Addendum No. 2 Four Canyons Parkway Phase 2B IFB-5692-25-DD.pdf
PDF 564 KB Posted
- Attached to
- Four Canyons Parkway Phase 2B State and local contract opportunity
- Solicitation number
- IFB-5692-25-DD
- Issued by
- Mesa County, Colorado
About this file
Addendum No. 2 is issued by the City of Grand Junction Purchasing Division for the Four Canyons Parkway Phase 2B Project (IFB-5692-25-DD). The addendum provides clarifications and modifications to the original bid documents, specifically addressing questions about irrigation services, fiber optic installation, fence resetting, and sign relocations. Key changes include removing Bid Items #256 and #258 related to fiber optic cable, adjusting the quantity for Bid Item #145 regarding fence resetting, and clarifying the status of various signs and irrigation connections along 25 Road.
The addendum does not introduce significant pricing changes but provides technical clarifications that may impact bidding contractors' approaches and cost calculations. Notably, the document specifies that only conduit and boxes for fiber optic infrastructure will be installed, not the fiber optic cable itself. For the fence resetting at 623 25 Road, approximately 450 linear feet will be handled under a separate contract or change order. The addendum also addresses potential confusion about duplicate bid items and provides guidance on sign relocations, emphasizing the need for contractor coordination with property owners and the city.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Addendum No. 3 Four Canyons Parkway Phase 2B IFB-5692-25-DD.pdf | ||
| Solicitation Four Canyons Parkway Phase 2B IFB-5692-25-DD.pdf | ||
| Addendum No. 1 Four Canyons Parkway Phase 2B IFB-5692-25-DD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Purchasing Division
ADDENDUM NO. 2
DATE: June 24, 2025 FROM: City of Grand Junction Purchasing Division TO: All Offerors RE: Four Canyons Parkway Phase 2B IFB-5692-25-DD
This addendum shall be a part of the Contract Documents for the above project and is hereby made effective on the date shown above. All other terms and conditions of the contract documents not addressed in this addendum shall remain unchanged.
The bidder shall acknowledge receipt of this addendum in the space provided in the Bid Form. Failure to do so may subject the bidder to disqualification.
Please make note of the following questions/answers/clarifications:
1. Question: Will Insert-A-T fittings be allowed for the 4” irrigation services on the 18” ADS pipe instead of using a standard tee fitting and several reducers.
Answer: Insert-A-T fittings shall not be allowed for the 4” irrigation services. Standard tee fittings are acceptable.
2. Question: Several questions were received regarding fiber optic installation.
• Fiber Splicing
• Splice Cases
• Termination Panels
• Testing and Acceptance
• Material Ownership and Supply
• Fiber Slack Requirements
• Labeling and Documentation Answer: Phase 2B of the Four Canyons Parkway project does not propose the installation of Fiber Optic cable. Only conduit and boxes are proposed to be installed and are noted in the construction plans. Bid Items #256 & 258 have been removed from the Final Bid Schedule.
3. Question: I would like to request clarification regarding Bid Item 145, which lists 800 LF of Reset Fence. I’ve been unable to locate the corresponding locations on the plans. I’m assuming this work pertains to 25 Road, where existing fences may need to be relocated to the new property line. Could you please confirm if this is correct or provide additional details?
Additionally, regarding the chain link fence at 623 25 Road with the automatic gate opener, we would like to request that this be listed as a separate line item for clarity and accurate pricing.
Answer #3: Your assumption is correct that Bid Item #145 pertains to resetting existing fences for several properties along 25 Road, to the new adjusted property alignment. The quantity for fencing to be reset is approximate and could be adjusted depending on several factors of the existing fencing.
Fencing to be relocated for 623 25 Road, including the coordination for resetting the automatic gate opener shall be completed under separate contract, or change order. The existing fence for 623 25 Road accounts for approximately 450 LF. This amount shall be deducted from Bid Item #145 and will be reflected in the updated Final Bid Schedule.
4. Question: Looking at Bid Items 146 and 163, are these duplicates as that is the same address as the Gastroenterology building. Also, is the City aware that the bottom portion of the sign isn’t working properly now due to some electronic issues. Is the contractor going to need to repair that portion of the sign or are we going to reset as-is?
Answer: Bid Items 146 & 163 are not duplicate items. Item 146 is the small sign at the 25 Road driveway; Item 163 is the large electronic sign at the intersection. The Contractor must coordinate with the property owner and inform them of the sign’s non-functioning panel before relocation. The Contractor is only responsible for relocation, but coordination with the owner and City may be needed to determine if repair is required at that time.
ADDENDUM #2 CLARIFICATIONS:
1. Please see attached revised Final Bid Schedule, reflecting the clarifications to question #2, with the removal of Bid Items #256 & #258. A description of “N/A” now fills Bid Item #256 & #258.
2. Please see attached revised Final Bid Schedule, reflecting the quantity change for Bid Item #145. The 450 LF of existing fencing to be reset for 623 25 Rd shall be completed under separate permit or change order.
3. Please see attached revised Final Bid Schedule, reflecting the quantity change for Bid Item #310 & #311. The quantities for these Bid Items have been reverted to the quantities prior to Addendum #1
(17,173 LF).
4. The updated sheet E4 of the Electrical Plans included in Addendum #1, reflecting the quantity change to Bid Item(s) #310 & #311, is no longer valid. Sheet E4 of the Electrical Plans included in the original Bid Package is correct.
The original solicitation for the project noted above is amended as noted. All other conditions of the subject remain the same.
Respectfully, Dolly Daniels, Senior Buyer City of Grand Junction, Colorado
Item No.
