A06-Specifications_Package_-_Hagerman_NWR_HVAC_Replacement.pdf

PDF 577 KB Posted

Attached to
TX-HAGERMAN NWR-HVAC REPLACEMENT Federal contract opportunity
Solicitation number
140FC124R0036
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This federal solicitation requests proposals for a Variable Refrigerant Flow heat recovery system project at the Hagerman National Wildlife Refuge Headquarters and Visitor Center. The project requires removal and replacement of the existing Daikin VRF system in accordance with the Statement of Work, drawings, and specifications. The magnitude of the project is estimated between $200,000 and $250,000. This is a 100% Total Small Business Set-Aside solicitation under NAICS code 238220 with a size standard of $19 million. Proposals are due by March 22, 2022 and the acceptance period is 60 days. The award will be made using Lowest Price Technically Acceptable based on price and technical acceptability. Interested parties should contact the points of contact for site visit arrangements and to submit any request for information in writing by email.

View the file

Other files for this federal contract opportunity

Other files attached to TX-HAGERMAN NWR-HVAC REPLACEMENT, newest first.
File Type Posted
Sol_140FC124R0036_Amd_0001.pdf PDF
A04-SOW_-_Hagerman_NWR_HVAC_Replacement_0001.pdf PDF
Sol_140FC124R0036.pdf PDF
B08_Construction_Over_SAT_FFP_2_14_24.pdf PDF
A06-Mechanical_Drawings_-_Hagerman_NWR_HVAC_Replacement.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications Package Hagerman NWR HQ/VC VRF Replacement

Section 01 33 00 Page 1 of 3

SECTION 01 32 16

SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Baseline Construction Schedule; G

SD-07 Certificates

Monthly Updates

1.2 PRE-CONSTRUCTION SCHEDULE REQUIREMENT

Within 20 calendar days after contract award and prior to the start of work, prepare and submit to the Contracting Officer a Baseline Construction Schedule in the form of a Bar Chart Schedule in accordance with the terms in Contract Clause FAR 52.236-15 Schedules for Construction Contracts, except as modified in this contract. The approval of a Baseline Construction Schedule is a condition precedent to:

a. The Contractor starting demolition work or construction stage(s) of the contract.

b. Processing Contractor's invoice(s) for construction activities/items of work.

c. Review of any schedule updates.

Submittal of the Baseline Construction Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).

1.3 SCHEDULE FORMAT

1.3.1 Bar Chart Schedule

The Bar Chart must, as a minimum, show work activities, submittals, Government review periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. The Bar Chart must be time scaled and generated using an electronic spreadsheet program.

Section 01 33 00 Page 2 of 3

1.3.2 Schedule Submittals and Procedures

Submit Schedules and updates via electronic media that is acceptable to the Contracting Officer.

1.4 SCHEDULE MONTHLY UPDATES

Update the Construction Schedule at monthly intervals or when the schedule has been revised. Keep the updated schedule current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.

a. Narrative Report: Identify and justify the following:

(1) Progress made in each area of the project;

(2) Longest Path;

(3) Date/time constraint(s), other than those required by the contract;

(4) Listing of changes made between the previous schedule and current updated schedule including: added or removed activities, original and remaining durations for activities that have not started, logic (sequence, constraint, lag/lead), milestones, planned sequence of operations, longest path, calendars or calendar assignments, and cost loading.

(5) Any decrease in previously reported activity Earned Amount;

(6) Pending items and status thereof, including permits, changes orders, and time extensions;

(7) Status of Contract Completion Date and interim milestones;

(8) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);

(9) Description of current and future schedule problem areas.

For each entry in the narrative report, cite the respective Activity ID and Activity Name, the date and reason for the change, and description of the change.

1.5 3-WEEK LOOK AHEAD SCHEDULE

Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule.

Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Construction Schedule on an electronic spreadsheet program. Activities must not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work. Deliver one electronic file of the 3-Week

Section 01 33 00 Page 3 of 3

Look Ahead Schedule to the Contracting Officer no later than 8 a.m. each Monday, and review during the weekly CQC Coordination or Production Meeting.

