About this file

This document provides details on a federal solicitation from the Department of the Interior Bureau of Land Management Nevada Region. Solicitation number 140L3922R0017 is seeking bids to install fencing at Rainbow Gardens. Interested vendors should review attachment A04_SOW.pdf for the full statement of work outlining project requirements, specifications, response date, and other contractual terms. This solicitation is for a fencing installation project at Rainbow Gardens to be awarded on a fixed-price basis.

View the file

Other files for this federal contract opportunity

Other files attached to RAINBOW GARDENS FENCE, newest first.
File Type Posted
Questions_-_Answers_0001.doc DOC document
Sol_140L3922R0017_Amd_0001.pdf PDF
Bid_Schedule.pdf PDF
B03_DBA_Wage_Determination.pdf PDF
Sol_140L3922R0017.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUREAU OF LAND MANGEMENT

RED

SOUTHERN NEVADA

RAINBOW GARDENS AREA OF

CRITICAL ENVIRONMENTAL CONCERN

WOOD POST AND WIRE CABLE FENCE

CONSTRCUTION PROJECT

JUNE 2022

STATEMENT

OF

WORK

TABLE OF CONTENTS

SECTION A – PROJECT DETAILS

SECTION B – PROJECT DETAILS

SECTION C - PERFORMANCE OF WORK

SECTION D - ADDITIONAL TERMS AND CONDITIONS

SECTION E – SITE SAFETY

ATTACHMENTS:

Exhibit 1 Vicinity Map / Fence Locations

Exhibit 2 Base Option Fence Location

Exhibit 3 Option 1 Fence Location

Exhibit 4 Option 2 Fence Location

Exhibit 5 Option 3 Fence Location

Exhibit 6A Steel Cable Fence

Exhibit 6B Modified Typical Post and Cable Fence

RAINBOW GARDENS POST AND CABLE FENCE – JUNE 2022 Page 1 of 8

SECTION A – PROJECT DETAILS

A1.0 Project Purpose and Scope:

The project calls for the construction of wood post and cable fences at various locations within the Rainbow Gardens Area of Critical Environmental Concern just east of Las Vegas, Nevada.

The purpose of these fences is to prevent unauthorized access points and illegal roads onto lands adjacent to the fence thereby allowing sensitive vegetation to recover and thrive.

All fences can be accessed using Lake Mead Boulevard. The nearest fence will be located approximately 4.2 miles east of the eastern edge of Las Vegas and the furthest approximately 7.3 miles east of Las Vegas.

From Lake Mead Boulevard, all fences are accessible via established dirt roads. Locations are shown on Exhibit 1 – Vicinity Map / Fence Locations.

A2.0 Project Descriptions:

Fence locations and descriptions are broken out as Base Option, Option 1, Option 2, and Option

3. The fence described in the Base Option is the minimum amount of fence to be constructed under this contract.

The Government may or may not exercise Options 1 thru 3 individually, collectively, or in combinations based on bid price and available Government funding. In this manner, the Government may choose to exercise one or more Options in Fiscal Year 2023 which begins on October 1, 2022 and ends on September 30, 2023.

Government and Contractor shall field confirm all fence locations prior to the start of fence construction.

A2.1 Base Option

Construct approximately 1,344 linear feet of post and steel cable fence directly off the north side of Lake Mead Blvd (SR 148), approximately 5 miles east of the Frenchman Mountain Trailhead.

This fence alignment shall be composed of two segments separated by a 30 to 50-foot wide opening at the entrance to the powerline access road, as shown on attached maps. The position and width of the opening shall be field determined by the Government in coordination with the Contractor. Approximate fence segments are listed below:

a) Base Option Segment 1 Start: (lat: 36.1859 / long: -114.9181).

b) Base Option Segment 1 End: (lat: 36.1849 / long: -114.9180).

c) Base Option Segment 2 Start: (lat: 36.1848 / long: -114.9180).

d) Base Option Segment 2 End: (lat: 36.1823 / long: -114.9172).

RAINBOW GARDENS POST AND CABLE FENCE – JUNE 2022 Page 2 of 8

A2.2 Option 1

Located directly off the south side of Lake Mead Blvd (SR 148), approximately 2.6 miles east of the Frenchman Mountain Trailhead (Attachments 3, 7).

Construct approximately 464 linear feet of post and steel cable fence. The fence will be constructed from a powerline access road and tie into existing post and cable fence (Attachments 3, 7). The approximate future fence location is listed below:

a) Option 1 Segment 1 Start: (lat: 36.2044 / long: -114.9443).

b) Option 1 Segment 1 End: (lat: 36.2038 / long: -114.9430).

There will be an approximately 30 to 50-foot wide opening at the powerline access road, as shown on attached maps. The position and width of the opening shall be field determined by the Government in coordination with the Contractor.

A2.3 Option 2

Construct 571 linear feet of post and steel cable fence. This future fence will be constructed approximately 1 mile east of Lake Mead Blvd (SR 148) the road from which it can be accessed. The approximate future fence location is listed below:

a) Option 2 Segment 1 Start: (lat: 36.1822 / long: -114.9004).

b) Option 2 Segment 1 End: (lat: 36.1808 / long: -114.8999).

