This performance work statement outlines requirements for the Great Smoky Mountains National Park to procure bear resistant steel dumpsters. The contractor shall design, fabricate, and deliver 20 dumpsters with latches and lids capable of withstanding bear activity. Dumpsters must be waterproof and constructed of 10-gauge steel with welded connections. Additional requirements specify dumpster dimensions, weight limits, paint coatings, reinforced side panels, gravity access doors, extended base runners and other details. The contractor must also provide shop drawings, warranties, and deliver the dumpsters to locations within the park by certain dates. The base performance includes one prototype and 19 dumpsters in year one, with additives to provide up to 30 additional dumpsters in subsequent years. The contractor must manage the work, comply with safety and environmental regulations, and maintain required insurance. Quality control and government quality assurance plans are also outlined.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| vendor_question_0001.docx | DOCX document | |
| Sol_140P5323R0058_Amd_0001.pdf | ||
| A06_GRSM_Stamped_Drawing.pdf | ||
| Sol_140P5323R0058.pdf | ||
| B08_Price_Schedule_Sheet_Dumpsters.pdf | ||
| A06_Specs_-Resistant_Dumpster(1_Lid).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bear Resistant Dumpster Purchase—Gatlinburg, TN
Performance Work Statement (PWS)
1. Background. The Great Smoky Mountains National Park (GRSM) is located in Tennessee and North Carolina and consists of nearly 521,000 acres. The park was established by Congress on June 15, 1934. The parks mission is to protect, preserve, and interpret the natural, cultural, and historical resources for the benefit and inspiration of present and future generations. There are over 13 million visitors annually.
2. Required Services. The contractor shall provide all design, labor, tools, equipment, materials and supervision required to deliver a side-load, water and bear resistant public use steel dumpsters to the Great Smoky Mountains National Park.
3. Contractor Responsibilities:
Contractor Responsibilities:
• Design, fabricate and deliver 20 steel dumpsters with additives for up to 30 dumpsters that are bear resistant and waterproof for the National Park Service, Great Smoky Mountains National Park.
• The Contractor shall be an experienced manufacturer/fabricator of, waterproof, and watertight (non-leaking) dumpsters of approximately the capacity of approximately 3 cubic yards.
• All dumpsters shall include a three (3) year warranty against manufacturing defects and impacts from Bears and Dumping Operations. The warranty shall include providing 20 additional latches for replacement to the Park during the delivery of the dumpsters.
• Dumpster Specifics:
o Capacity: 2.5 to 3.2 cubic yards o Approximate Dimensions:
▪ 54” to 60” rear height*
▪ 36” to 40” front height*
▪ 46” front to back
▪ 58” width
* Contractor shall determine optimum angle from back to front within these parameters.
o Weight of the dumpster: shall not exceed 800 pounds.
o Weight of Human Opened door: shall not exceed _____ pounds.
o Fit on __ x __ concrete pad
• All materials, fittings, and connections shall be heavy duty and designed to withstand bear activity, abusive commercial use, side-load dumping operations and harsh weather conditions.
o Truck dimensions
• Dumpster walls and floor shall be fabricated using a minimum 10-gauge ASTM A1011 sheet steel. The dumpster “box” shall be watertight.
• Dumpster lid shall be fabricated from 3/16” minimum thickness steel plate.
• Dumpster components shall be welded together. All welds shall be continuous (no spot welds), professionally performed and finished with smooth uniform appearance.
• Hinges and latches shall be stainless steel; hinges shall be continuous, full length to fit the dumpster lid and the smaller access doors.
• Dumpsters shall be coated on the interior with an automotive under seal and exteriors painted out with a heavy primer coat and two heavy coats of high quality rust inhibitive flat Brown (Federal Color 595C 28061) enamel paint, which is rated as highly resistant to abrasion, humidity, ultraviolet light and chemicals for a minimum of five (5) years.
Contractor may consider and recommend a durable spray on liner for interior bottom and sides of dumpster to inhibit rust.
• Dumpsters shall be user friendly, safe, bear/animal resistant and rain/snow proof.