1.6 CORRESPONDENCE AND TEST REPORTS:

Correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs) must reference Schedule Activities that are being addressed. Test reports (e.g., concrete, soil compaction, weld, pressure) must reference Schedule Activities that are being addressed.

1.7 ADDITIONAL SCHEDULING REQUIREMENTS

Any references to additional scheduling requirements, including systems to be inspected, tested and commissioned, that are located throughout the remainder of the Contract Documents, are subject to all requirements of this section.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

Section 01 33 00 Page 1 of 13

SECTION 01 33 00

SUBMITTAL PROCEDURES

1.1 SUMMARY

1.1.1 Submittal Information

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

1.1.2 Project Type

The Contractor's Project Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified.

Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications;

warranties; and other such required submittals.

1.1.3 Submission of Submittals

Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:

Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.

Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates Of Insurance

Section 01 33 00 Page 2 of 13

Surety Bonds

List Of Proposed Subcontractors

List Of Proposed Products

Baseline Schedule

Submittal Register

Schedule Of Prices Or Earned Value Report

Accident Prevention Plan

Work Plan

Quality Control (QC) plan

Environmental Protection Plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Section 01 33 00 Page 3 of 13

Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports

Daily logs and checklists

Final acceptance test and operational test procedure

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits

Text of posted operating instructions

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and (SDS)concerning impedances, hazards and safety precautions.

SD-09 Manufacturer's Field Reports

Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.

Factory test reports.

SD-10 Operation and Maintenance Data

Data provided by the manufacturer, or the system provider, including manufacturer's help and product line documentation, necessary to maintain and install equipment, for operating and maintenance use by facility personnel.

Data required by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

Data incorporated in an operations and maintenance manual or control system.

Section 01 33 00 Page 4 of 13

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Special requirements necessary to properly close out a construction contract.

For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Approving Authority

Office or designated person authorized to approve the submittal.

1.2.3 Work

As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that

Submittal Register; G

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."

1.4.2 For Information Only

Submittals not requiring Government approval will be for information only.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."

1.5 PREPARATION

1.5.1 Transmittal Form

Section 01 33 00 Page 5 of 13

Transmit each submittal, except sample installations and sample panels to the office of the approving authority using the transmittal form prescribed by the Contracting Officer. Include all information prescribed by the transmittal form and required in paragraph IDENTIFYING SUBMITTALS. Use the submittal transmittal forms to record actions regarding samples.

Use the R2EN-021 transmittal form for submitting both Government-approved and information-only submittals. These forms or similar forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.5.2 Submittal Format

1.5.2.1 Format of SD-01 Preconstruction Submittals

When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the contract documents.

1.5.2.2 Format for SD-02 Shop Drawings

Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.

Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.

a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, industry, and technical society publication references.

b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.

Submit an electronic copy of drawings in PDF format and native electronic format.

1.5.2.2.1 Drawing Identification

Include on each drawing the drawing title, number, date, and revision numbers and dates.

Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.

1.5.2.3 Format of SD-03 Product Data

Section 01 33 00 Page 6 of 13

Present product data submittals for each section. Include a table of contents, listing the page and catalog item numbers for product data.

Indicate, by prominent notation, each product that is being submitted;

indicate the specification section number and paragraph number to which it pertains.

1.5.2.3.1 Product Information

Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.

Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.

1.5.2.3.2 Standards

Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.

1.5.2.3.3 Data Submission

Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of the construction effort.

Submit the manufacturer's instructions before installation.

1.5.2.4 Format of SD-04 Samples

1.5.2.4.1 Sample Characteristics

Furnish samples in the following sizes, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:

a. Sample of Equipment or Device: Full size.

b. Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by 11 inches.

Section 01 33 00 Page 7 of 13

c. Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.

d. Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.

e. Sample Volume of Nonsolid Materials: Pint. Examples of nonsolid materials are sand and paint.

f. Color Selection Samples: 2 by 4 inches. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.

g. Sample Panel: 4 by 4 feet.

h. Sample Installation: 100 square feet.

