A06_-_140L1721Q0031-Specifications.pdf

PDF 410 KB Posted

Attached to
UFO ROAD WORK FY2021 Federal contract opportunity
Solicitation number
140L1721Q0031
Issued by
Department of the Interior Bureau of Land Management Colorado Region

View the file

Other files for this federal contract opportunity

Other files attached to UFO ROAD WORK FY2021, newest first.
File Type Posted
B13_-_140L1721Q0031-_Fillable_889_Form.pdf PDF
A06_-_140L1721Q0031-Plans.pdf PDF
Sol_140L1721Q0031.pdf PDF
A04_-_140L1721Q0031-Schedule_of_Items.pdf PDF
B13_-_140L1721Q0031_-Past_Performance_Questionnaire.doc DOC document
B03_-_140L1721Q0031-_Wage_Rate.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior Bureau of Land Management

Uncompahgre Field Office

Road Maintenance FY 2021

SPECIFICATIONS

UFO - Road Maintenance FY2021 UFO2021RDWORK

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 SUMMARY OF WORK

01 20 00 PRICE AND PAYMENT PROCEDURES

01 33 00 SUBMITTAL PROCEDURES

01 57 60 SUPPLEMENTAL ENVIRONMENTAL CONTROLS

DI VI SI ON 31 - EARTHWORK

31 00 50 ROAD MAINTENANCE AND RECONDITIONING

31 00 60 ROLLING DIP CONSTRUCTION AND MAINTENANCE

31 00 70 CHECK DAM

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 PROJECT DESCRIPTION

The work includes, but is not limited to; road maintenance, road reconditioning, rolling dip construction, and rolling dip reconstruction.

1.2 LOCATION

The project is located within Montrose County and Delta County, Colorado.

1.3 WORK DURATION AND SCHEDULE

Work shall be completed within 270 days of the notice to proceed. The work will not take that long. The allowable duration is to allow multiple opportunities to work within the work restrictions. Work shall occur

Monday - Friday, excluding federal holidays.

1.4 WORK RESTRICTIONS

Road maintenance work will only be allowed after the ground has received precipitation, or when the ground has some moisture. Work will not be allowed when the ground is dry, after prolonged periods without precipitation.

1.4.1 Black Ridge Roads - Work Restriction

Work will not be allowed on the Black Ridge Roads from 30 November to 15 May to protect wildlife. There are not any restrictions for wildlife on Poison Springs Roads.

1.5 PICTURES

The pictures on the plans are for reference only. The pictures do not fully represent the entire roads. The pictures only to show general characteristics of the roads.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 2

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

Payment items for the work of this contract for which contract payments will be made are listed in the

SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job are included in the listed job item most closely associated with the work involved.

The price and payment made for each item listed constitutes full compensation for furnishing all labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1 POISON SPRINGS ROADS - ROAD MAINTENANCE

1.1.1 Payment

Payment will be made for all costs associated with maintaining Poison Springs Roads, in the locations specified on the plans.

1.1.2 Unit of Measure

Unit of measure: Linear Feet.

1.2 POISON SPRINGS ROADS - DIP CONSTRUCTION

1.2.1 Payment

Payment will be made for all costs associated with constructing a dip.

1.2.2 Unit of Measure

Unit of measure: Each.

1.3 POISON SPRINGS ROADS - EXISTING DIP RECONSTRUCTION

1.3.1 Payment

Payment will be made for all costs associated with reconstructing an existing dip.

1.3.2 Unit of Measure

Unit of measure: Each.

SECTION 01 20 00 Page 3

1.4 POISON SPRINGS ROADS - LEAD-OFF DITCH

1.4.1 Payment

Payment will be made for all costs associated with constructing a new lead-off ditch.

1.4.2 Unit of Measure

Unit of measure: Each.

1.5 POISON SPRINGS ROADS - CHECK DAM CONSTRUCTION

1.5.1 Payment

Payment will be made for all costs associated with constructing check dams.

1.5.2 Unit of Measure

Unit of measure: Ton.

1.6 BLACK RIDGE ROADS - DIP CONSTRUCTION

1.6.1 Payment

Payment will be made for all costs associated with constructing a dip.

1.6.2 Unit of Measure

Unit of measure: Each.

1.7 BLACK RIDGE ROADS - EXISTING DIP RECONSTRUCTION

1.7.1 Payment

Payment will be made for all costs associated with reconstructing an existing dip.

1.7.2 Unit of Measure

Unit of measure: Each.

1.8 BLACK RIDGE ROADS - LEAD-OFF DITCH

1.8.1 Payment

Payment will be made for all costs associated with constructing a lead-off ditch.

SECTION 01 20 00 Page 4

1.8.2 Unit of Measure

Unit of measure: Each.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00 Page 5

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only.

1.2 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer's

Representative is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the

Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the

Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.3 GOVERNMENT APPROVING AUTHORITY

The Contracting Officer's Representative will:

a. Note the date on which the submittal was received.

b. Review submittals for approval within 10 days of receipt.

c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.

Upon completion of review of submittals requiring Government approval, one copy of the submittal will be retained by the Contracting Officer's Representative and one copy of the submittal will be returned to the

Contractor.

1.3.1 Review Notations

Submittals will be returned to the Contractor with the following notations:

a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.

b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided the Contractor takes no exception to the corrections.

c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.

d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is

SECTION 01 33 00 Page 6 not required, does not have evidence of being reviewed and approved by Contractor, or is not complete.

A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed.

Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.

e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the

Government. This applies only to "information-only submittals" as previously defined.