• Dumpsters shall be durable and operate effectively, maintaining structural and aesthetic integrity for an expected 10-year lifetime, given the level of use common to Great Smoky
Mountains National Park.
• Dumpsters shall be designed to be mechanically lifted and emptied by side loading disposal trucks (see attached drawing for specific information for the location and size of the lifting hooks). The side panels shall be reinforced to withstand the abuse of the side loading operations.
• Dumpster shall include one self-closing gravity access door (one minimum 22” by 16” to
24”) with stainless steel bear resistant latches, located on a sloping dumpster lid as shown, to facilitate trash deposit. The latch shall have a latch cover. The latch and latch cover shall be capable of withstanding abuse during refuse collection operations and shall self- lock upon closure. The latches shall be bear/animal resistant and shall be watertight.
• The latch and latch cover shall be coated with material or color that reduces temperature from sun during hot summer months. Any color or coating will require approval by NPS.
• Dumpsters shall be mounted on extended base “runners,” to prevent overturning and to elevate dumpster floor at least 1 1/2 inches above the ground or pad.
• Contractor shall prepare shop drawings for Park approval a minimum of 14 days prior to manufacturing dumpsters. Shop drawings shall show exact dimensions, latching mechanism, latch cover, as well as location of high quality sticker showing instructions for use, bear statement, and recycling message. In addition to the shop drawing the contractor shall submit color samples for approval.
• Contractor shall deliver all dumpsters to 107 Park Headquarters Road, Gatlinburg, TN
37738 at the North District Maintenance Area between 7:30 am and 4:30 pm between
Monday and Thursday. The contractor shall give a minimum notice of 48 hours prior to delivery.
The Park intends to replace up to 180 dumpsters over the next five (5) years. The Base
Performance item includes the design of the dumpster within the stated specifications as well as production and delivery of 19 dumpsters to various locations throughout the Great Smoky
Mountains National Park. Additives for up to 30 additional dumpsters include the manufacturing and delivery of the dumpsters to various locations throughout the Great Smoky Mountains
National Park. The Park may select none, one or some of the additives.
Schedule of Work Units Price Each (Price shall include
Delivery)
Total Price
Base Performance – Year
1 – Design Dumpsters meeting specification, manufacture and deliver
20 dumpsters to the Park
(deliver to 107 Park
Headquarters Road, Gatlinburg, TN 37738)
1 prototype Dumpster +
19 copied Dumpsters
Additive 1 Year 2 –
Manufacture and deliver
30 dumpsters to the Park
(deliver to 107 Park
Headquarters Road, Gatlinburg, TN 37738)
30 Dumpsters (Same design)
Additive 2 – Year 3 –
Manufacture and deliver
30 dumpsters to the Park
(deliver to 107 Park
Headquarters Road, Gatlinburg, TN 37738)
30 Dumpsters (Same design)
4. Government Furnished Property, Materials & Supplies. None.
5. Business Hours. The contractor shall complete on-site work or delivery, including unloading, during normal business hours of 7:30 am to 4:30 pm, Monday through Thursday, excluding Federal holidays. The contractor shall coordinate specific on-site work schedule with the Contracting Officer and COTR five days prior to performance start date. While on site, the
COTR may be reached by mobile phone during normal business hours. Work shall be completed within 120 days after Contracting Officer issues notice to proceed. All deliveries shall be made between 7:30 am and 4:30 pm Monday through Thursday, excluding any Federal holidays.
Contractor shall give COTR a minimum of 48 hours advanced notice prior to delivery. All deliveries will be made to 107 Park Headquarters Road, Gatlinburg, TN 37738 at the North
District Maintenance Area.
6. Management. The contractor shall manage the total work effort in accordance with effective and efficient management principles and safe working practices to ensure on-time completion of this contract.
7. Safety & Environmental Compliance.
• The contractor shall comply with pertinent provisions of the Occupational Safety and
Health Act (OSHA), and state, local, safety, laws.
• The contractor shall comply with pertinent Environmental Protection Agency laws and regulations.
• The GRSM safety officer has the authority to issue restraint or cease-and-desist orders to the contractor when violations or unsafe acts are present and threaten Government and contractor employees or damage to Government property.
