Exhibit 1 Spec List and Specifications.pdf
PDF 471 KB Posted
- Attached to
- RECOVERYSTARR SNOW PARK PAVING Federal contract opportunity
- Solicitation number
- AG-0489-S-10-0338
About this file
Exhibit 1 - Spec List and Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AG-0489-S-10-0338 sol package.pdf | ||
| Exhibit 3 title_sheet.pdf | ||
| Exhibit 2 Malheur Road Rules.pdf | ||
| Exhibit 3 Starr Snow Park.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
153 - Contractor Quality Control
153.04 Records
154 - Contractor Sampling and Testing
155 - Schedules for Construction Contracts
155 Delete
156 - Public Traffic
170 - Develop Water Supply and Watering
170 –water supply and watering
171 - Weed and Disease Prevention
303 - Road Reconditioning
404 - Minor Hot Asphalt Concrete
404.02 Composition of Mix (Job-Mix Formula)
404.04 Weather Limitations
404.06 Placing
404.07 Compacting (a)
404.09 Acceptance
Table 404-1. Sampling and Testing Requirements
409 - Asphalt Surface Treatment
409.02 Material
409.06 Weather
409.06 Date & Time
409.08 Asphalt Application
409.10 Fog Seal
Table 409-2 Approximate Quantities of Material – Double Course Surface Treatments
409.13 Acceptance
Table 409-4 Sampling and Testing Requirements
411 - Asphalt Prime Coat
411.06 Asphalt Application
412 - Asphalt Tack Coat
703 - Aggregate
703.05 Subbase, Base, Surface Course, and Screened Aggregate
703.10(e) Flakiness Index
703.10(i) Adherent Coating
Table 703-7 Target Value Ranges
718 - Traffic Signing and Marking Material
718.05 Aluminum Panels
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule --The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
http://www.nist.gov/
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price --“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or
“design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96
Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service --The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse --A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36
CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards --The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.01_nat_us_07_31_2007
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be str ived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to
106.05 inclusive. The primary method of acceptance is specified in each Section of work.
However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program.
Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.
If the validity of the Government test results cannot be determined, the Contractor and
Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
―except as provided in Subsection 106.07‖.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill P lan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
Exact time and location of spill including a description of the area involved.
Containment procedures.
Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections :
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
153 - Contractor Quality Control
153.04_nat_us_10_24_2007
153.04 Records.
Delete all but the first sentence
154 - Contractor Sampling and Testing
154.01_nat_us_05_24_2005
154.01 Description
Delete the last sentence of the first paragraph.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.00_nat_us_04_17_2007
Delete Section 156 in its entirety and replace with the following:
Description
156.01 This work consists of controlling and protecting public traffic adjacent to and with in the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Construction sign panels 633
Retro-reflective sheeting 718.01
Temporary concrete barrier 618
Temporary plastic fence 710.11
Temporary traffic control devices 718.22
156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed ___ minutes at any one time followed by an open period of no less than ___ minutes.
Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the
MUTCD. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting
Officer as part of the traffic control plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic control devices clean.
(h) Remove all temporary traffic control devices upon contract completion or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services
Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s).
Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.
Prior to closing roads during construction, give written notice to the Contracting Officer at least
10 days in advance.
Table 156-1
Temporary Road Closures
Road
Number
From
Terminus
To
Terminus
Maximum
Consecutive
Days of
Closure
Minimum
Consecutive
Days Open
156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.
170 - Develop Water Supply and Watering
170.00_0604_us_03_26_2009
170 –water supply and watering
DESCRIPTION
170.01 This work consists of providing facilities to furnish an adequate water supply, hauling, and applying water for surface blading and shaping, dust abatement, and surfacing of roads as necessary to provide safe travel for low and/or high clearance vehicles; to protect adjacent resource values and road investments; and to prevent damage to roads during use by Contractor.
2. MATERIALS
170.02 Suitable and adequate water sources are located 5.5 miles North of the project site at the intersection of U.S. Highway 395 and National Forest Road 3920. If the Contractor elects to provide water from other than the designated source, Contractor shall be responsible to obtain the right to use the water and pay any royalty involved. Forest Service shall be furnished a copy of any agreement obtained by the Contractor.