1.4 DISAPPROVED SUBMITTALS

Make corrections required by the Contracting Officer's Representative. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting

Officer.

If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.5 APPROVED SUBMITTALS

The Contracting Officer's approval of submittals is not to be construed as a complete check.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 33 00 Page 7

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 1 PAGES

UFO - Road Maintenance FY2021

01 57 60 SD-01 Preconstruction Submittals

3.3 GSpill Prevention And Cleanup

Plan

31 00 70 SD-07 Certificates

2.1Weight Tickets

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SECTION 01 57 60

SUPPLEMENTAL ENVIRONMENTAL CONTROLS

PART 1 GENERAL

1.1 DEFINITIONS

Equipment: for the purpose of this specification, equipment shall include, but isn't limited to; dozers, backhoes, trackhoes, trailers, graders, compactors, or any other construction equipment used to accomplish the work. Passenger vehicles are not considered equipment.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Spill Prevention And Cleanup Plan; G

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 FIRE PREVENTION

All equipment shall have a spark arrester installed. The Contractor shall have a fire extinguisher and shovel readily available to contain and extinguish fires.

3.2 EQUIPMENT CLEANING AND MAINTENANCE

Equipment shall be cleaned prior to arriving on site. Equipment shall arrive on site free from dirt, debris, weeds, and seeds. All equipment shall be inspected by the Contracting Officer's Representative prior to arriving on site. Notify the Contracting Officer's Representative at least 7 days prior to equipment delivery to coordinate inspection. If equipment leaves the jobsite and returns at a later date, then equipment shall be re-inspected before reentering the work site.

Equipment maintenance will not be allowed on site. Equipment leaking fluids shall be removed from site.

3.3 SPILL PREVENTION

The Contractor shall submit a spill prevention and cleanup plan. The spill prevention and cleanup plan shall identify foreseeable accidents, including spills while adding fluids to equipment, and identify an action plan to rapidly clean all accidents. Cleanup materials and equipment shall be on site during work.

3.4 WASTE CONTROL

All waste generated by the work shall be contained and removed from the site and disposed of in a legal manor.

SECTION 01 57 60 Page 8

SECTION 01 57 60 Page 9

SECTION 31 00 50

ROAD MAINTENANCE AND RECONDITIONING

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

Maintain and recondition existing roads. Rebuild and reshape the; traveled way, turnouts, shoulders, ditches, waterbars, and rolling dips.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 ROADWAY SHAPING AND GRADING

3.1.1 SCARIFY

Prior to shaping, scarify the roadway to a depth greater than existing ruts, washboards, potholes, or other surface irregularities.

3.1.2 SHAPING AND GRADING

Shape the roadway in a manner that will conserve usable material; usable material shall not be graded into ditches and/or over the shoulders of the road.

Provide a cross slope that will drain water across the roadway. Maintain an inslope, outslope, or crown.

3.1.3 FINISHING

Finish the road surface to be reasonably smooth, uniform, and shaped to conform to the typical sections as shown on the drawings.

Remove from the road surface any rock larger than 3 inches in its greatest dimension.

Vegetation and organic material larger than 12 inches in length, or larger than 2 inches in diameter, shall be removed from the roadway.

3.2 ENTRENCHED ROAD SECTIONS

Entrenched road sections shall be excavated, shaped and graded as shown on the drawings. Excavated material from entrenched sections shall be incorporated into the roadway. The excavated, and incorporated, material shall be compacted in layers not exceeding six inches.

3.3 ROLLING DIPS AND WATERBARS

Where rolling dips and waterbars exist, they shall be cleaned and restored as nearly as possible to their original dimensions.

SECTION 31 00 50 Page 10

SECTION 31 00 50 Page 11

SECTION 31 00 60

ROLLING DIP CONSTRUCTION AND MAINTENANCE

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

Construct and reconstruct rolling dips as shown on the drawings and as specified.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 ROLLING DIP CONSTRUCTION

3.1.1 EXCAVATION

Material excavated in the creation of the rolling dip shall be conserved, including material excavated from the outlet ditch construction. Excavated material shall be used to construct the crest of the rolling dip. Excess excavated material shall be spread uniformly over the roadway.

3.1.2 EMBANKMENT

The crest of the rolling dip shall be compacted to a uniformly firm surface in layers not exceeding six inches.

3.1.3 DRAINAGE OUTLET

Provide outlet ditch to daylight.

3.2 ROLLING DIP RECONSTRUCTION AND MAINTENANCE

Where rolling dips exist, they shall be cleaned and restored as nearly as possible to their original dimensions.

Provide drainage ditches as necessary to allow free flow of water into, and away from, the dip.

3.2.1 EXISTING ROLLING DIP MATERIAL RECLAMATION

Reclaim eroded roadway material. Excavate material from the existing outlet ditch. Reuse that material in the construction of the rolling dip and put excess material on the road. Do not "waste" existing eroded material, from the existing dip outlet ditch.

SECTION 31 00 60 Page 12

SECTION 31 00 70

CHECK DAM

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

Construct check dam as shown on the drawings and as specified.

1.2 SUBMITTALS

Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-07 Certificates

Weight Tickets

PART 2 PRODUCTS

2.1 EROSION CONTROL ROCK

Submit weight tickets for erosion control rock. Erosion control rock shall meet the following gradation.

Sieve Size Percent Passing

5 inch 100 - 90

3 inch 80 - 50

1 inch 10 - 0

PART 3 EXECUTION

3.1 INSTALLATION

Place rock in the eroded ditch in a manner that slows down runoff and controls erosion.

SECTION 31 00 70 Page 13