• The contractor shall immediately report to the Contracting Officer, COTR and GRSM safety officer all accidents resulting in employee injury or death or damage to property while performing this contract.
8. Insurance. The Contractor shall be insured in accordance with State of Tennessee or North
Carolina insurance regulations. The Government is not responsible for damage to Contractor’s equipment, vehicles, tools or materials or their employees and the personal property brought on-site. The Government will not accept any liability due to contractor employee negligence.
• Liability: The Contractor shall maintain a level of insurance that will protect the contractor and the Government from any claims as a result of bodily injury (including death) and property damage which may arise from and during the performance of this contract, and shall submit proof of insurance to the Contracting Officer.
9. Performance Requirements Summary (PRS). The contractor performance requirements are summarized into required services that relates directly to successful contract completion.
The performance standard identifies the minimum acceptable levels of service allowed.
PWS
Section
Required
Service Standard
Monitoring
Method
Incentive/
Disincentive
Design, manufacture and deliver dumpsters
100% compliance
100% Inspection Performance
Evaluation
100% compliance
Random Inspection Performance
Evaluation
10. Motor Vehicle & Traffic Regulations. Contractor employees operating motor vehicles shall possess an appropriate, valid driver's license. Driver and vehicle permits, licenses, registrations and proof of insurance shall be maintained in the vehicle at all times and made available upon request. Contractor employees shall comply with federal vehicle motor law requiring seat belts be worn at all times. Contractor employees shall adhere to the posted speed limits.
11. Employee Parking. All contractor employees shall comply with parking procedures published for the GRSM.
12. Replacement of Contractor Employee for Security Reasons. The Government retains the right to request removal of the contractor’s employee(s), regardless of prior clearances.
13. Non-Payment for Additional Work. Any additional contractor performed services not specified in contract, either at its own volition or at the request of an individual other than an appointed Contracting Officer, except as may be explicitly authorized in the contract, shall be performed at the financial risk of the contractor. Only an appointed Contracting Officer is authorized to bind the Government to a change in specifications, contract terms, or conditions.
14. Conflict of Interest. The contractor shall not employ off-duty COR’s or other Government employees if such employment would create a conflict of interest or be contrary to the policies contained in conflict-of-interest directives.
15. Quality Control. The contractor shall establish and maintain a Quality Control Plan (QCP) to ensure the work performed conforms to the contract requirements. The Performance
Requirements Summary establishes performance standards that are the minimum requirements for acceptable performance of required services. The contractor’s QCP shall address methods for remedying poor performance. The Contractor shall develop QCP and submit with proposal package. The Contractor’s QCP includes:
• Required services identified in Performance Requirements Summary
• Contractor’s surveillance methodology
• Method and timeframe for responding to COTR or customer complaints
• Progress meetings with Government stakeholders
16. Quality Assurance. The COTR will monitor the contractor’s performance under this contract using the quality assurance procedures specified in the Government’s Quality Assurance
Surveillance Plan (QASP). The QASP may be modified after contract award upon review and acceptance of the contractor’s QCP to ensure both plans are mutually supportive. The purpose of the QASP is to ensure that the required services are performed in accordance with the contract requirements. The plan ensures reliable and continued operation by precluding unnecessary complaints and unacceptable performance. Government’s QASP includes:
• Acceptance of the contractor’s quality control plan
• Random inspection of the contractors work
• Communicating customer complaints
• Progress meetings with the contractor
The implementation of this QASP does not relieve the contractor of its responsibility to implement and abide by the QCP incorporated into this contract, and to provide acceptable performance of all required services listed herein. At the CO’s discretion, the contractor may incur a payment deduction for lack of compliance with the QCP, PWS or PRS.
17. Contractor’s Proposal Package. The following deliverables are to be submitted with offer in response to RFQ.
• Technical approach to perform required services.
• Contractor’s QCP
• Proof of Insurance–Business Liability & Workers Compensation.
18. Inspection. The Government will conduct inspection upon completion of required services.
Final payment will be processed upon confirming that all noted contractor performance deficiencies have been satisfactorily corrected.
File details come from the government source that posted it. Updated .