3. EQUIPMENT
170.03
a. Mobile watering equipment shall have water tight tanks of known capacity when used for mixing dust abatement materials. The tank capacity shall be measured prior to use.
b. An air gap, or positive anti-siphon device, shall be provided between the water source and the vehicle being loaded if: (1) the vehicle has been used for other t han water haul, (2) the source is a domestic potable water supply, (3) or the water is used for tank mixing with any other materials.
c. Designated water sources may require some work prior to their use. Such work may include cleaning ponding areas, installing temporary weirs or sandbags, pipe repair, pump installation or other items appropriate to Contractor's operation. Flowing streams may be sandbagged on a temporary basis or a weir placed to pond the water. Water draw shall not be more than 1/3 of the stream flow. Pumping shall not result in no or negligible stream flow below site. Work within flowing streams will require review and approval by a Forest
Service Fish or Hydrology Specialist.
d. Foot valves on pumps will be screened with screens that meet National Marine Fishery
Services standards. NMFS developed criteria for pump intake screens will be used on all water pump intakes as described in the ―Addendum, Juvenile Fish Screen Criteria For
Pump Intakes‖ (NMFS, May 9, 1996).
Intake hose screen mesh openings shall not exceed 3/32 inch (2.29mm) woven wire or perforated plate screens, or 0.0689 inch (1.75mm) for profile wire screens, with a minimum 27% open area.
If fry size salmonids are never present at the site, screen size opening shall not exceed ¼ inch
(6.35mm) for woven wire, perforated plate screens, or profile wire screens, with a minimum of
40% open area.
Trucks will be maintained to prevent oil leaks. Loading is done in a manner to prevent overflowing and discharge of wash into stream.
Standard operating practice shall be to protect the stream bank, riparian area, and provide maintenance for the access road.
171 - Weed and Disease Prevention
171.00_nat_us_03_30_2005
Description
171.01 This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest
System lands.
Material
171.02 Conform to the following Subsection:
Water 725.01
Construction Requirements
171.03 General . Notify the CO in writing at least 15 days before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
Perform all work at a location designated on the plans or other locations approved in writing.
Provide the CO with an opportunity to monitor the washing and inspection.
171.04 Equipment. Use a high pressure washing system.
For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
For work at a commercial washing facility, use an approved facility.
171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment.
Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment.
Rewash the construction equipment as necessary or as directed.
171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.
Measurement
171.08 Do not measure weed prevention for payment.
Payment
171.09 Include all costs associated with the Section 171-Weed Prevention in the unit price for
Section 151-Mobilization.
303 - Road Reconditioning
303.00_0604_us_01_15_2010
Delete Section 303 in its entirety and replace with the following:
Description
303.01 This work consists of reconditioning ditches, shoulders, roadbeds, parking areas, turnouts, approach road intersections, cattleguards, asphalt and aggregate surfaces. Clean and maintain all drainage structures.
Material
303.02 Conform to the following subsection:
Water 725.01
Construction Requirements
303.03 Ditch Reconditioning. Remove all slide material, sediment, vegetation and other debris from the existing ditches and culvert inlets and outlets. Reshape ditches and culvert inlets and outlets to achieve positive drainage and a uniform ditch width, depth, and grade.
303.04 Shoulder Reconditioning. Remove all slide material, vegetation, and other debris from existing shoulders of roads, turnouts, and parking areas.
303.05 Roadbed Reconditioning. After pulverizing the designated road and parking lot area surfacing according to 303.08, mix, spread, and compact the materials. Maintain the existing cross slopes or crown on road or parking lot surfaces unless otherwise shown on the plans.
Establish a blading pattern that will retain the surfacing materials on the road or parking lot bed and provide a complete mixing of the materials. Adjust the moisture content to a level suitable for compaction. Operate rollers over the full width of each layer until visual displacement ceases, but not fewer than three complete passes. Use rollers that meet the following requirements:
(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than
250 pounds per inch of width of the compression roll or rolls.
