR 97204
NOTE: The request should identify the solicitation number and the specification requested by date, title, and number, as cited in the solicitation.
C.7 FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29. (Aug 1998)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to—
GSA Federal Supply Service Specifications Section, Suite 8100 470 East L’Enfant Plaza, SW Washington, DC 20407
Telephone (202) 619-8925 Facsimile (202) 619-8978.
(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.
C.8 AGAR 452.211-72 Statement of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J, and comply with all safety and health regulations stipulated by OSHA.
C.9 AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
C.10 Pre-BID CONFERENCE No pre-bid conference is currently scheduled.
C-11
FAR 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
a. The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
b. There are no site visits planned.
C.12
TECHNICAL CONTACT
The Contracting Officer’s Representative for this project is Bryan Kurtz, (541) 410-0279 or e-mail at bkurtz@fs.fed.us.
C.13
MEASUREMENT AND PAYMENT
Refer to Standard Specifications 906 and 907 for details on measurement and payment.
C.14
SAFETY
The contractor shall provide the crew with proper safety equipment, which includes, but is not limited to: Hardhats, hearing protection, eye protection, gloves, chaps, nonskid boots, etc. The Contractor and the Contractor’s employees shall adhere to all safety regulations and guidelines applicable to this type of work. It is the contractor’s responsibility to know what safety regulations and guidelines are applicable to this type of work. The Contractor shall provide a written, job-specific safety plan for the inherently hazardous conditions that exist during operations. The Contractor’s safety plan shall identify and describe any inherently hazardous conditions and specific actions to reduce these hazards. This plan shall be provided to the Contracting Officer at the pre-work conference. Work shall not commence on this project if the Contractor fails to provide a safety plan. Inherently hazardous conditions that could lead to serious injury or loss of life are lacerations from saws, slips and trips from uneven terrain, hidden obstacles of slope of ground, driving and weather conditions. These are not inclusive.
C.15
TRAFFIC CONTROL
As per Section 904 of the Specifications.
C.16
PERFORMANCE REQUIREMENTS
a. Adhere to all Standard Specifications, and Drawings for the Construction and Maintenance of Trails.
b. Communicate with the CO and COR as to progress, location, and completion of items.
c. Adhere to all Contract Requirements listed herein.
d. Adhere to all requirements of Region 6 Fire Protection Requirement
C.17
FAR 52.236-4 PHYSICAL DATA (APR 1984)
Except as is specifically SHOWN ON THE DRAWINGS, no physical data is available from the Government.
C.16
SUBMITTALS, SHOP DRAWINGS, MATERIAL CERTIFICATIONS AND TESTING REPORTS
SUBMITTALS
The following shall be submitted on this project:
| Title |
| Referenced By Specification No. |
| Time of Government Approval after Submittal |
| Project Schedule |
| FAR 52.236-15 |
| 5 days |
| Health and Safety Plan (Accident Prevention) |
| 107.08 |
| 5 days |
SHOP DRAWINGS
The following shop drawings shall be submitted on this project:
| Title |
| Referenced By Specification No. |
| Time of Government Approval after Submittal |
NONE
MATERIAL CERTIFICATIONS AND TESTING REPORTS
The following material certifications and/or testing reports shall be submitted to the Contracting Officer’s Representative on this project:
| Title |
| Referenced By Specification No. |
NONE
PART I—THE SCHEDULE
SECTION D--PACKAGING AND MARKING
{For this Solicitation, there are no clauses in this Section}
SECTION E--INSPECTION AND ACCEPTANCE
E.1 FAR 52.246-1 Contractor Inspection Requirements (Apr 1984)
The Contractor is responsible for performing or having performed all inspections and tests necessary to substantiate that the supplies or services furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers’ parts. This clause takes precedence over any Government inspection and testing required in the contract’s specifications, except for specialized inspections or tests specified to be performed solely by the Government.