1.5.2.4.2 Sample Incorporation

Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at the time of use.

Recording of Sample Installation: Note and preserve the notation of any area constituting a sample installation, but remove the notation at the final clean-up of the project.

1.5.2.4.3 Comparison Sample

Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.

When color, texture, or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.

1.5.2.5 Format of SD-05 Design Data

Provide design data and certificates in electronic format (PDF).

1.5.2.6 Format of SD-06 Test Reports

By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.

1.5.2.7 Format of SD-07 Certificates

Provide design data and certificates in electronic format (PDF).

Section 01 33 00 Page 8 of 13

1.5.2.8 Format of SD-08 Manufacturer's Instructions

Present manufacturer's instructions submittals for each section. Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry, and technical-society publication references. If supplemental information is needed to clarify the manufacturer's data, submit it as specified for SD-07 Certificates.

Submit the manufacturer's instructions before installation.

1.5.2.8.1 Standards

Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.

1.5.2.9 Format of SD-09 Manufacturer's Field Reports

By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.

1.5.2.10 Format of SD-10 Operation and Maintenance Data (O&M)

Comply with the requirements specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA for O&M Data format.

1.5.2.11 Format of SD-11 Closeout Submittals

When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.

Provide data in the unit of measure used in the contract documents.

1.5.3 Source Drawings for Shop Drawings

1.5.3.1 Source Drawings

The source drawing files (DWG) will not be provided to the Contractor.

1.5.4 Electronic File Format

Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within, and also separately attach the native files which were used to create PDF.

Section 01 33 00 Page 9 of 13

The attached files should include the original digital files used to create the submittal. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is searchable and can be copied. If documents are scanned, optical character resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature or a scan of a signature.

1.6 INFORMATION ONLY SUBMITTALS

Submittals without a "G" designation must be certified by the QC manager and submitted to the Contracting Officer for information-only. Provide information-only submittals to the Contracting Officer a minimum of 14 calendar days prior to the Preparatory Meeting for the associated Definable Feature of Work (DFOW). Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer will mark "Receipt Acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.7 PROJECT SUBMITTAL REGISTER

1.7.1 Submittal Management

Prepare and maintain a submittal register, as the work progresses. As an attachment, provide a submittal register showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required.

The Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.

1.7.2 Preconstruction Use of Submittal Register

Submit the submittal register. Verify that all submittals required for the project are listed.

1.7.3 Action Codes

1.7.3.1 Government Review Action Codes

Section 01 33 00 Page 10 of 13

"A" - "Approved/Complies"

"AN" - "Approved/Complies as noted"

"RR" - "Revise and Resubmit";

"D" - "Disapproved"

"RA" - "Receipt Acknowledged"

"N" - "No Action"

1.7.4 Delivery of Copies

Submit an updated electronic copy of the submittal register to the Contracting Officer with each invoice request. Provide an updated Submittal Register monthly regardless of whether an invoice is submitted.

1.8 VARIATIONS

Variations from contract requirements require Contracting Officer approval pursuant to contract Clause FAR 52.236-21 Specifications and Drawings for Construction, and will be considered where advantageous to the Government.

1.8.1 Considering Variations

Discussion of variations with the Contracting Officer before submission of a variation submittal will help ensure that functional and quality requirements are met and minimize rejections and resubmittals. For variations that include design changes or some material or product substitutions, the Government may require an evaluation and analysis by a licensed professional engineer hired by the contractor.

Specifically point out variations from contract requirements in a transmittal letter. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.

1.8.2 Proposing Variations

When proposing variation, deliver a submittal, clearly marked as a "VARIATION" to the Contracting Officer, with documentation illustrating the nature and features of the variation including any necessary technical submittals and why the variation is desirable and beneficial to Government.

If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.

The Contracting Officer will indicate an approval or disapproval of the variation request; and if not approved as submitted, will indicate the Government's reasons therefore. Any work done before such approval is received is performed at the Contractor's risk.