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
1 108.2 6" Water Pipe (C-900 PVC) 800. LF $ ____________ $ ____________
2 108.2 8" Water Pipe (C-900 PVC) 1,500. LF $ ____________ $ ____________
3 108.2 12" Water Pipe (C-900 PVC) 3,110. LF $ ____________ $ ____________
4 108.3 2" Gate Valve 4. EA $ ____________ $ ____________
5 108.3 6" Gate Valve 11. EA $ ____________ $ ____________
6 108.3 8" Gate Valve 8. EA $ ____________ $ ____________
7 108.3 12" Gate Valve 6. EA $ ____________ $ ____________
8 108.3 6" x 2" Tee 1. EA $ ____________ $ ____________
9 108.3 6" x 6" Tee 2. EA $ ____________ $ ____________
10 108.3 8" x 2" Tee 1. EA $ ____________ $ ____________
11 108.3 8" x 6" Tee 5. EA $ ____________ $ ____________
12 108.3 8" x 8" Tee 2. EA $ ____________ $ ____________
13 108.3 12" x 6" Tee 6. EA $ ____________ $ ____________
14 108.3 12" x 8" Tee 3. EA $ ____________ $ ____________
15 108.3 12" x 12" Tee 1. EA $ ____________ $ ____________
16 108.3 6" 11 1/4 degree Elbow 1. EA $ ____________ $ ____________
17 108.3 6" 22 1/2 degree Elbow 5. EA $ ____________ $ ____________
18 108.3 6" 45 degree Elbow 2. EA $ ____________ $ ____________
19 108.3 8" 11 1/4 degree Elbow 6. EA $ ____________ $ ____________
20 108.3 8" 22 1/2 degree Elbow 20. EA $ ____________ $ ____________
21 108.3 8" 45 degree Elbow 13. EA $ ____________ $ ____________
22 108.3 8" x 12" Reducer 1. EA $ ____________ $ ____________
23 108.3 12" 11 1/4 degree Elbow 2. EA $ ____________ $ ____________
24 108.3 12" 22 1/2 degree Elbow 15. EA $ ____________ $ ____________
25 108.3 12" 45 degree Elbow 2. EA $ ____________ $ ____________
26 108.3 Fire Hydrant 8. EA $ ____________ $ ____________
27 108.4 6"x3/4" Tapping Saddle 1. EA $ ____________ $ ____________
28 108.4 8"x3/4" Tapping Saddle 4. EA $ ____________ $ ____________
29 108.4 12"x3/4" Tapping Saddle 10. EA $ ____________ $ ____________
30 108.4 12"x1" Tapping Saddle 1. EA $ ____________ $ ____________
31 108.4 12"x2" Tapping Saddle 2. EA $ ____________ $ ____________
32 108.4 3/4" Corporation Stop 15. EA $ ____________ $ ____________
33 108.4 1" Corporation Stop 1. EA $ ____________ $ ____________
34 108.4 2" Corporation Stop 2. EA $ ____________ $ ____________
35 108.4 Water Service Line (3/4") (Type K Copper) 430. LF $ ____________ $ ____________
36 108.4 Water Service Line (1") (Type K Copper) 30. LF $ ____________ $ ____________
37 108.4 Water Service Line (2") (Type K Copper) 135. LF $ ____________ $ ____________
38 108.4 3/4" Meter Setter (Install Only) (Ute Water to Provide)
10. EA $ ____________ $ ____________
Bid Schedule: FOUR CANYONS PKWY PH2B ADDENDUM No. 2 Contractor:________________________________________________________
BF-2 (1 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
39 108.4 1" Meter Setter (Install Only) (Ute Water to Provide)
1. EA $ ____________ $ ____________
40 108.4 2" Meter Setter (Install Only) (Ute Water to Provide)
1. EA $ ____________ $ ____________
41 108.4 Meter Pit (Install Only) (Ute Water to Provide) 12. EA $ ____________ $ ____________
42 104.4 Cap Top Half of Sewer in Concrete per City Standard Detail GU-04.
5. EA $ ____________ $ ____________
43 104.4 Fully Encase Sewer in Concrete per City Standard Detail GU-04.
5. EA $ ____________ $ ____________
44 108.2 Import Trench Backfill (Class 3) (Including haul and disposal of unsuitable excavated material) (Assumed Unit Weight = 133 lbs/cu.ft.)
1,235. TON $ ____________ $ ____________
45 108.7 Granular Stabilization Material (Type B) 740. TON $ ____________ $ ____________
46 108.2 Storm Drain Pipe - 30" Concrete Pipe 2,644. LF $ ____________ $ ____________
47 108.2 Storm Drain Pipe - 18" Concrete Pipe 2,160. LF $ ____________ $ ____________
48 108.2 Storm Drain Pipe - 12" Concrete Pipe 750. LF $ ____________ $ ____________
49 108.6 Storm Drain Manhole (90" ID) 1. EA $ ____________ $ ____________
50 108.6 Storm Drain Manhole (60" ID) 6. EA $ ____________ $ ____________
51 108.6 Storm Drain Manhole (48" ID) 7. EA $ ____________ $ ____________
52 108.6 WQ manhole. ADS stormwater treatment unit Barracuda S8 or engineer approved equal.
Includes 96" concrete manhole supplied by manufacturer and connection of adjacent storm sewer lines, forming inverts and adjusting to final grade. (Complete in Place).
1. EA $ ____________ $ ____________
53 108.6 WQ manhole. ADS stormwater treatment unit Barracuda S6 or engineer approved equal.
Includes 72" concrete manhole supplied by manufacturer and connection of adjacent storm sewer lines, forming inverts and adjusting to final grade. (Complete in Place).
1. EA $ ____________ $ ____________
54 108.6 WQ Manhole. ADS stormwater treatment unit Barracuda Max S3 or engineer approved equal. Includes 36" HP (36" ADS triple wall polypropylene barrel section) manhole with ductile iron flat top lid supplied by manufacturer and connection of adjacent storm sewer lines, forming inverts and adjusting to final grade.
