Amended Section B Schedule of Items
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PreBidSiteVisitNotes_5.2.2017.pdf | ||
| SF30AmendmentMod2Pages.pdf | ||
| amended_DavisBacon_Wage_Determination.pdf | ||
| ModSeedSpec.pdf | ||
| AmendDrawing050817_(002).pdf | ||
| Specs_WFDistrReplace_010217.docx | DOCX document | |
| PlansVol1_010317.pdf | ||
| AG-0343-S-17-0032-RFP_West_Fork_Water_System_Replacement.doc | DOC document | |
| PlansVol2_010317.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-03R6-S-17-0032 amended schedule of Items
West Fork Water System Rehabilitation
PART 1 – THE SCHEDULE
SECTION B – SUPPLIES OR SERVICES AND PRICES
West Fork Water Distribution System Replacement
Ravalli County, Montana
B-1 Schedule of Items
Pay
Item
Description Meth of
Meas.
Unit
Estimated
Qty
Unit
Price
Total
PROPOSAL
01 Mobilization LSQ LS 1 $________ $________
02 Demolition LSQ LS 1 $________ $________
03 Clearing and Grubbing LSQ LS 1 $________ $________
4” C-900 PVC Water
Distribution Line
AQ LF 1,750 $________ $________
2” HDPE Water Distribution
Line
AQ LF 427 $________ $________
1-1/2” HDPE Water
Distribution Line
AQ LF 400 $________ $________
1” HDPE Water Distribution
Line
AQ LF 667 $________ $________
08 2" Curb Stop Valves AQ EA 3 $________ $________
09 1-1/2" Curb Stop Valves AQ EA 1 $________ $________
10 1" Curb Stop Valves AQ EA 6 $________ $________
11 4” Gate Valve AQ EA 1 $________ $________
12 Combination Air-Vac Valve AQ EA 1 $________ $________
AG-03R6-S-17-0032 amended schedule of Items
West Fork Water System Rehabilitation
13 Frost Free Hydrant AQ EA 2 $________ $________
14 Fire Fill Hydrant AQ EA 1 $________ $________
15 Pressure Reducing Valves AQ EA 3 $________ $________
Laundry House Mechanical
Modifications
LSQ LS 1 $________ $________
17 Erosion Control LSQ LS 1 $________ $________
18 Grading and Seeding LSQ LS 1 $________ $________
TOTAL PROPOSAL $________
* Designated Method of Measurement
DQ – Designed Quantities; AQ – Actual Quantities, LSQ – Lump Sum Quantities;
B-1 Notes
1. Bidder must bid on all items. Round to nearest cent.
2. In the event of an error in extending bid prices, unit prices will govern unless otherwise determined by the Contracting Officer in accordance with applicable regulations.
3. Offers for quantities less than those listed in the numbered items may be rejected.
4. Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-
Price Construction Contracts, shall not be in addition to the contract price. Include payment bond under Item 01 Mobilization.
5. The Government reserves the right to request additional information as required to fully understand the Contractor’s pricing structure and determine its reasonableness.
6. Contingency costs are not permissible in accordance with FAR 31.205-7. Unforeseen conditions are addressed under the following FAR clauses: 52.236-2 and 52.243-4 (see
Section I).