Specifically point out variations from contract requirements in a transmittal letter. Failure to point out variations may cause the Government

Section 01 33 00 Page 11 of 13 to require rejection and removal of such work at no additional cost to the Government.

1.8.3 Warranting that Variations are Compatible

When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.8.4 Review Schedule Extension

In addition to the normal submittal review period, a period of 14 working days will be allowed for the Government to consider submittals with variations.

1.9 SCHEDULING

Schedule and submit concurrently product data and shop drawings covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.

a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.

b. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.

Contracting Officer review will be completed within 10 working days after the date of submission.

1.10 GOVERNMENT APPROVING AUTHORITY

When the approving authority is the Contracting Officer, the Government will:

a. Note the date on which the submittal was received.

b. Review submittals for approval within the scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with comments and markings appropriate for the action indicated.

1.10.1 Review Notations

Submittals will be returned to the Contractor with the following notations:

Section 01 33 00 Page 12 of 13

a. Submittals marked "approved" or "accepted" authorize proceeding with the work covered.

b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize proceeding with the work covered provided that the Contractor takes no exception to the corrections.

c. Submittals marked "not approved," "disapproved," or "revise and resubmit" indicate incomplete submittal or noncompliance with the contract requirements or design concept. Resubmit with appropriate changes. Do not proceed with work for this item until the resubmittal is approved.

d. Submittals marked "not reviewed" indicate that the submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.

e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.

1.11 DISAPPROVED SUBMITTALS

Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer as required under the FAR clause titled CHANGES.

The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.12 APPROVED SUBMITTALS

Approval or acceptance by the Government for a submittal does not relieve the Contractor of the responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC) requirements of this contract, the Contractor is responsible for ensuring information contained with in each submittal accurately conforms with the requirements of the contract documents.

After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.13 APPROVED SAMPLES

Section 01 33 00 Page 13 of 13

Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, provide assurance that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.

Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those that may be damaged in testing, will be returned to the Contractor, at its expense, upon completion of the contract. Unapproved samples will also be returned to the Contractor at its expense, if so requested.

Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make as that material. The Government reserves the right to disapprove any material or equipment that has previously proved unsatisfactory in service.

Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.

Replace such materials or equipment to meet contract requirements.

1.14 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

1.15 CERTIFICATION OF SUBMITTAL DATA

Certify the submittal data as follows on Form R2EN-021: "I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

______NAME OF CONTRACTOR ______ SIGNATURE OF CONTRACTOR

Not Used

Hagerman NWR HVAC VRF Replacement HAGERMANVRF

Section 01 42 00 Page 1 of 4

SECTION 01 42 00

SOURCES FOR REFERENCE PUBLICATIONS

1.1 REFERENCES

Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g., ASTM B564 Standard Specification for Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.

1.2 ORDERING INFORMATION

The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided.

AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)

2111 Wilson Blvd, Suite 400 Arlington, VA 22201 Ph: 703-524-8800 Internet: http://www.ahrinet.org

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

1791 Tullie Circle, NE Atlanta, GA 30329 Ph: 404-636-8400 or 800-527-4723 Fax: 404-321-5478 E-mail: ashrae@ashrae.org Internet: https://www.ashrae.org/

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

Two Park Avenue New York, NY 10016-5990 Ph: 800-843-2763 Fax: 973-882-1717 E-mail: customercare@asme.org Internet: https://www.asme.org/

AMERICAN WELDING SOCIETY (AWS)

8669 NW 36 Street, #130 Miami, FL 33166-6672 Ph: 800-443-9353 Internet: https://www.aws.org/

ASSOCIATED AIR BALANCE COUNCIL (AABC)

1220 19th St NW, Suite 410 Washington, DC 20036 http://www.ahrinet.org/ https://www.ashrae.org/ https://www.asme.org/ https://www.aws.org/

Section 01 42 00 Page 2 of 4

Ph: 202-737-0202 Fax: 202-315-0285 E-mail: info@aabc.com Internet: https://www.aabc.com/

ASTM INTERNATIONAL (ASTM)