E.2 FAR 52.246-12 Inspection of Construction (Aug 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may— By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
E.2
AGAR 452.246-70 INSPECTION AND ACCEPTANCE (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at On-site
E.3
CONFORMITY WITH DRAWINGS AND SPECIFICATIONS
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
SECTION F--DELIVERIES OR PERFORMANCE
F.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
FAR 52.242-14 Suspension of Work (Apr 1984) FAR 52.242-15 Stop-Work Order (Aug 1989)
FAR 52.241-17 Government Delay of Work F.2
FAR 52.211-10 COMMENCMENT, PROSECUTION, AND COMPLETION
OF WORK (APR 1984)
The contractor shall be required to (a) commence work under this contract within 10 days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than September 15, 2010. The time stated for completion shall include final cleanup of the premises. Work is estimated to begin on or about June 15, 2010.
F.3 AGAR 452.236-75 Maximum Workweek--Construction Schedule (NOV 1996) Within five (5) calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following in writing for approval:
(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work.
The maximum work week that will be approved shall be coordinated with the Contracting Officer’s Representative.
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 FAR 52.236-6 Superintendence by the Contractor (Apr 1984)
At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor G.2 AGAR 452.215-73 Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled as determined by the Contracting Officer after the date of contract award. The conference will be held at a location determined by the Contracting Officer and/or COR.
(NOTE: The Government may, at its option, suspend work with full count of contract time continuing, if the Contractor fails to provide a Contractor’s Representative on site who is (1) conversant in English, and (2) able to read and understand the Contract.)
G.3 Designation of Contracting Officer's Representative The Contracting Officer designates the Contracting Officer's Representative (COR).
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)
On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR.
If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
G.4 Notification of Subcontracting The Contractor shall promptly notify the Contracting Officer upon entering into any subcontract arrangement. The notification shall include as a minimum:
1. The name, address, and telephone number of the subcontractor.
2. The date upon which the subcontract was entered into and its duration.
3. A detailed description of the work being subcontracted including a listing of contract items, units, etc., as appropriate.
G.5 Public Officials Not Personally Liable There shall be no personal liability upon the Contracting Officer or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them, by, or with the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the Government.
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1
USE OF PREMISES
a. Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for the Contractor.
b. Camping is allowed at the trailhead. Camping is also allowed Coyote Creek and Switchback Camp, as shown on map. The contractor will be responsible for restoring the campsites to their original condition.
c. Unless provided otherwise, the Contractor shall: (i) provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State, and local regulations.
d. Camp sites and trailer parking areas used by any employee working on the project for the contractor shall be kept neat and clean. There shall be no improvements made to the site.
H.2
LOCAL MATERIALS SOURCES
All borrow areas shall be approved in advance by the COR and generally shall be so located and excavated as to be screened from the trailway, or utilize suitable material generated from trail construction.
H.3
LANDSCAPE PRESERVATION
(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.
(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products onsite, appropriate preventive measures shall be taken to ensure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states.
i) Servicing of all equipment shall be done only in the area approved by the Contracting Officer.
ii) If the total oil or oil products storage exceeds 6,000 litters or if any single container exceeds a capacity of shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer. The Contractor will be required to make reasonable attempts to preserve the scenic and natural environment along this construction project.
(c) Trash and Refuse - Contractor shall remove all of his own trash and refuse from the contract area. Material to be removed includes, but is not limited to; used engine oil, oil filters, oil cans, grease cartridges, camp refuse such as tin cans, paper, garbage, etc. This material must be removed to a State, County, or Municipality-designated solid waste disposal area.
H.4
CLEANING OF TOOLS AND EQUIPMENT
To prevent the introduction of seeds of noxious weeds onto National Forest land, Contractor shall ensure all tools and equipment moved onto National Forest land is free of soil, seeds, vegetative matter, or other debris that contain or hold seeds. Contractor shall employ whatever cleaning methods necessary to ensure compliance the the terms of this provision, and shall notify the Forest Service prior to moving each piece of equipment onto National Forest land. Notification shall include identifying the location of the equipment’s most recent operations. Upon request of Forest Service, arrangements will be made for the Forest Service to inspect each piece of equipment prior to it being placed into service.
H.5
USE OF MOTORIZED EQUIPMENT
No motorized equipment is permitted.
