This is Addendum 02 and the associated Bid Proposal Form for a chiller replacement project issued by the Lansing School District in Michigan, with engineering services provided by Matrix Consulting Engineers. The project involves the replacement of the chilled water system at Gardner Elementary School in Lansing, Michigan. A pre-bid conference was held with an attendance sign-in sheet provided in the addendum. Proposals are due no later than 2:00 PM on June 4, 2026, and should be submitted to the Lansing School District Purchasing Department at 519 W Kalamazoo Street, Lansing, Michigan 48933. Work is to commence within ten consecutive calendar days after notice of contract award, with substantial completion required by January 1, 2027. Bidders must acknowledge receipt of all addenda on the proposal form and submit one original and two copies in a sealed envelope clearly marked as SO-1858 Gardner Elementary Chiller Replacement.
The base bid cost breakdown requires contractors to provide separate line-item pricing for general trades, mechanical, electrical, and controls work. An allowance of $80,000 is included for use according to Owner's written instructions, which covers material costs, receiving, handling, installation, and contractor overhead and profit. Contractors must also specify fees for handling additional work performed by subcontractors and for additional work performed by other entities. The project is not subject to prevailing wage requirements. Key clarifications addressed in the addendum include confirmation that exterior piping shall be insulated and jacketed rather than painted, condenser water piping uses water rather than propylene glycol, and only the bid sheet and bid bond are due with the initial proposal, with supplier and vendor application forms to be submitted later as startup submittals if the bid is awarded.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| SO-1858 Gardner School Chiller Replacement Addendum 1.pdf | ||
| SO-1858 Gardner School Chiller Replacement.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
544 Cherbourg Drive, LANSING, MI 48917
PHONE: (517) 487-2511
FAX: (517) 487-2544
ADDENDUM NO. 2
LSD Gardner Elementary Chiller Replacement
Date:05/29/2026 Job Number: 260150.00
OWNER: ENGINEER:
Lansing School District Matrix Consulting Engineers 333 Dahlia Dr 544 Cherbourg Drive Lansing, MI 48911 Lansing, MI 48917
This Addendum is issued for the purpose of modifying and/or clarifying the original Contract Documents and shall take precedence over them.
All work included herein shall be in accordance with the original drawings and specifications except as specifically noted herein. All incidental items required to provide the following modifications shall be included even though not specifically described.
This addendum is being sent to all bidders receiving plans and specifications. Receipt of this Addendum shall be noted on the Proposal Form in the appropriate location.
Pre-Bid Conference
1. Sign-In Sheet (Issued):
a. See attached sign-in sheet from the Pre-Bid Conference.
Specifications
1. Section 004100 – Bid Proposal Form (Re-issued):
a. See revised date of substantial completion.
2. Section 012100 – Allowance (Re-issued):
a. See revised allowance value.
Clarifications
1. The asbestos report for Gardner Elementary School can be requested through the school district.
2. The project is not subject to prevailing wage requirements.
3. The chilled water system is independent of the hot water hydronic system.
ADDENDUM NO. 2
Request for Information (RFI) Responses:
1. Is the exterior piping to be painted?
a. No. Exterior piping shall be insulated and jacketed in accordance with the spec.
2. Is the allowance 10% or flat?
a. The allowance will be revised to a dollar amount allowance.
3. Is the condenser water piping 30% PG or water?
a. Water.
4. Are the supplier/vendor application forms to be completed and turned in with the bid proposal or as a start-up submittal?
a. Only the bid sheet and bid bond are due for the bid.
5. Please clarify if there is a roof warranty.
a. There is no roof warranty.
6. The front end documents claim this is a prevailing wage project; however, in the pre-bid meeting this was mentioned that it was not the case. Please clarify.
a. The project is not subject to prevailing wage requirements.
END OF ADDENDUM
544 Cherbourg Dr, LANSING, MI 48917
PHONE: (517) 487-2511
Bid Proposal Form
Lansing School District Gardner Elementary School
Chilled Replacement Lansing, MI
LSD Project #SO-1858 Project #260150.00
Proposals are due no later than 2:00 PM on June 4, 2026.
Bids received after this date and time will not be accepted or considered.
Please mail or drop off your proposal to: Lansing School District, Attn: Purchasing Dept, 519 W Kalamazoo St, Lansing, MI 48933. All proposals should include one original and two copies in a sealed envelope and clearly marked as SO-1858 Gardner Elementary Chiller Replacement.