Complete in Place).
1. EA $ ____________ $ ____________
55 108.6 Single Storm Drain Inlet with drive over curb opening (24" x 36")
3. EA $ ____________ $ ____________
56 108.6 Storm Drain Inlet with vertical curb opening (24" x 36")
25. EA $ ____________ $ ____________
57 108.6 Storm Drain - Large Area Inlet (24"x36") 1. EA $ ____________ $ ____________
BF-2 (2 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
58 108.5 Storm Drain - Manhole Barrel Section (D>5')(90" I.D.)
4.3 VLF $ ____________ $ ____________
59 108.5 Storm Drain - Manhole Barrel Section (D>5')(60" I.D.)
30. VLF $ ____________ $ ____________
60 108.5 Storm Drain - Manhole Barrel Section (D>5')(48" I.D.)
2. VLF $ ____________ $ ____________
61 108.5 Storm Drain - Inlet Box Section (D>5')(24"x36" I.D.)
5. VLF $ ____________ $ ____________
62 108.5 Connect to Existing Manhole or Pipe 1. EA $ ____________ $ ____________
63 108.2 Imported Trench Backfill (Class 3) (Including haul and disposal of unsuitable excavated material) (Assumed Unit Weight = 133 lbs/cu.ft.)(Storm Drain)
1,220. TON $ ____________ $ ____________
64 108.7 Granular Stabilization Material (Type B) (18" Thick Min.) (Includes haul and disposal of unsuitable excavated material) (Assumed Unit Weight = 138 lbs/cu.ft.)(Storm Drain)
950. TON $ ____________ $ ____________
65 108.3 2-way Sanitary Sewer Service Clean-Out (Std Detail SS-07) (For Rain Garden Underdrains)
6. EA $ ____________ $ ____________
66 108.2 4" Gravity Underdrain Pipe (Factory Slotted
SDR 17 PVC)
250. LF $ ____________ $ ____________
67 420 Geotextile Separator (CL 2) (Mirafi 180N or
EQ)
(For Rain Garden Underdrain)
300. SY $ ____________ $ ____________
68 420 Geotextile Separator (CL 2) (Mirafi 1100N or EQ) (For Rain Garden Underdrain)
155. SY $ ____________ $ ____________
69 304 Drain Gravel (For Rain Garden Underdrains) 41. TON $ ____________ $ ____________
70 304 Filter Sand (ASTM C-33)(For Rain Garden Underdrains)
70. TON $ ____________ $ ____________
71 LSC Bio-Retention Topsoil Media (12" Thick) (all designated areas within Rain Gardens, see Underdrain Plans & Landscape Detail Sheets for Bio-Retention Media Properties )
305. SY $ ____________ $ ____________
72 108.2 Irrigation Pipe - 8" SDR-35 PVC 70. LF $ ____________ $ ____________
73 108.2 Irrigation Pipe - 10" C-900 PVC 10. LF $ ____________ $ ____________
74 108.2 Irrigation Pipe - 12" SDR-35 PVC 22. LF $ ____________ $ ____________
75 108.2 Irrigation Pipe - 18" C-900 PVC 450. LF $ ____________ $ ____________
76 108.2 Irrigation Pipe - 12" Corrugated HDPE Pipe 60. LF $ ____________ $ ____________
77 108.2 Irrigation Pipe - 18" Corrugated HDPE Pipe 1,500. LF $ ____________ $ ____________
78 108.2 Irrigation Pipe - 24" Corrugated HDPE Pipe 10. LF $ ____________ $ ____________
79 108.5 Irrigation Connection (2494 Flat Top Ln) 1. EA $ ____________ $ ____________
80 108.5 Irrigation Connection (623 25 Rd) 1. EA $ ____________ $ ____________
81 108.5 Irrigation Connection (625 25 Rd) 1. EA $ ____________ $ ____________
BF-2 (3 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
82 108.5 Irrigation Connection (653 1/2 25 Rd) 1. EA $ ____________ $ ____________
83 108.5 Irrigation Connection (653 25 Rd) 1. EA $ ____________ $ ____________
84 108.5 Irrigation Connection (651 25 Rd) 1. EA $ ____________ $ ____________
85 108.5 Irrigation Connection (649 25 Rd) 1. EA $ ____________ $ ____________
86 108.5 Irrigation Manhole (36" I.D.) 9. EA $ ____________ $ ____________
87 108.5 Irrigation Manhole (48" I.D.) Structures (29),(28),&(27) per Details and Plan
3. EA $ ____________ $ ____________
88 108.5 Irrigation - Manhole Barrel Section (D>5')(36" I.D.)
21. VLF $ ____________ $ ____________
89 108.5 Irrigation - Manhole Barrel Section (D>5')(48" I.D.)