100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 610-832-9500 Fax: 610-832-9555 E-mail: service@astm.org Internet: https://www.astm.org/

FM GLOBAL (FM)

270 Central Avenue Johnston, RI 02919-4949 Ph: 401-275-3000 Fax: 401-275-3029 Internet: https://www.fmglobal.com/

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

445 and 501 Hoes Lane Piscataway, NJ 08854-4141 Ph: 732-981-0060 or 800-701-4333 Fax: 732-981-9667 E-mail: onlinesupport@ieee.org Internet: https://www.ieee.org/

INTERNATIONAL CODE COUNCIL (ICC)

500 New Jersey Avenue, NW 6th Floor, Washington, DC 20001 Ph: 800-786-4452 or 888-422-7233 Fax: 202-783-2348 E-mail: order@iccsafe.org Internet: https://www.iccsafe.org/

MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS

INDUSTRY (MSS)

127 Park Street, NE Vienna, VA 22180-4602 Ph: 703-281-6613 E-mail: info@msshq.org Internet: http://msshq.org

NATIONAL ELECTRICAL CONTRACTORS ASSOCIATION (NECA)

3 Bethesda Metro Center, Suite 1100 Bethesda, MD 20814 Ph: 301-657-3110 Fax: 301-215-4500 Internet: https://www.necanet.org/

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

1300 North 17th Street, Suite 900 Arlington, VA 22209 Ph: 703-841-3200 Internet: https://www.nema.org https://www.aabc.com/ https://www.astm.org/ https://www.fmglobal.com/ https://www.ieee.org/ https://www.iccsafe.org/ http://msshq.org/ https://www.necanet.org/ https://www.nema.org/

Section 01 42 00 Page 3 of 4

NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)

8575 Grovemont Circle Gaithersburg, MD 20877 Ph: 301-977-3698 Fax: 301-977-9589 Internet: http://www.nebb.org

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

1 Batterymarch Park Quincy, MA 02169-7471 Ph: 800-344-3555 Fax: 800-593-6372 Internet: https://www.nfpa.org

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

4201 Lafayette Center Drive Chantilly, VA 20151-1219 Ph: 703-803-2980 Fax: 703-803-3732 Internet: https://www.smacna.org/

U.S. ARMY CORPS OF ENGINEERS (USACE)

CRD-C DOCUMENTS available on Internet: http://www.wbdg.org/ffc/army-coe/standards Order Other Documents from:

Official Publications of the Headquarters, USACE E-mail: hqpublications@usace.army.mil Internet: http://www.publications.usace.army.mil/ or https://www.hnc.usace.army.mil/Missions/Engineering- Directorate/TECHINFO/

U.S. DEPARTMENT OF DEFENSE (DOD)

Order DOD Documents from:

Room 3A750-The Pentagon 1400 Defense Pentagon Washington, DC 20301-1400 Ph: 703-571-3343 Fax: 215-697-1462 E-mail: customerservice@ntis.gov Internet: https://www.ntis.gov/ Obtain Military Specifications, Standards and Related Publications from:

Acquisition Streamlining and Standardization Information System

(ASSIST)

Department of Defense Single Stock Point (DODSSP) Document Automation and Production Service (DAPS) Building 4/D 700 Robbins Avenue Philadelphia, PA 19111-5094 Ph: 215-697-6396 - for account/password issues Internet: https://assist.dla.mil/online/start/; account registration required Obtain Unified Facilities Criteria (UFC) from:

Whole Building Design Guide (WBDG) http://www.nebb.org/ https://www.nfpa.org/ https://www.smacna.org/ http://www.wbdg.org/ffc/army-coe/standards http://www.wbdg.org/ffc/army-coe/standards http://www.publications.usace.army.mil/ https://www.hnc.usace.army.mil/Missions/Engineering-Directorate/TECHINFO https://www.hnc.usace.army.mil/Missions/Engineering-Directorate/TECHINFO https://www.ntis.gov/ https://assist.dla.mil/online/start