Name of Bidder:
Address:
Phone No.: E-mail:
Date:
BASE PROPOSAL
We the undersigned, propose to furnish all labor, materials, and facilities for the completion of the General Construction Contract (including Site, Architectural, Structural, Mechanical and Electrical Work), for the above named project in accordance with drawings and specifications prepared by Matrix Consulting Engineers Inc., dated May 18, 2026 and all addenda (if applicable), for the sum of:
dollars
($ ) and hereby agree to enter into a contract for the work if this proposal is accepted in writing.
Bid Proposal Form
2 o f 4
ADDENDA
We acknowledge the receipt of the following addenda to drawings and specifications:
Addendum No.______________________ Initial_______ Date__________________ Addendum No.______________________ Initial_______ Date__________________ Addendum No.______________________ Initial_______ Date__________________
TIME OF COMPLETION
Work is to commence within ten (10) consecutive calendar days after notice of Award of Contract. The work shall be substantially complete on or before January 1, 2027.
BASE BID COST BREAKDOWN
Provide a cost breakdown for each of the subcontractor proposals being provided in the base bid.
Trade Contractor Providing Proposal Cost General Trades ______________________________ $_______________ Mechanical ______________________________ $_______________ Electrical ______________________________ $_______________ Controls ______________________________ $_______________
FEE FOR HANDLING ADDITIONAL WORK
For handling additional work performed upon instructions of the Owner by subcontractors of the undersigned, add to the subcontractor’s prices for the additional work a fee of _____%, which shall include all of the undersigned’s charges.
For additional work performed upon instructions of the Owner other than that of subcontractors of the undersigned, add to the actual cost of all labor and materials, including insurance and taxes (less all discounts) a fee of _____%, which shall include all charges for overhead and profit.
3 o f 4
VOLUNTARY SUBSTITUTIONS
If awarded a contract for the work bid upon above, on the basis of the amount of our proposal, we agree to furnish materials and equipment specifically mentioned in the specifications.
If any of the following voluntary substitutions for materials or equipment are approved, we further agree to make the corresponding deduction from our proposal.
Name of Manufacturer Amount of Deduction
PERSONNEL ASSIGNMENT FOR THIS PROJECT:
Project Superintendent:
Project Engineer:
SUBCONTRACTOR ASSIGNMENT FOR THIS PROJECT:
General Trades:
Mechanical:
Electrical:
Controls:
4 o f 4
SIGNATURES
When the bidder is an individual:
Bidder Witness
When the bidder is a partnership:
Bidder Bidder Bidder Bidder
Witness
When the bidder is a corporation:
President Secretary
______________________________________ is a corporation organized and existing under the laws of ______________________ and has (has not) been granted a certificate of authority to do business in the State of _____________________.
Lansing School District Project No. 260150.00 Gardner Elementary School Chiller Replacement May 2026 LSD Project No. SO-1858 Bid Documents
ALLOWANCES 012100 - 1
SECTION 012100 - ALLOWANCES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
B. Types of allowances include the following:
1. General Allowance.
1.3 DEFINITIONS
A. Allowance: A quantity of work or dollar amount included in the Contract, established in lieu of additional requirements, used to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order.
1.4 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection, or purchase and delivery, of each product or system described by an allowance must be completed by the Owner to avoid delaying the Work.
B. At Architect's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work.
C. Purchase products and systems selected by Architect from the designated supplier.
1.5 ACTION SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances in the form specified for Change Orders.
LSD Project No. SO-1858 Bid Documents
ALLOWANCES 012100 - 2
1.6 INFORMATIONAL SUBMITTALS
A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.
C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.7 ALLOWANCES
A. Use the allowance only as directed by Architect for Owner's purposes and only by Change Orders that indicate amounts to be charged to the allowance.
B. Contractor's overhead, profit, and related costs for products and equipment ordered by Owner under the allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, taxes, insurance, equipment rental, and similar costs.
C. Change Orders authorizing use of funds from the allowance will include Contractor's related costs and reasonable overhead and profit.
D. At Project closeout, credit unused amounts remaining in the allowance to Owner by Change Order.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCES
A. Allowance No. 1: General Allowance: Include an allowance of $80,000 for use according to Owner's written instructions.
LSD Project No. SO-1858 Bid Documents
ALLOWANCES 012100 - 3
1. This allowance includes material cost; receiving, handling, and installation; and Contractor overhead and profit.
END OF SECTION 012100