13. VLF $ ____________ $ ____________
90 108.2 Imported Trench Backfill (Class 3) (Including haul and disposal of unsuitable excavated material) (Assumed Unit Weight = 133 lbs/cu.ft.)(Irrigation)
700. TON $ ____________ $ ____________
91 108.7 Granular Stabilization Material (Type B) (18" Thick Min.) (Includes haul and disposal of unsuitable excavated material) (Assumed Unit Weight = 138 lbs/cu.ft.)(Irrigation)
365. TON $ ____________ $ ____________
92 202 Remove Asphalt Mat. Full Depth. 22,500. SY $ ____________ $ ____________
93 202 Remove Concrete 2,500. SY $ ____________ $ ____________
94 202 Abandon Pipe by Plugging End with Concrete 4. EA $ ____________ $ ____________
95 202 Remove Landscape Border 450. LF $ ____________ $ ____________
96 202 Remove Fire Hydrant and return to Ute Water 3. EA $ ____________ $ ____________
97 202 Remove Water Meter 8. EA $ ____________ $ ____________
98 202 Remove Water Valve 23. EA $ ____________ $ ____________
99 202 Remove Storm Drain Inlet 5. EA $ ____________ $ ____________
100 202 Remove Irrigation Manhole 6. EA $ ____________ $ ____________
101 202 Remove Storm Drain Manhole 10. EA $ ____________ $ ____________
102 202 Remove Light Pole 2. EA $ ____________ $ ____________
103 202 Remove Light Pole Base 2. EA $ ____________ $ ____________
104 202 Remove Post 7. EA $ ____________ $ ____________
105 202 Remove Delineator 13. EA $ ____________ $ ____________
106 202 Remove Ground Sign 27. EA $ ____________ $ ____________
107 202 Remove Sod. 5,056. SY $ ____________ $ ____________
108 202 Remove Tree 52. EA $ ____________ $ ____________
109 202 Remove Tree Stump 6. EA $ ____________ $ ____________
110 202 Remove Bush 56. EA $ ____________ $ ____________
111 202 Remove Property Pin (no reference or reset) 8. EA $ ____________ $ ____________
BF-2 (4 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
112 202 Remove Fence (includes all gates and associated appurtenances)
2,228. LF $ ____________ $ ____________
113 202 Remove Pipe as shown on Plans 4,500. LF $ ____________ $ ____________
114 202 Remove Mail Box 3. EA $ ____________ $ ____________
115 202 Remove Signal Pole Steel Template (base) and Return to City Traffic
1. EA $ ____________ $ ____________
116 202 Clearing and Grubbing 1. LS $ ____________ $ ____________
117 210 Adjust Sprinkler System (Heritage Estates HOA Detention Pond Area)
1. EA $ ____________ $ ____________
118 210 Adjust Sprinkler System (2508 Blichmann) 1. EA $ ____________ $ ____________
119 210 Adjust Sprinkler System (2501 Blichmann) 1. EA $ ____________ $ ____________
120 210 Adjust Sprinkler System (Heritage Heights HOA Tract on the West side of 25 Rd North of 625 25 Rd)
1. EA $ ____________ $ ____________
121 210 Adjust Sprinkler System (625 25 Rd) 1. EA $ ____________ $ ____________
122 210 Adjust Sprinkler System (623 25 Rd) 1. EA $ ____________ $ ____________
123 210 Adjust Sprinkler System (2502 Foresight) (includes old Foresight Cir Median)
1. EA $ ____________ $ ____________
124 210 Adjust Sprinkler System (2503 Foresight) 1. EA $ ____________ $ ____________
125 210 Adjust Sprinkler System (610 25 Rd) 1. EA $ ____________ $ ____________
126 210 Adjust Sprinkler System (604 25 Rd) 1. EA $ ____________ $ ____________
127 210 Adjust Sprinkler System (Copper Creek HOA at 25 Rd and Waite Ave)
1. EA $ ____________ $ ____________
128 210 Adjust Sprinkler System (Garrett Estates HOA Detention Pond Area at 25 Rd and F 1/2 Rd)
1. EA $ ____________ $ ____________
129 210 Adjust Sprinkler System (Herritage Estates HOA North Side of F 1/4 Rd West of 25 Rd)
1. EA $ ____________ $ ____________
130 210 Adjust Sprinkler System (2494 F 1/4 Rd) 1. EA $ ____________ $ ____________
131 210 Adjust Water Valve to Finished Grade 16. EA $ ____________ $ ____________
132 210 Adjust Water Meter to Finished Grade 5. EA $ ____________ $ ____________
133 210 Reset Water Meter 1. EA $ ____________ $ ____________
134 210 Reset Outet Structure for Heritage Estates Detention
1. EA $ ____________ $ ____________
135 210 Reset Outet Structure for Garrett Estates Detention
1. EA $ ____________ $ ____________
136 210 Adjust Manhole to Finished Grade 21. EA $ ____________ $ ____________
136A 210 Modify Manhole to Finished Grade 7. EA $ ____________ $ ____________
137 210 Reset Landscape Boulder 1. EA $ ____________ $ ____________
138 210 Trim Tree to clear walkway 6. EA $ ____________ $ ____________
139 210 Trim Bush to clear walkway 11. EA $ ____________ $ ____________
140 210 Reference/Reset Survey Monument 5. EA $ ____________ $ ____________
141 210 Reset Gate 2. EA $ ____________ $ ____________
142 210 Reset Mail Box (Coordinate with USPS) 7. EA $ ____________ $ ____________
BF-2 (5 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
143 210 Reset Landscape Border 40. LF $ ____________ $ ____________
144 210 Reset 2" PVC Irrigation Halls Estates Irrigation Tract adjacent to Hanna Ln
650. LF $ ____________ $ ____________
145 210 Reset Fence 350. LF $ ____________ $ ____________
146 210 Reset Commercial Sign for 604 25 Rd 1. EA $ ____________ $ ____________
147 210 Reset Landscape Ground Cover (Halls Est.