Section 01 42 00 Page 4 of 4

National Institute of Building Sciences (NIBS) 1090 Vermont Avenue NW, Suite 700 Washington, DC 20005 Ph: 202-289-7800 Fax: 202-289-1092 Internet: https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

8601 Adelphi Road College Park, MD 20740-6001 Ph: 866-272-6272 Internet: https://www.archives.gov/ Order documents from:

Superintendent of Documents U.S. Government Publishing Office (GPO) 732 N. Capitol Street, NW Washington, DC 20401 Ph: 202-512-1800 or 866-512-1800 Bookstore: 202-512-0132 Internet: https://www.gpo.gov/

UNDERWRITERS LABORATORIES (UL)

2600 N.W. Lake Road Camas, WA 98607-8542 Ph: 877-854-3577 or 360-817-5500 E-mail: CustomerExperienceCenter@ul.com Internet: https://www.ul.com/ UL Directories available through IHS at https://ihsmarkit.com/

Not used

Not used https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc https://www.archives.gov/ https://www.gpo.gov/ https://www.ul.com/ https://ihsmarkit.com/

Section 01 45 00.00 Page 1 of 4

SECTION 01 45 00.00

QUALITY CONTROL

1.1 SUMMARY

The requirements of this section apply to and are a component part of each section of the specifications.

1.2 ADMINISTRATIVE REQUIREMENTS

Notify the Government 48 hours before work will begin at the site.

Notify the Contracting Officer when work is suspended for five working days or longer. Do not resume work without notifying the Contracting Officer.

Notify the Contracting Officer at least 48 hours before backfilling or encasing any underground utility.

1.3 SUBMITTALS

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that

SD-06 Test Reports

Inspection Records;

Field Tests;

Factory Tests;

1.4 QUALITY CONTROL

1.4.1 Quality Control Requirements

Provide a quality control program that includes: selection of construction materials and sources; suppliers; subcontractors; on-site and off-site fabrication of Contractor-furnished assemblies; on-site and off-site assembly; erection; work procedures; workmanship; inspection; and testing.

Provide document systems ensuring that quality provisions of the contract schedule, specifications, and drawings have been performed.

1.4.1.1 Procurement

Assume responsibility for controlling procurement sources and those of the subcontractors to ensure that each purchase meets quality requirements.

Section 01 45 00.00 Page 2 of 4

1.4.1.2 Receiving Inspection System

Maintain a site receiving inspection system that ensures that procured materials and equipment are inspected and tested.

Ensure that receiving inspection records accompany each procurement delivery to the construction site. Maintain records of site receiving inspections.

Show defects, discrepancies, dispositions, and waivers. Include evidence of Government source inspection within the records.

1.4.1.3 Nonconforming Articles and Material Control

Control nonconformances discovered by the Contractor, subcontractors, suppliers, or Government quality representatives to prevent the use of affected products and to correct deficient operations.

a. Provide a "nonconformance" report for each instance comprising:

(1) A unique and traceable number.

(2) Identification of the nonconforming article or material.

(3) A description of the nonconformance and the applicable requirement.

(4) Cause or reason for the nonconformance.

(5) Remedial actions taken or recommended.

(6) Disposition of the nonconforming article or material.

b. Identify and mark each nonconforming article for removal from the work area.

c. Monitor and correct deficient operations.

1.4.1.4 Fabrication, Process, and Work Control

Ensure compliance of requirements in contract specifications and drawings with procedures and controls.

Establish in-process inspections, to ensure compliance with quality requirements.

1.4.1.5 Quality Control Records

Maintenance of quality control records does not provide relief from submitting samples, test data, detail drawings, material certificates, or other information required by each section in the specification.

Ensure that each record is identified and traceable to specific requirements in the specifications and drawings.

1.4.2 Quality Inspections

1.4.2.1 Government Inspections

Section 01 45 00.00 Page 3 of 4

Work performed under this contract is subject to inspection by the Contracting Officer. Changes to the specifications or drawings will not be allowed without written authorization of the Contracting Officer.

When the Contracting Officer determines that inspected work needs to be corrected, allow the Contracting Officer 24[hours to complete reinspection of the corrected work.