(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum weight of 6 tons, specifically designed to compact the material on which it is used.
(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi.
303.07 Roadway Reconditioning. Perform all applicable work described in Subsections
303.03 through 303.05. Remove cattleguard decks and clean the decks and the area beneath the cattleguards of soil and other material to the bottom of the original foundation over the entire width of the installation. Reinstall the cattleguard deck to match elevation and slope of new compacted asphalt overlay and/or asphalt surface treatment.
303.08 Pulverizing. Scarify the existing asphalt surface materials and base aggregate to a depth of six inches in the designated areas. Pulverize the asphalt materials into fragments 2 ½ inches or smaller in size using sheep foot rollers, grid rollers, or other equipment that can successfully produce the desired size of materials. Nominal amounts of oversize can be disposed of on adjacent fill slopes or at the toe of the fills.
303.09 Acceptance. Road reconditioning work will be evaluated under Subsections 106.02 and
106.04.
Measurement
303.10 Measure the Section 303 items listed in Schedule of Items according to Subsection
109.02 and the following:
Measure ditch and shoulder reconditioning by the mile, horizontally along the centerline of the roadway for each side of the roadway.
Measure pulverizing and reconditioning of the roadbed, roadway, and parking lot by the square yard.
404 - Minor Hot Asphalt Concrete
404.02_nat_us_06_09_2006
404.02 Composition of Mix (Job-Mix Formula).
Delete the second paragraph and replace with the following:
Submit a job-mix formula and supporting documentation, test results, and calculations for the material to be incorporated into the work. Include copies of laboratory test results and mix design data that demonstrate that the properties of the aggregate, additives, and mixture meet the current requirements and criteria of Federal or state agencies. Ensure that the job-mix formula was performed no more than one year prior to placing the hot asphalt concrete. After reviewing the
Contractor’s proposed job-mix formula, the CO will determine the final values for the job-mix formula to be used and notify the Contractor in writing.
404.04_nat_us_03_02_2005
404.04 Weather Limitations.
Change 35 o F to 45 o F:
404.06_nat_us_03_02_2005
404.06 Placing.
Add the following:
Do not place asphalt until the CO has approved in writing the area where it will be placed.
Delete the last sentence and replace with the following:
Offset the longitudinal joint of one layer at least 6 inches from the joint in the layer immediately below. Make the longitudinal joint in the top layer along the centerline of two-lane roadways or at the lane lines of roadways with more than two lanes. Offset transverse joints in succeeding layers and in adjacent lanes at least 10 feet, where possible.
404.07_nat_us_03_02_2005
404.07 Compacting (a).
Delete and replace with the following:
(a) Roadway paving. Thoroughly and uniformly compact the surface a minimum of three passes with rollers that meet one of the following requirements:
(1) Steel-wheeled rollers, other than vibratory type, capable of exerting a force of not less than
1.5 ton/feet of width of the compression roll or rolls.
(2) Vibratory steel-wheel rollers with a minimum mass of 5 ton, equipped with amplitude and frequency controls, and designed to compact asphalt concrete.
(3) Pneumatic-tire rollers with smooth tread tires of equal size that provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 lbf/in
Perform initial compaction while the mixture is above 250 °F. Perform finish rolling with steel-wheel rollers and continue until no roller tracks remain.
404.09_nat_us_03_02_2005
404.09 Acceptance.
Add the following to the second paragraph:
See Table 404-1 for sampling and testing requirements.
Table 404-1. Delete and replace with the following:
Ta ble 404-1. Sampling and Testing Requirements.
Material or Product
Ty pe of
Acceptance (Subsection)
Characteristic Category Sampling
Methods Specifications
Sampling
Frequency
Point of
Sampling
Split
Sample
Reporting
Time
Asphalt
Mixture (404.09)
- - - AASHTO T
Three minimum per project and at least one per
500 Cubic yards
Roadway prior to compaction yes As soon as sampled
409 - Asphalt Surface Treatment
409.02_nat_us_05_12_2004
409.02 Material.
When designated, conform to applicable State department of transportation asphalt cement or emulsified asphalt requirements.