HOA adjacent to Hanna Ln N side Four Canyons Pkwy 24 1/2 to 24 3/4)
11,000. SF $ ____________ $ ____________
148 210 Reset Landscape Ground Cover (Heritage Heights HOA South side of Four Canyons Pkwy from 24 1/2 Rd to 24 3/4 Rd)
4,350. SF $ ____________ $ ____________
149 210 Reset Landscape Ground Cover (Heritage Heights HOA South side of Four Canyons Pkwy from 24 3/4 Rd to 25 Rd)
8,100. SF $ ____________ $ ____________
150 210 Reset Landscape Ground Cover (2501 Blichmann)
120. SF $ ____________ $ ____________
151 210 Reset Landscape Ground Cover (610 25 Rd) 130. SF $ ____________ $ ____________
152 210 Reset Landscape Ground Cover (604 25 Rd) 60. SF $ ____________ $ ____________
153 210 Reset Landscape Ground Cover (661 Garrett Way)
200. SF $ ____________ $ ____________
154 210 Reset Landscape Ground Cover (663 Garrett Way)
350. SF $ ____________ $ ____________
155 210 Reset Landscape Ground Cover (665 Garrett Way)
250. SF $ ____________ $ ____________
156 210 Reset Landscape Ground Cover (667 Garrett Way)
250. SF $ ____________ $ ____________
157 210 Reset Landscape Ground Cover (669 Garrett Way)
250. SF $ ____________ $ ____________
158 210 Reset Landscape Ground Cover (Garrett Way HOA on Garrett Way)
50. SF $ ____________ $ ____________
159 210 Reset Landscape Ground Cover (671 Garrett Way)
350. SF $ ____________ $ ____________
160 210 Reset Landscape Ground Cover (25 Rd and Waite Ave intersection - Copper Creek entrance - in ROW)
50. SF $ ____________ $ ____________
161 210 Reset Landscape Ground Cover (2494 F 1/4 Rd)
200. SF $ ____________ $ ____________
162 210 Cap Existing Sanitary Sewer with Cap 75. LF $ ____________ $ ____________
163 210 Reset Sign (Gastroenterology Associates on Patterson)
1. EA $ ____________ $ ____________
164 210 Reset Sign 3. EA $ ____________ $ ____________
165 PH POTHOLING 75. EA $ ____________ $ ____________
166 203 Unclassified Excavation 73,876. CY $ ____________ $ ____________
167 203 Unclassified Embankment 10,776. CY $ ____________ $ ____________
BF-2 (6 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
168 203 Haul Earthwork Material 61,600. CY $ ____________ $ ____________
169 207 Topsoil (12" Thick) (all planting areas within ROW) (Except areas designated without, see Landscape Plans)
3,000. SY $ ____________ $ ____________
170 203 (Roadway Subgrade Stabilization) Muck Excavation
10,000. CY $ ____________ $ ____________
171 304 (Roadway Subgrade Stabilization) Aggregate Base Course (Class 3) (24" Thick)
15,000. SY $ ____________ $ ____________
172 420 (Roadway Subgrade Stabilization) Geotextile Separator (Cl 2)
15,000. SY $ ____________ $ ____________
173 420 (Roadway Subgrade Stabilization) Geogrid Reinforcement
15,000. SY $ ____________ $ ____________
174 208 Storm Drain Inlet Protection (Erosion Log filter at Drop Inlet)
12. EA $ ____________ $ ____________
175 208 Storm Drain Inlet Protection (Type II) 35. EA $ ____________ $ ____________
176 208 Erosion Log 1,350. LF $ ____________ $ ____________
177 208 Prefabricated Vehicle Tracking Pad 5. EA $ ____________ $ ____________
178 208 Prefabricated Concrete Washout Structure 5. EA $ ____________ $ ____________
179 209 Dust Abatement 500. DAYS $ ____________ $ ____________
180 212 Seeding - Native Seed Mix 0.7 ACRE $ ____________ $ ____________
181 304 Aggregate Base Course (Class 2) (14" Thick) (Four Canyons Pkwy, 25 Rd from Blichmann to Patterson, F 1/2 Rd from 25 Rd to Crossing St)
40,500. SY $ ____________ $ ____________
182 304 Aggregate Base Course (Class 2) (10" Thick) (25 Rd from Four Canyons Pkwy to Waite Ave)
6,920. SY $ ____________ $ ____________
183 304 Aggregate Base Course (Class 2) (12" Thick) (25 Rd & Four Canyons Pkwy Intersection)
8,050. SY $ ____________ $ ____________
184 304 Aggregate Base Course (Class 2) (12" Thick) (24 3/4 Rd, 25 Rd Ct, Blichmann, F 1/4 Rd, and Foresight Cir)
10,100. SY $ ____________ $ ____________
185 304 Aggregate Base Course (Class 6) (12" Thick) (Driveway)
1,500. SY $ ____________ $ ____________
186 304 Aggregate Base Course (Class 6) (8" Thick) (Four Canyons Pkwy, 25 Rd from Blichmann to Patterson, and F 1/2 Rd from 25 Rd to Crossing St)
36,350. SY $ ____________ $ ____________
187 304 Aggregate Base Course (Class 6) (8" Thick) (25 Rd from Four Canyons Pkwy to Waite Ave)
6,250. SY $ ____________ $ ____________
188 304 Aggregate Base Course (Class 6) (8" Thick) (25 Road & Four Canyons Pkwy Intersection)
7,350. SY $ ____________ $ ____________
189 304 Aggregate Base Course (Class 6) (8" Thick) (24 3/4 Rd, 25 Rd Ct, Blichmann, F 1/4 Rd and Foresight Cir)
8,800. SY $ ____________ $ ____________
190 304 Aggregate Base Course (Class 6) (8" Thick) (Patterson Rt Turn)
500. SY $ ____________ $ ____________
BF-2 (7 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
191 304 Aggregate Base Course (Class 6) (8" Thick) (Road Shoulder)
225. SY $ ____________ $ ____________
192 304 Aggregate Base Course (Class 6) (4" Thick) (Gravel Driveways on Plan)
360. SY $ ____________ $ ____________
193 304 Washed Rock Surface Course (Driveways and on Properties as shown) (2" Thick)