Notify the Contracting Officer in writing before backfilling or encasing any underground utility so that work may be inspected. Failure to notify the Contracting Officer before backfill or encasement occurs will require the work to be uncovered at no additional cost to the Government.

The Contractor's Quality Program is subject to evaluation, review, and verification as determined by the Contracting Officer. Contractor will be notified in writing of any noncompliance and will be given 14 calendar days to correct identified deficiencies.

1.4.2.2 Contractor's Quality Inspections

Implement an inspection system that documents and indicates quality control through records of inspections, tests, and procedures.

Include or identify the following within the Quality Assurance System:

a. The representative responsible for on-site communication and operation of the inspection program.

b. A receiving inspection system documenting inspections for each procurement.

c. Documentation for handling and disposing of nonconforming components and materials.

d. Inspection records for each specific section of the specification and drawings.

e. Identification of tests to be performed, test procedures, records, and independent organizations used.

f. Documentation that shows certification or recertification of procedures.

g. Calibration of gages, tools, measuring instruments, and independent laboratories used.

Establish a system of scheduled or random audits to ensure task completion.

1.4.3 Field Services

1.4.3.1 Responsibility for Inspection and Testing

Assume responsibility for all inspections and tests and for the accompanying documentation.

Section 01 45 00.00 Page 4 of 4

1.4.3.2 Inspection and Test Records

Maintain records of each inspection and test performed throughout the life of the contract, including factual evidence that the required inspections or tests have been performed, which include the type and number of inspections or tests involved, identification of operators and inspectors, result of inspections or tests, nature of defects, causes for rejection, proposed remedial action, and corrective actions taken.

Ensure that all inspection records, test procedures, test results, and associated forms are verified by and provided to the Contracting Officer.

Submit final test data with a cover letter/sheet clearly marked with the system name, date, and the words "Final Test Data.

Notify the Government at least three days before scheduled inspections and tests.

1.5 DELIVERY, STORAGE, AND HANDLING

Provide controls, procedures and documentation with each shipment, that meet requirements of each section of the specifications.

With each shipment, include documentation required by the contract along with specifications necessary to identify, store, preserve, operate, and maintain the items shipped.

2.1 SYSTEM DESCRIPTION

2.1.1 Records

Include all factory tests or manufacturer's certifications; and routine field tests and similar tests. Ensure that quality records are available for examination by the Contracting Officer.

Furnish legible copies of the test and inspection records to the Contracting Officer. Ensure that records cover work placement traceable to the contract schedule, specifications and drawings, and that records are verifiable.

2.1.1.1 Letters of Authority or Delegation

Submit to the Contracting Officer letters of authority or delegation outlining the authority and responsibilities of quality control personnel along with a copy of the letter of delegation that defines delegated duties and responsibilities.

Section 01 78 00 Page 1 of 10

SECTION 01 78 00

CLOSEOUT SUBMITTALS

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM E1971 (2005; R 2011) Standard Guide for Stewardship for the Cleaning of Commercial and Institutional Buildings

U.S. ARMY CORPS OF ENGINEERS (USACE)

ERDC/ITL TR-19-6 (2019) A/E/C Graphics Standard, Release 2.1

ERDC/ITL TR-19-7 (2019) A/E/C CAD Standard - Release 6.1

1.2.1 As-Built Drawings

As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the Contract Documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications; official responses to submitted Requests for Information (RFI's); direction from the Contracting Officer; design that is the responsibility of the Contractor, and differing site conditions. Maintain the as-builts throughout construction as red-lined hard copies on site. These files serve as the basis for the creation of the record drawings.

1.2.2 Record Drawings

The record drawings are the final compilation of actual conditions reflected in the as-built drawings.

1.3 SOURCE DRAWING FILES

Request the full set of electronic drawings, in the source format, for Record Drawing preparation, after award and at least 15 working days prior to required use.

1.3.1 Terms and Conditions

Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government.

Section 01 78 00 Page 2 of 10

The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files.