A06_PROLOGUE_REV1_NIFC_Campus_Storm_Drain_Piping_Replacement_27FEB2023.pdf

PDF 140 KB Posted

Attached to
NIFC Campus Storm Drain Federal contract opportunity
Solicitation number
140L3723R0001
Issued by
Department of the Interior Bureau of Land Management Idaho Region

About this file

This document provides details for a federal construction project opportunity with the Bureau of Land Management in Idaho. The project scope involves replacing storm drain piping on the campus of the National Interagency Fire Center, including demolition of existing site features and construction of new concrete, asphalt, utilities, and stormwater infrastructure. Key requirements include performing work within a 150-day period while limiting on-site construction to 90 days, with no trenching allowed until after October 1st, providing security fencing and safety barriers, and adhering to COVID safety protocols as directed by NIFC. Offerors must be able to work on an occupied campus and control dust and access. The pre-bid meeting date is specified in the related solicitation. Interested parties should respond to solicitation number 140L3723R0001 by the response deadline to be considered for this storm drain replacement project at the NIFC campus in Boise, Idaho led by the Bureau of Land Management.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

BUREAU OF LAND MANAGEMENT

Fire and Aviation 3833 S Development Ave

Boise, Idaho 83705-5354

February 27, 2023

PROLOGUE

NIFC-CAMPUS STORM PIPE REPLACEMENT - GAOA21

This project is for construction of site features including concrete and asphalt pavement, site utilities, water and storm piping, and site demolition. The project location is at the National Interagency Fire Center at 3833 S. Development Avenue, in Boise, ID 83705.

General information about the construction is provided below.

1. Construction Period: The total period of performance is 150 days for this work. The construction time on site is limited to 90-days. No trenching through campus during the period of performance until after October 1st, 2023.

2. Campus Occupancy and Safety: The campus will be occupied during this construction.

The adjacent buildings will be occupied during this construction project. Contractor is responsible for providing adequate dust control measures are in place to prevent dust migration into buildings. Contractor shall provide sufficient safety barriers for the site and walkways.

3. Site Security: Contractor shall install a temporary lockable perimeter fence before demolishing current security fence. The perimeter fence shall be secure at all times.

Contractor is responsible for ensuring security fencing is in place at the end of each work day. Contractor shall provide continuous monitoring of perimeter in work area when fence is not in place. Contractor shall coordinate with the COR when perimeter fence will be removed.

4. NIFC Access: NIFC is a controlled access federal facility. Visitors and contractors are vetted at Main Gate prior to entry. The following are requirements for entry to site:

a. Prior notification. The Contractor shall provide a listing of personnel and the time period access will be needed for each individual. This information is required 3 days prior to arrival.

b. Identification. Contractor personnel shall present an official US Government or State Government issued photo identification at the security gate. If driving, a valid driver’s license is required.

c. Identification shall adhere to REAL ID standards upon effective date of federal requirement.

d. Pass display. All the contactors’ personnel shall wear the NIFC furnished badge between the waist and shoulders while on campus and shall return the badge upon expiration.

e. Contractor personnel shall not enter the site more than 30 minutes prior to the start of scheduled workday and must leave the facility within 30 minutes of the scheduled workday completion.

f. COVID Requirements: Contractor shall adhere to COVID requirements and processes based on community and transmission levels. NIFC will have all levels and requirements posted and entry gate.

5. Contractor Area: A lay-down, staging, and contractor-provided portable toilet area will be designated for the project. The physical size of the area required will be coordinated with the government upon award. Contractor shall provide sanitary facilities during the construction period for their employees and subcontractors.

6. Work Hours: Construction work shall be conducted during regular office hours which are 8:00 am to 4:30 pm, Monday through Friday with exceptions for holidays and early releases. Contractor requested work during holidays, evenings, nights, and weekends will be considered by the government COR on a case-by-case basis.

7. Pre-Bid Meeting: Refer to solicitation for date, time, & location of the pre-bid meeting.

--end--