H.6
USE OF PACK AND SADDLE ANIMALS
Use of Livestock. Riding and pack stock may be used to transport personnel, supplies, materials, and equipment to and from, and within the project area. Commonly accepted (“Leave NoTrace”), low impact stock-handling techniques shall be used to minimize the impact from stock on National Forest land. Stock use is restricted as follows:
(1) Stock shall not be tied directly to trees except for brief (less than 1 hour) periods for loading and unloading. For longer periods, low impact high-line methods shall be used.
(2) The number of stock allowed shall not be more than the number needed to accomplish contract work.
(3) No grazing will be allowed. Stock shall be contained with 100% feed provided by the Contractor. All hay (cubes or bales) used on National Forest lands shall be certified as weed seed free. Containment areas (hitch lines, electric fence corrals, supplemental feeding areas, etc.) shall be moved every 10 days or as otherwise directed by the Contracting Officer (CO). Containment areas shall not be within 200 feet of any permanent water source.
H.7
CONTROL OF EROSION, SEDIMENTATION AND POLLUTION (USDA 452.236-74) (FEB 1988)
a. Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
b. Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged on the ground; into or near rivers, streams, and impoundments; or into natural or manmade channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
H.8
AGAR 452.236-73 ARCHAEOLOGICAL OR HISTORIC SITES (FEB 1988)
If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.
H.9
DISPOSAL OF CONSTRUCTION DEBRIS
Debris from the construction shall be disposed of at a site and in a manner approved by the Contracting Officer.
H.10
CLEAN-UP
The following is in addition to FAR Clause 52.236-12.
The contractor shall remove all construction stakes, tags, and plastic flagging located within 50 feet of the completed trail centerline for the entire length of the project within 5 days after the final acceptance of all other work on the project.
H.11
AGAR 452.236-77 EMERGENCY CONTROL (FEB 1988)
a. Contractor's Responsibility of Fighting Fire. The Contractor, under the direction of the Forest Supervisor or, in the absence of said officer, acting independently, shall immediately extinguish all fires on or in the vicinity of the project. If it is determined subsequently by the Contracting Officer that a fire was caused by the Contractor or the Contractor's agents or employees, whether caused directly or indirectly as a result of Contractor operations, the Contractor's cost relating to extinguishing the fire shall not be reimbursed by the Government and shall be the sole responsibility of the Contractor. In addition, the Contractor may be held liable for all damages on costs incurred by the Government for labor subsistence, equipment, supplies, and transportation deemed necessary to suppress a fire set or caused by the Contractor or the Contractor's agent or employees.
b. Contractor's Responsibility for controlling Other Emergencies. When requested by the Contracting Officer, the Contractor shall allow the Forest Service to temporarily use not less than the current area rate established by the Forest Service. Employees and equipment will be released from emergency operations when other labor and equipment adequate for the protection of the area is obtained.
H.12
BARRICADES, WARNING SIGNS, AND OTHER DEVICES
Approved signs shall be placed at the trailhead notify the public of the construction activity.
H.13
OTHER CONTRACTORS
Other Contractor(s), Forest Service Crews, or volunteer groups may be working adjacent to the project site. The Contractor shall fully cooperate with the others, including planning and notification of construction activities, camp sites, or other actions involving public safety.
H.14
PRODUCT SUBSTITUTIONS, SHOP DRAWINGS AND MATERIAL CERTIFICATION
Any modification of other items, designs, materials, products or equipment (including Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.
H.15 Safety Prior to allowing any work to commence on the project, the Contractor must submit a Safety Plan, to the Contracting Officer that is in accordance with State of Oregon OSHA Regulations. Such safety plan must include all tasks and related activities anticipated to successfully complete the work. Identify inherently hazardous conditions that could lead to serious injury or loss of life.