409.06_nat_us_05_12_2004
409.06 Weather.
Delete the first paragraph and replace with the following:
Apply surface treatments with aggregate only when ambient air and surface temperatures are above 60 °F and rising in the shade, when the weather is not foggy or rainy, and when rain is not forecast for at least 24 hours after application.
409.06 Date & Time.
Add the following.
Construct fog seal and single-course surface treatments between _____ (dates) and ______ and multiple-course surface treatments between ______ and ______. Dates to be determined at Post
Award Conference.
409.08_nat_us_06_21_2005
409.08 Asphalt Application.
Add the following to the 3rd paragraph:
Ensure the length of spread is no more than what can be covered with aggregate within 1 minute of the asphalt application.
409.10 Fog Seal.
Add the following to the first paragraph:
Dilute by adding an equal amount of water to the emulsified asphalt. Do not cut the emulsified asphalt more than once.
409.11_nat_us_12_18_2004
Table 409-2 Approximate Quantities of Material – Double Course Surface Treatments
Delete Tables 409-2 and substitute the following:
Table 409-2
Approximate Quantities of Material for
Double Course Surface Treatments
Designation
(Thickness)
Nominal
Maximum
Size of
Aggregate
Aggregate
Gradation (1)
Estimated
Quantity of
Aggregate (2) pounds/yd
Quantity of
Emulsified
Asphalt (3) gallons/yd
Quantity of Asphalt
Binder (3) gallons/yd
2A (1/2 inch) st Application 3/8 inch D 26 – 35 0.20 – 0.31 0.11 – 0.22 nd
Application No. 4 E 9 – 15 0.31 – 0.40 0.18 – 0.29
2B (5/8 inch) st Application 1/2 inch C 29 – 40 0.31 – 0.40 0.18 – 0.29 nd
Application No. 4 E 14 – 20 0.40 – 0.51 0.24 – 0.33
2C (3/4 inch) st Application 3/4 inch B 40 – 49 0.35 – 0.51 0.22 – 0.33 nd
Application 3/8 inch D 20 – 26 0.51 – 0.60 0.33 – 0.42
(1) See Table 703-7 for aggregate gradations.
(2) Aggregate masses are for aggregates having a bulk specific gravity of 2.65, as determined by
AASHTO T 84 and
T 85. Make proportionate corrections when the aggregate furnished has a bulk specific gravity above 2.75 or below 2.55.
(3) Adjust the asphalt content of the first application for the condition of the road.
(1) See Table 703-7 for aggregate gradations.
(2) Aggregate masses are for aggregates having a bulk specific gravity of 2.65 as determined by
AASHTO T 84 and T 85. Make proportionate corrections when the aggregate furnished has a bulk specific gravity above 2.75 or below 2.55.
(3) Adjust the asphalt content of the first application for the condition of the road.
409.13_nat_us_05_13_2004
409.13 Acceptance.
Delete the 2 nd paragraph and replace with the following:
Aggregate gradation for asphalt surface treatment will be evaluated under Subsection 106.04.
Table 409-4 Sampling and Testing Requirements .
Delete the last cell (4 th
) under Sampling Frequency and replace with the following:
1 per tanker truck and 1 per trailer
Delete the 2 nd and 3 rd cell under Type of Acceptance and replace with the following:
Measured and tested for conformance (106.04)
411 - Asphalt Prime Coat
411.06_nat_us_05_12_2004
411.06 Asphalt Applicatio n.
Add to the fifth paragraph:
If emulsified asphalt is used, use choker aggregate.
412 - Asphalt Tack Coat
412.07_nat_us_07_03_2007
Measurement
412.07 Acceptance
Delete the first paragraph and replace with the following:
Emulsified asphalt will be evaluated under Subsections 106.02, 106.03, and 702.07.
703 - Aggregate
703.05_nat_us_08_14_2009
Delete 703.05 and replace with the following:
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-2
(2) Liquid limit, AASHTO T 89 25 max.