1,750. SY $ ____________ $ ____________
194 306 Reconditioning (6" Deep) (Four Canyons Pkwy, 25 Rd from Blichmann to Patterson, and F 1/2 Rd from 25 Rd to Crossing St)
40,500. SY $ ____________ $ ____________
195 306 Reconditioning (6" Deep) (25 Road from Four Canyons Pkwy to Waite Ave)
6,920. SY $ ____________ $ ____________
196 306 Reconditioning (6" Deep) (25 Road & Four canyons Pkwy Intersection)
8,050. SY $ ____________ $ ____________
197 306 Reconditioning (6" Deep) (24 3/4 Rd, 25 Rd Ct, Blichmann, F 1/4 Rd and Foresight Cir)
10,100. SY $ ____________ $ ____________
198 306 Reconditioning (6" Deep) (Patterson Rt Turn) 500. SY $ ____________ $ ____________
199 306 Reconditioning (6" Deep) (Driveways) 1,500. SY $ ____________ $ ____________
200 329 Sod. (To repair & Match Existing) 53,000. SF $ ____________ $ ____________
201 401 Asphalt Millings (4" thick) (1 1/2" max particle size) (Temporary Drive Surfaces)
100. TON $ ____________ $ ____________
202 401 Hot Mix Asphalt (4" thick) (Grading SX 100, Binder Grade 64-22) (Driveway)
330. TON $ ____________ $ ____________
203 401 Hot Mix Asphalt (2" thick) (Grading SX 100, Binder Grade 64-28) (Four Canyons Pkwy, 25 Rd from Blichmann to Patterson, and F 1/2 Rd from 25 Rd to Waite Ave)
4,000. TON $ ____________ $ ____________
204 401 Hot Mix Asphalt (2" thick) (Grading SX 100, Binder Grade 64-28) (25 Road from Four Canyons Pkwy to Waite Ave)
700. TON $ ____________ $ ____________
205 401 Hot Mix Asphalt (2" thick) (Grading SX 100, Binder Grade 64-28) (25 Road & Four canyons Pkwy Intersection)
810. TON $ ____________ $ ____________
206 401 Hot Mix Asphalt (2" thick) (Grading SX 100, Binder Grade 64-28) (24 3/4 Rd, 25 Rd Ct, Blichmann Ave, F 1/4 Rd and Foresight Cir)
970. TON $ ____________ $ ____________
207 401 Hot Mix Asphalt (5 1/2" thick) (Grading SX 100, Binder Grade 64-22) (Four Canyons Pkwy, 25 Rd from Blichmann to Patterson, and F 1/2 Rd from 25 Rd to Crossing St)
11,000. TON $ ____________ $ ____________
208 401 Hot Mix Asphalt (5" thick) (Grading SX 100, Binder Grade 64-22) (25 Road from Four Canyons Pkwy to Waite Ave)
1,720. TON $ ____________ $ ____________
209 401 Hot Mix Asphalt (7" thick) (Grading SX 100, Binder Grade 64-22) (25 Road & Four canyons Pkwy Intersection)
2,850. TON $ ____________ $ ____________
BF-2 (8 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
210 401 Hot Mix Asphalt (4" thick) (Grading SX 75, Binder Grade 64-22) (24 3/4 Rd, 25 Rd Ct, Blichmann Ave, F 1/4 Rd and Foresight Cir)
1,940. TON $ ____________ $ ____________
211 401 Hot Mix Asphalt (2" thick) (Grading SX 75, Binder Grade 64-22) (T-Top on plan)
40. TON $ ____________ $ ____________
212 504 Precast Concrete Block Retaining Wall System (includes all necessary appurtenances, work, etc. to complete).
600. FSF $ ____________ $ ____________
213 504 Retaining Wall System (Keystone Legacy Stone or Engineer Approved Equal) (For Rain Gardens and adjacent to Landscaping at the Slate on 25 Apts.)
1,340. FSF $ ____________ $ ____________
214 608 Concrete Landscape Border (match existing in kind)
100. LF $ ____________ $ ____________
215 608 Concrete Pavement (Patterson Rt Turn Ln) (9" Thick) (CL-P)
500. SY $ ____________ $ ____________
216 608 Concrete Curb and Spill Gutter (1.5' Wide) (both Spill and Collector Gutter) to include Class 6 Aggregate Base Course per Typical Cross Section
9,070. LF $ ____________ $ ____________
217 608 Concrete Curb (6" Wide) (6" High) to include Class 6 Aggregate Base Course per Typical Cross Section
700. LF $ ____________ $ ____________
218 608 Concrete Curb and Gutter (2' Wide) (both collector and spill gutters) to include Class 6 Aggregate Base Course per Typical Cross Section
14,620. LF $ ____________ $ ____________
219 608 Concrete Drive Over Curb and Gutter 3' wide and both collector and spill gutter to include Class 6 Aggregate Base Course per Typical Cross Section
1,420. LF $ ____________ $ ____________
220 608 Concrete Sidewalk (6" Thick) to include 6" of Class 6 Aggregate Base Course.
12,250. SY $ ____________ $ ____________
221 608 Concrete Drainage Pan (2' Wide) to include 6" of Class 6 Aggregate Base Course.
300. LF $ ____________ $ ____________
222 608 Concrete Drainage Pan (3' Wide) to include 6" of Class 6 Aggregate Base Course.
260. LF $ ____________ $ ____________
223 608 Concrete Drainage Pan (6' Wide) to include 6" of Class 6 Aggregate Base Course.
110. LF $ ____________ $ ____________
224 608 Concrete Intersection Corner (8" thick) to include 6" of Class 6 Aggregate Base Course.
240. SY $ ____________ $ ____________
225 608 Concrete Median Island Nose (8" Thick) to include 6" of Class 6 Aggregate Base Course.
70. SY $ ____________ $ ____________
226 608 Concrete Curb Ramp to include 6" of Class 6 Aggregate Base Course.
400. SY $ ____________ $ ____________
227 608 Concrete Pavement (6" Thick) to include 6" of Class 6 Aggregate Base Course.
85. SY $ ____________ $ ____________
BF-2 (9 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
228 608 Concrete Driveway Section (8" Thick) (Commercial) to include 6" of Class 6 Aggregate Base Course.