H.16 Personal Protective Equipment (PPE)
a. The Contractor will train in the safe operation and use of equipment to be used in contract performance.
b. PPE, including but not limited to PPE for the eyes, face, head and extremities shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered in a manner capable of causing injury or impairment in the function of any part of the body.
c. Defective or damaged PPE shall not be used.
d. The Contractor shall assure that each employee wears foot protection that provides adequate traction and ankle support that is constructed with leather or other cut-resistant material which will protect the employee against contact with any running equipment.
e. The Contractor shall provide, at no cost to the employee, and assure that each employee who works in an area where there is potential for head injury from falling or flying objects, wears a hardhat that meets the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.
f. The Contractor shall provide, at no cost to the employee, where there is potential for eye injury due to flying objects, eye protection that meets the minimum requirements of ANSI standard Z87.1-2003.
g. The Contractor shall provide, at no cost to the employee, hearing protection where there is a potential for hearing loss due to high intensity noise.
H.17 FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS(APR 1984)
a. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.
b. The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made know to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
H.18
CONTROL OF EROSION, SEDIMENTATION AND POLLUTION (USDA
452.236-74) FEB 1988
a. Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
b. Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged on the ground; into or near rivers, streams, and impoundments; or into natural or manmade channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
H.19
FIRE PROTECTION REQUIREMENTS
The following fire requirements are attached in Section J and are applicable:
a. Fire Protection and Suppression, R6-FS-6300-52 (5/97)
b. Additional Fire Precautionary Measure 2 – Communications, R6-FS-6300-54 (5/89) H.20
EMERGENCY RESPONSE (USDA 452.236-77) (NOV 1996)
(a) Contractor’s Responsibility for Fighting Fire. (1) The Contractor, under the provision of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish, all fires on the work site other than those fires in use as a part of the work. (2) The contractor may be held liable for all damages and for all costs incurred by the Government for labor subsistence, equipment, supplies, and transportation deemed necessary to suppress a fire set or caused by the Contractor or the Contractor’s agent or employees.
(b) Contractor’s Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.
(c) Contractor’s Responsibility for Responding to Emergency. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to restricted to fire fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.
H.21
CONTROL OF NOXIOUS WEEDS—CLEANING OF EQUIPMENT
To prevent the introduction and control the spread of seeds of noxious weeds onto and around National Forest land, the Contractor shall ensure all equipment moved onto National Forest land is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. When the Contractor is working in an area that has been identified as a noxious weed infestation area, the Contractor shall ensure equipment is cleaned of weed seeds prior to moving to another work area on the Forest. The Contractor shall employ whatever cleaning methods necessary to ensure compliance with the terms of this provision, and shall notify the Forest Service prior to moving each piece of equipment onto National Forestland, unless otherwise agreed in writing. Notification will include identifying the location of the equipment’s most recent operations. The Contractor shall certify, in writing, compliance with the terms of this clause prior to each start-up of operations. For the purposes of this clause, “equipment” includes all motorized equipment operated off system roads, transport vehicles, and all motorized equipment used in road maintenance. Not included are log trucks, chip vans, pickup trucks, cars, or other vehicles used to daily transport personnel.
PART II-CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
I.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (MAY 2008) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.222-3 Convict Labor (JUN 2003) 52.222-6 Davis-Bacon Act (JUL 2005) 52.222-7 Withholding of Funds (FEB 1988)
52.222-8 Payrolls and Basic Records (FEB 1988) (Deviation, JAN 2010) 52.222-9 Apprentices and Trainees (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements (FEB 1988)
52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988)
52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (FEB 1988)
52.222-20 Walsh-Healy Public Contracts Act (DEC 1996) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) 52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998)
52.222-50 Combating Trafficking in Persons (SEP 2007) 52.223-5 Pollution Prevention and Right-to-Know Information (AUG 2003)
52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007)
52.224-1 Privacy Act Notification (APR 1984)
52.224-2 Privacy Act (APR 1984)
52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)
52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)
52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (FEB 1992)
52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) 52.228-14 Irrevocable Letter of Credit (DEC 1999)
52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002) 52.232-23 Assignment of Claims (JAN 1986)
52.232-27 Prompt Payment for Construction Contracts (OCT 2008)
52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003)
52.233-1 Disputes (JUL 2002)
52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)
52.236-2 Differing Site Conditions (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)
52.236-5 Material and Workmanship (APR 1984)
52.236-6 Superintendence by the Contractor (APR 1984)
52.236-7 Permits and Responsibilities (NOV 1991)
52.236-8 Other Contracts (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984)
52.236-10 Operations and Storage Areas (APR 1984)
52.236-11 Use and Possession Prior to Completion (APR 1984)
52.236-12 Cleaning Up (APR 1984)
52.236-13 Accident Prevention (NOV 1991) Alternate I (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984)
52.236-17 Layout of Work (APR 1984)
52.236-26 Preconstruction Conference (FEB 1995) 52.243-5 Changes and Changed Conditions (APR 1984)
52.244-6 Subcontracts for Commercial Items (MAR 2009)
52.245-1 Property Records (JUN 2007) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short From) (APR 1984)
52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996)
452.236-73 Archeological or Historic Sites (FEB 1988)
452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)
452.236-76 Samples and Certificates (FEB 1988)
452.236-77 Emergency Response (NOV 1996) I.2 FAR 52.203-15 – Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009 (Mar 2009)
(a) The Contractor shall post notice of employees rights and remedies for whistleblower protections provided under section 1553 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111–5).