(3) Plastic limit, AASHTO T 90 Nonplastic
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 50% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-3
(2) Liquid limit, AASHTO T 89 35 max.
(3) Plastic Index, AASHTO T 90
a) If the percent passing the No. 200 sieve is less than 12% 2 to 9
b) If the percent passing the No. 200 sieve is greater than 12% Less than 2
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 75% min.
(9) Free from organic matter and lumps or balls of clay
Do not furnish material that contains asbestos fibers.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:
(1) Gradation Table 703-16
(2) Plastic Index, AASHTO T 90 Less than 9
(3) Los Angeles abrasion, AASHTO T 96 55% max.
(4) Free from organic matter and lumps or balls of clay.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
Delete Table 703-2 and replace with the following :
T a b le
-2 rg e t
V a lu e R a n g e s fo r S u b b a se a n d
B a se G r a d a ti n
P e r ce n t b y
M a ss P a ss in g
D e si g n a te d S ie v e
A A
S H
T O
T a n d
T
G r a d in g D e si g n a ti
E
B a se
.0
.0
T h e v al u e in t h e p ar en th es es i s th e al lo w ab le d ev ia ti o n fr o m t h e ta rg et v al u es
D
B a
.0
.0
C
B a
.0
.0
B
S u b b a
.0
.0
A
S u b b a se
.0
.0
S ie v e S iz e
½ i ch i n c h
½ i n
/4 i n
/2 i n
/8 i n
N
Delete Table 703-3 and replace with the following:
b le
-3 rg e t
V a lu e R a n g e s fo r S u r fa c e G r a d a ti
P e r ce n t b y
M a ss P a ss in g
D e si g n a te d S ie v e
A A
S H
T O
T a n d
T
G r a d in g D e si g n a ti
U
.0
.0
T h e v al u e in t h e p ar en th es es i s th e al lo w ab le d ev ia ti o n fr o m t h e ta rg et v al u es
I f th e p la st ic it y i n d ex
P
I) i s g re at er t h a n th e
T V r an g e fo r th e
N o s ie v e si ze i s
-1
.0
.0
S
.0
.0
H
.0
.0
G
.0
.0
F
-1
-8
-6
-5
-3
-2
.0 -1
.0
S ie v e S iz e
/2 i n
/4 i n
/2 i n
/8 i n
Add Table 703-16:
Table 703-16
Gradation Requirements for Screened Aggregate
Sieve Size
Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)
Grading Designation
L M N O P Q R
6 inch 100 100
4 inch 100 100
3 inch 100 100
2 inch 100
No. 4 15-45 15-45 15-45
703.06_nat_us_03_02_2005
703.10(e) Flakiness Index.
Delete and replace with the following:
Flakiness Index, FLH T 508 30% max.
703.10(i) Adherent Coating.
Adherent coating on the aggregate, FLH T 512 0.5% max.
703.10_nat_us_03_02_2005
Delete Table 703-7 and substitute the following:
Table 703-7 Target Value Ranges
Table 703-7
Target Value Ranges for
Single and Multiple Course Surface Treatment Aggregate Gradation
Sieve
Percent by Mass Passing Designated Sieve
(AASHTO T 27 & T 11)
Size
Grading Designation
A B C D E F
1½ inch 100(1)
1 inch 90-100(3) 100(1)
¾ inch 0-35(5) 90-100(3) 100(1)
½ inch 0-8(3) 0-35(5) 90-100(3) 100(1)
⅜ inch — 0-12(3) 0-35(5) 85-100(3) 100(1) 100(1)
No. 4 — — 0-12(3) 0-35(5) 85-100(3) 85-100(1)
No. 8 — — — 0-8(3) 0-23(4) —
No. 200 0-1(1) 0-1(1) 0-1(1) 0-1(1) 0-1(1) 0-10(1)
(1) Statistical procedures do not apply.
( ) The value in the parentheses is the allowable deviation ( ) from the target values.
718 - Traffic Signing and Marking Material
718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.