Amendment_0001.pdf
PDF 176 KB Posted
- Attached to
- BITTERROOT NATIONAL FOREST - West Fork Water System Replacement Federal contract opportunity
- Solicitation number
- AG-0343-S-16-0071
About this file
Amendment 0001 - Questions/answers from 8/18/16 site visit and revision to specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sect3110000Rev082516.docx | DOCX document | |
| Davis_Bacon_Wage_Determinations_-_West_Fork_Well_Replacement.docx | DOCX document | |
| SupplySystem_Specs_WF_072916.docx | DOCX document | |
| SupplySystemDrawingsVol1Unsigned080216.pdf | ||
| SupplySystemDrawingsVol2Unsigned080216.pdf | ||
| AG-0343-S-16-0071_-RFP_West_Fork_Water_System_Replacement.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 1
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
1 8-25-2016
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
USDA, Forest Service Idaho-Montana Acquisition Team (IMAT) 3815 N. Schreiber Way Coeur d’Alene, ID 83815
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
AG-0343-S-16-0071
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copy to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
The purpose of this amendment is to do the following:
1) To provide detailed questions and answers and notes from 8/18/16 site visit as follows:
a) Question #1: Must a continuous water supply be maintained to the District? No. However, it should be address in the technical evaluation under technical approach how long the contractor plans on having no water supply to the District offices, bunkhouses, and residences. Section 011400 Work Restriction, 3.3 Scheduling, B. states, “Schedule and conduct operations to minimize down time of the water supply to facilities. Submit schedule to the Contracting Officer, outlining proposed construction sequence.”
b) Question #2: What type of fencing is expected for open trenches? Normal construction type fencing, orange plastic fencing, around open trenches is expected.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Estyn Kevitt
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Page 2 of 2 Pages
MODIFICATION OF CONTRACT - Attachment to SF-30
CONTRACTOR: PROJECT: Whitefish Mtn Road –Reestablish Native Surface
CONTRACT NO: AG-02RC-S-16-0011 UNIT: Flathead National Forest
List below (or on attached sheet if necessary) each proposed modification identified by item number, location of station, etc., giving the reasons for the modification
Amendment Language
Amount of Increase (+) Or Decrease(-)
c) Question #3: Is the electric meter to the pump house being replaced? Yes. See drawing sheet 15, E2.0, Note 8. Surface mount meter base and the fusible switch on the back of the building.
Coordinate with Ravalli County Electric Cooperative to install this 200 AMP 120/240 single phase service.
d) Question #4: Will excess material be hauled off site? A disposal site will be identified within 1 mile of the project for all excess natural material, common borrow, soil, rocks, root balls, and untreated lumber. See Section 01400 Work Restrictions, 3.7 Waste Disposal Site, A-C.
e) Question #5: Is there known bedrock? No test excavation has been performed to identify depths to bed rock, etc. Expect large boulders to be hit during trenching. There is visual evidence of a rock outcropping at the top of the steep grade near the old helipad site. This was identified during the pre-bid tour.
f) Question #6: Does the Forest know when the distribution part of the water system will be solicited?
The answer given at the pre-bid meeting was that we hoped it would be sometime in the next year.
Since the pre-bid meeting, funding has been identified in next year’s budget for the distribution side of the project. We hope to have another solicitation out shortly to address the distribution side of the system
g) Question #7: QA/QC plan. What does it look like? What are the qualifications? See section 014000 Quality Requirements and Section 014030 Contractor Quality Control. Section 014030 under 1.2 Submittals lists what is required to be in the plan. Specific qualifications are not listed. The Contractor should provide information regarding employee’s past experiences, training, or certifications that they feel qualify the individual to perform the QA/QC duties being tasked with.
h) Note #1: Clearing and Grubbing. It was discussed at the pre-bid meeting that the requirement to remove merchantable material may be removed through an amendment in the solicitation. The amendment would require merchantable material be limbed and decked at a designated location near the bottom of the steep grade heading up to the water storage tank. Disposal of root balls and over-sized material will be in a designated disposal site within 1 mile of the project.
i) Note #2: Erosion Control. The contractor will provide an erosion control plan per Section 015100 Erosion Control and on drawing. SD-6, Erosion Control Details. The erosion control requirements on the drawings are for those particular control devices. The FS is not requiring any specific method, however, the Contractor will have to provide a plan outlining the locations and devices they plan on using
j) Note #3: Surface Finishing of existing roads. The first road/driveway northwest of the pump house will be finished with 4” of ¾” gravel. If the Contractor excavates through the old asphalt helipad, it can be resurfaced with 4” of ¾” gravel. The road between the old helipad and the water tank is native surfaced
k) Note #4: The existing water tank is a considered a confined space when employees need to enter to conduct work. Contractor shall follow confined space requirements when working in this area. All OSHA requirements apply
2) To include updates to the specifications. Division 31 – Earthwork – Section 311000 is revised and the attachment will replace this section in the original specifications.
(+) $0.00
Contract Amount Prior to This Modification----------------> $0.00
New Contract Total--------------------> $0.00
Contract Time Days Increased Days Decreased New Total Contract Time
Signature Title Date
SUBMITTED
Contractor: Owner/President
Signature Title Date
RECOMMENDED
Contracting Officer's Representitive
Signature Title Funds Available Symbol Date
ACCEPTED Yes No
Contracting Officer