QUALITY ASSURANCE SURVEILLANCE PLAN.pdf
PDF 54 KB Posted
- Attached to
- Bitterroot National Forest Trail Packing Services Federal contract opportunity
- Solicitation number
- AG-03R6-S-12-0029
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| EXPERIENCE QUESTIONAIRE.pdf | ||
| WAGE DETERMINATION.pdf | ||
| Scheduled Packing Dates.pdf | ||
| Schedule of Items.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN
Packing Services
1. Purpose: This Quality Assurance Surveillance Plan (QASP) describes methods that will be used to monitor the Contractor’s performance. The QASP is not part of the Contract. It is provided to the
Contractor solely for informational purposes and is subject to change by the Government during the life of the contract. The Government reserves the right to perform assessments more or less often than outlined in this QASP.
2. Introduction: The QASP establishes methods to assess or evaluate performance of the Contractor under the contract. It is designed to provide an effective method of monitoring Contractor Performance for each objective on the Performance Requirements Summary (PRS) in the contract. The Government is concerned with the quality of the services provided, and not with the method that the Contractor uses to provide the services.
3. Responsibility for Quality Control: The Contractor is responsible for quality control and management actions to meet the performance requirements and terms of the Contract. The Government performs quality assurance to assess the quality of services rendered, and to verify the services meet the contract requirements, and contract standards are achieved. Quality Control for Commercial Items is in accordance with accepted industry practices.
4. Surveillance Methods: The Government will evaluate the Contractor’s performance under this contract.
Examples of Government surveillance may include:
a. Random review by the government of actual performance.
b. The government may respond with a review following trail crew and/or public complaints with verification by the CO or COR.
c.
5. Deduction Methods: The Government will record performance noting any substandard performance. For substandard performance, the Government’s preferred course of action will be discussions with the
Contractor to make the Contractor aware of the problem, and to effectively prevent any recurrence of substandard performance. The Government may also take the following actions:
a. Presentation of a Contract Discrepancy Report requiring a written explanation for substandard performance.
b. Payment deductions in accordance with the PRS;
c. Payment deductions in accordance with the applicable FAR clause(s).
d. Require correction or re-performance of the service.
QUALITY ASSURANCE SURVEILLANCE SUMMARY
Performance Objective Maximum
Allowable
Defect Rate
Surveillance Method AQL/Deductions
Overall Packing 3 defects per trip
COR Inspections
Customer Feedback
5% deduction from established monthly rate for the entire room or area being serviced when standards are not met.
Perform Work Within
Schedule Requirements
2 defects per trip
COR Inspections
Customer Feedback
2% deduction from established monthly rate for the entire room or area being serviced when standards are not met.
Maintain Safety of
Crew Public and
Animals
1 defects per trip
COR Inspections
Customer Feedback
2% deduction from established monthly rate for the entire room or area being serviced when standards are not met.
Deduction Threshold. If the number of defects, or instances of unacceptable performance, observed per trip is equal to or less than the maximum allowable defect rate (MADR), then there will be no deduction in payments to the Contractor for that task. However, if the number of defects observed per trip is greater than the MADR, then there will be a deduction in payments to the Contractor for that task.