810. SY $ ____________ $ ____________
229 608 Concrete Median Edging (1.5' Wide) (4" thick) (make sure not repeated landscape quantities)
6,205. LF $ ____________ $ ____________
230 608 Concrete Median Cover Material (6" Patterned Concrete) to include 6" of Class 6 Aggregate Base Course. (make sure not repeated landscape quantities)
460. SY $ ____________ $ ____________
231 608 Detectable Warning (Cast Iron, Wet Set) (2'x2) 145. EA $ ____________ $ ____________
232 614 Sign Panel (CL I) 704. SF $ ____________ $ ____________
233 614 Sign Panel (CL II) 12. SF $ ____________ $ ____________
234 614 3 LB. U SHAPE CHANNEL STEEL POST 88. EA $ ____________ $ ____________
235 614 Steel Sign Support (2 1/2" round NP-40) (Pole/Slipbase)
1. EA $ ____________ $ ____________
236 614 Safe Hit Flexible Delineator SH248GP3-WS 09 to include sleeve or Engineer Approved Equal
10. EA $ ____________ $ ____________
237 202 Remove Existing Signal (Includes pole, mast arm, foundation, associated pull box, and telemetry per plan)
1. EA $ ____________ $ ____________
238 503- 00036
Drilled Caisson (36 Inch) 44. LF $ ____________ $ ____________
239 503- 00042
Drilled Caisson (42 Inch) 34. LF $ ____________ $ ____________
240 613- 07005
Type Five Pull Box (Traffic) (30x48x24) 5. EA $ ____________ $ ____________
241 614- 70150
Pedestrian Signal Face (16) (Countdown) 6. EA $ ____________ $ ____________
242 614- 70336
Traffic Signal Face (12-12-12) (With Backplate) (Patterson)
2. EA $ ____________ $ ____________
243 614- 70336b
Traffic Signal Face (12-12-12) (With Backplate and Retroflective Border) ("T"shape for
HAWKS)
8. EA $ ____________ $ ____________
244 Traffic Signal Face (12-12-12-12-12) (With Backplate) (Patterson)
3. EA $ ____________ $ ____________
245 614- 72855
Traffic Signal Controller Cabinet 2. EA $ ____________ $ ____________
246 614- 72863
Pedestrian Push Button Post Assembly 8. EA $ ____________ $ ____________
247 614- 72886
Intersection Detection System (Camera) 1. EA $ ____________ $ ____________
248 614- 72886
Intersection Detection System (Camera with Radar)
4. EA $ ____________ $ ____________
BF-2 (10 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
249 614- 72886o
Intersection Detection System (Opticom) 1. EA $ ____________ $ ____________
250 614- 81140
Traffic Signal-Light Pole Steel (1-40 Foot Mast Arm)
3. EA $ ____________ $ ____________
251 614- 81150
Traffic Signal-Light Pole Steel (1-50 Foot Mast Arm)
2. EA $ ____________ $ ____________
252 614 Mount City Provided Sign on Mast Arm 1. EA $ ____________ $ ____________
253 614 Sign Panel (CL I)(See Signal Plans) 135. SF $ ____________ $ ____________
254 614 Sign Panel (CL II)(at HAWK Signal Poles, see Signal Plans)
48. SF $ ____________ $ ____________
256 N/A
257 614- 87320
Closed Circuit Television (patterson) 1. EA $ ____________ $ ____________
258 N/A
259 614 2" PVC Conduit 800. LF $ ____________ $ ____________
260 614 White Delineator (Break away reflector) 180. EA $ ____________ $ ____________
261 627 High Build Acrylic Waterborne Paint Pavement Marking (White)(2 Coats)
200. Gal $ ____________ $ ____________
262 627 High Build Acrylic Waterborne Paint Pavement Marking (Yellow)(2 Coats)
105. Gal $ ____________ $ ____________
263 627 Preformed Thermoplastic Pavement Marking (Word / Symbol) (Asphalt only)
1,332. SF $ ____________ $ ____________
264 627 Preformed Thermoplastic Pavement Marking (X-Walk & Stop Line) (Asphalt only)
3,262. SF $ ____________ $ ____________
265 627 4" Preformed Thermoplastic Pavement Marking (White) (Cross Hatch inside bike buffer) (125 Mil)
655. SF $ ____________ $ ____________
266 627 Preformed Thermoplastic Pavement Marking (Green Bikeway Ladder)
1,224. SF $ ____________ $ ____________
267 627 Preformed Thermoplastic Pavement Marking (4" White stripe on outside of Green Bikeway Ladder)
210. SF $ ____________ $ ____________
268 627 Preformed Thermoplastic Markings - Bike Rider w/ Helmet (Left) (White bike on green background)(6'6"x3'4" (90 Mil)
50. EA $ ____________ $ ____________
BF-2 (11 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
269 627 Preformed Thermoplastic Pavement Marking (Word / Symbol) (Concrete)(Inlaid)(includes balck contrast tape, 1.5" each side, total of 3") (Patterson Rt. Turn)
50. SF $ ____________ $ ____________
270 627 Preformed Thermoplastic Pavement Marking (X-Walk & Stop Line) (Concrete only, Inlaid)(includes balck contrast tape, 1.5" each side, total of 3") (Patterson Rt. Turn)
80. SF $ ____________ $ ____________
271 LSC Soil Amendment (To be tilled) 82,985. SF $ ____________ $ ____________
272 LSC 1-1/2" Tan Granite (3" Depth) 78,542. SF $ ____________ $ ____________
273 LSC 1-1/2" Tan Granite (3" Depth), Plus 2-3" La Sal Purple Granite (scattered at 1 CF/100 SF)
42,147. SF $ ____________ $ ____________