(b) The Contractor shall include the substance of this clause including this paragraph (b) in all subcontracts.
(End of clause)
I.3 FAR 52.204-7 Central Contractor Registration (APR 2008)
(a) Definitions. As used in this clause—
“Central Contractor Registration (CCR) database” means the primary Government repository for Contractor information required for the conduct of business with the Government.
“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.
“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.
“Registered in the CCR database” means that—
(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and
(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record “Active”. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.
(b)
(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number—
(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business name.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(iii) Company physical street address, city, state and Zip Code.
(iv) Company mailing address, city, state and Zip Code (if separate from physical).
(v) Company telephone number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(g)
(1)
(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to:
(A) Change the name in the CCR database;
(B) Comply with the requirements of Subpart 42.12 of the FAR;
(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.
(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the Internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961-5757.
I.4 FAR 52.204-11 – American Recovery and Reinvestment Act—Reporting Requirements (Mar 2009)
(a) Definitions. As used in this clause—
“Contract,” as defined in FAR 2.101, means a mutually binding legal relationship obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds and that, except as otherwise authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited to) awards and notices of awards; job orders or task letters issued under basic ordering agreements; letter contracts; orders, such as purchase orders, under which the contract becomes effective by written acceptance or performance; and bilateral contract modifications. Contracts do not include grants and cooperative agreements covered by 31 U.S.C. 6301, et seq. For discussion of various types of contracts, see FAR Part 16.
“First-tier subcontract” means a subcontract awarded directly by a Federal Government prime contractor whose contract is funded by the Recovery Act.
“Jobs created” means an estimate of those new positions created and filled, or previously existing unfilled positions that are filled, as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as ‘‘full-time equivalent’’ (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
“Jobs retained” means an estimate of those previously existing filled positions that are retained as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as ‘‘full-time equivalent’’ (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
“Total compensation” means the cash and noncash dollar value earned by the executive during the contractor’s past fiscal year of the following (for more information see 17 CFR 229.402(c)(2)):
(1) Salary and bonus.
(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Statement of Financial Accounting Standards No. 123 (Revised 2004) (FAS 123R), Shared Based Payments.
(3) Earnings for services under non-equity incentive plans. Does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.
(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.
(5) Above-market earnings on deferred compensation which is not tax-qualified.
(6) Other compensation. For example, severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property if the value for the executive exceeds $10,000.
(b) This contract requires the contractor to provide products and/or services that are funded under the American Recovery and Reinvestment Act of 2009 (Recovery Act). Section 1512(c) of the Recovery Act requires each contractor to report on its use of Recovery Act funds under this contract. These reports will be made available to the public.
(c) Reports from contractors for all work funded, in whole or in part, by the Recovery Act, and for which an invoice is submitted prior to Mar 31, 2010, are due no later than April 10, 2010. Thereafter, reports shall be submitted no later than the 10th day after the end of each calendar quarter.
(d) The Contractor shall report the following information, using the online reporting tool available at http://www.FederalReporting.gov .
(1) The Government contract and order number, as applicable.
This is the start of the file's text. The full file is on GovTribe.