274 LSC 2-3" La Sal Purple Granite (3" Depth) 4,443. SF $ ____________ $ ____________
275 LSC Landscape Boulder - Small (2'x2'x3') 463. EACH $ ____________ $ ____________
276 LSC Landscape Boulder - Large (3'x3'x4') 54. EACH $ ____________ $ ____________
277 LSC Deciduous Tree ( 1-1/2 Inch Caliper) 66. EACH $ ____________ $ ____________
278 LSC Deciduous Tree ( 2 Inch Caliper) 42. EACH $ ____________ $ ____________
279 LSC Deciduous Shrub (5 Gallon Container) 591. EACH $ ____________ $ ____________
280 LSC Evergreen Tree (6 Foot, B&B) 15. EACH $ ____________ $ ____________
281 LSC Evergreen Shrubs (5 Gallon Container) 120. EACH $ ____________ $ ____________
282 LSC Perennials (1 Gallon Container) 354. EACH $ ____________ $ ____________
283 LSC Ornamental Grasses (1 Gallon Container) 351. EACH $ ____________ $ ____________
284 IRR Irrigation Connection to Four Canyons Pkwy
PH1
1. EACH $ ____________ $ ____________
285 IRR 4 Inch PVC Irrigation Sleeve, 18" bury under sidewalks
100. LF $ ____________ $ ____________
286 IRR 4 Inch PVC Irrigation Sleeve, 30" bury under roadways
730. LF $ ____________ $ ____________
287 IRR 6 Inch PVC Irrigation Sleeve, 18" bury under sidewalks
100. LF $ ____________ $ ____________
288 IRR 6 Inch PVC Irrigation Sleeve, 30" bury under roadways
940. LF $ ____________ $ ____________
289 IRR 4" HDPE Mainline 7,086. LF $ ____________ $ ____________
290 IRR 1 Inch PVC CL 160 Lateral Pipe 15,996. LF $ ____________ $ ____________
291 IRR 1-1/2 Inch PVC CL 160 Lateral Pipe 400. LF $ ____________ $ ____________
292 IRR Tracer Wire for all Mainline and PVC Lateral Pipes
23,482. LF $ ____________ $ ____________
293 IRR 3/4 Inch Quick Coupler Valve 5. EACH $ ____________ $ ____________
294 IRR 1 Inch Automatic PES-B Scrubber Valves 6. EACH $ ____________ $ ____________
295 IRR 1.5 Inch Automatic PES-B Scrubber Valves 4. EACH $ ____________ $ ____________
296 IRR 2-wire Control Wire 4. LF $ ____________ $ ____________
297 IRR 2-wire Control, including decoders, grounding Lump SUM - - - $ ____________
298 IRR Isolations Valves - For Mainline 5. EACH $ ____________ $ ____________
BF-2 (12 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
299 IRR Isolations Valves - For Rain Garden Lateral Shutoff
5. EACH $ ____________ $ ____________
300 IRR Manual Drain Valves 1. EACH $ ____________ $ ____________
301 IRR Risers with Compression Tee transition to Tubing
191. EACH $ ____________ $ ____________
302 IRR 1/2" Drip Tubing (No Emitters and Not including Tree Ring Assemblies)
10,760. LF $ ____________ $ ____________
303 IRR Netafim Drip Emitters (incl. 1/4" Distribution Tubing)
3,543. EACH $ ____________ $ ____________
304 IRR Tree Ring Assembly 123. EACH $ ____________ $ ____________
305 IRR Flush Caps in 6" Round Box 77. EACH $ ____________ $ ____________
306 IRR Air Relief/Pressure Relief Assembly 1. EACH $ ____________ $ ____________
307 613 2" Schedule 80 PVC (for Franchise Utility crossing) (varies)
2,200. LF $ ____________ $ ____________
308 613 4" Schedule 80 PVC (for Franchise Utility crossing) (varies)
2,200. LF $ ____________ $ ____________
309 613 Large Splice Box (Quasite) (3' - 2 5/8" x 2'-2") Broadband Logo.
25. EACH $ ____________ $ ____________
310 613 2" Schedule 80 PVC (City Broadband Conduit) 17,173. LF $ ____________ $ ____________
311 613 2" Schedule 80 PVC (City Electrical Conduit) 17,173. LF $ ____________ $ ____________
312 ELEC Type two Pull Box 154. EACH $ ____________ $ ____________
313 ELEC Wiring Lump SUM - - - $ ____________
314 ELEC Light Standard and Luminaire (Pedestrian) 138. EACH $ ____________ $ ____________
315 ELEC Light Standard Foundation (Pedestrian) 138. EACH $ ____________ $ ____________
316 ELEC Lighting Control Center PWR Pedestal (Special) (LCBP x1.74)
3. EACH $ ____________ $ ____________
317 ELEC Trench - Site Lighting and Electrical/Fiber Lump SUM - - - $ ____________
318 620 Sanitary Facility 1. EACH $ ____________ $ ____________
319 625 Construction Surveying Lump SUM - - - $ ____________
320 626 Mobilization Lump SUM - - - $ ____________
321 630 Traffic Control (Complete In Place) Lump SUM - - - $ ____________
322 630 Traffic Control Plan Lump SUM - - - $ ____________
323 630 Construction Phasing Plan Lump SUM - - - $ ____________
324 630 Temporary Paving 2,000. SY $ ____________ $ ____________
325 FO Field Office, Class 1 1. EACH $ ____________ $ ____________
BF-2 (13 of 14)
CDOT,
City Ref. Description Quantity Units Unit Price Total Price
Bid Schedule: FOUR CANYONS PKWY PH2B Contractor:________________________________________________________
F/A 700- 70019
Asphalt Cement Cost Adjustment - - - - - - - - - 400,000.00$
MCR Minor Contract Revisions - - - - - - - - - 800,000.00$
Bid Amount: $
Bid Amount:
dollars
Contractor Name:
Contractor Address:
Contractor Phone #:
BF-2 (14 of 14)