A2.4 Option 3

Construct two post and steel cable fence segments totaling approximately 2,218 linear feet.

Both segments will tie into geographic features such that vehicles cannot access the unauthorized wash around the fence segments (Attachments 5, 9).

This future fence will be located off a dirt road, south of Lake Mead Blvd across from the location of the Base Option (approximately 5 miles east of the Frenchman Mountain Trailhead) (Attachments 5, 9).

a) Option 3 Segment 1 Start: (lat: 36.1880 / long: -114.9305).

b) Option 3 Segment 1 End: (lat: 36.1874 / long: -114.9282).

c) Option 3 Segment 2 Start: (lat: 36.1872/ long: -114.9275).

d) Option 3 Segment 2 End: (lat: 36.1851/ long: -114.9237).

SECTION B – PROJECT DETAILS

B1.0 Government Furnished Materials / Information There will be no government furnished property. All materials, equipment, tools, labor, transportation, and supervision to perform the specified work will be furnished by the Contractor.

RAINBOW GARDENS POST AND CABLE FENCE – JUNE 2022 Page 3 of 8

The Government assumes NO LIABILITY for the accuracy or correctness of any information or data provided to the Contractor. Additionally, the Government assumes no liability for errors or omissions the documents provided may contain. The Contractor is responsible for verifying the accuracy of the data provided prior to submitting their proposal.

B2.0 Soil Conditions

SOILWEB an online soil survey browser developed by U.C. Davis and the Natural Resources Conservation Service (NRCS) show two project area soil types – Heleweiser-Carrizon-Teebar association (285) and the Baseline-Guardian association (228). The majority of work will be conducted in soils labeled as 228. Slightly hard subsurface soils should be expected. Coarse grain pebbles, cobbles and/or hard sandstone might be encountered in some post holes from near ground surface to final post hole depths.

B3.0 Public Access

Outdoor enthusiasts and others access and utilize the Rainbow Gardens area daily and utilize passenger vehicles, pickup trucks, ATV’s and UTV’s to do so. The Contractor should expect that some enthusiasts may try to pass through project areas during fence construction.

Note: The Base Option and Option 1 fence alignments cross under high voltage power lines.

B4.0 “Call Before You Dig”

Contractor must contact “Call Before You Dig” before installing any post and cable.

B5.0 Site Walk Prior to Mobilization

Prior to initiating any construction activities, the Contractor and Government shall meet at the site and perform a project walk to confirm fence locations, alignments, contractor equipment layouts, traffic mitigation, personnel assignments, construction schedules, payroll, payments, and administrative provisions of the contract.

B6.0 Fence Post Construction

Contractor shall construct fence to tie in with existing post and cable or into landscape features to prevent vehicular travel around the ends of the posts. Refer to Exhibits 6A and 6B for fence details.

B6.1 Post Spacing

For each fence section, post’s shall be spaced 12 feet apart (12-13 feet average).

B6.2 Post Holes

Each post hole shall be at least 16 inches in diameter and terminate at a minimum depth of 36 inches below ground surface.

If needed, heavy equipment, such as pneumatic drill or mechanized auger, is approved for use to drill the post holes.

RAINBOW GARDENS POST AND CABLE FENCE – JUNE 2022 Page 4 of 8

B6.3 Setting Posts:

Place wood post inside the hole, plumb, and back-fill the hole with the excavated materials and compact the fill materials heavily, using water, up to the ground surface.

Back-fill the hole with the excavated materials in approximately 8-inch lifts up to the ground surface. Compact each lift to approximately 90 percent of dry density using water and hand tools.

If solid rock is encountered at 24 inches or deeper, 90 lbs of quick-set concrete may be used in a manner that securely fixes the bottom of the post to the bedrock. The remainder of the hole shall be filled and compacted as described above.

Trim the top of the posts uniformly so the top of each post 46 inches above ground surface.

B6.4 Steel Cable Installation

Along the fence line on the center of the wood face, and 5 inches below the top of the wood posts drill a hole using a 1.25 inch auger bit.

The steel cable 1-inch diameter 6 x 19 EIPS Steel Core Cable shall be inserted into the holes of all posts. After the steel cable is inserted, secure with bolts and nuts on one end of the cable to the post, pull the cable until is it uniformly stretched and secure the other end of the cable permanently. Thus, each end of the cable is tightly clamped to both sides of the post.

Steel cable is properly stretched when it is springy to the touch. Fastening bolts will be welded to disrupt the steel threads to deter vandalism and secure to bolts.

B6.5 Post Reflectors

Every other post shall have reflectors mounted 6 inches below the top of post on all 4 sides.

B6.6 Fence Materials:

The Contractor shall furnish all materials, no government property will be provided. Material specification shall meet the specifications below. Material submittals will be provided to BLM to verify that materials meet required specifications. The government will inspect and approve all materials prior to installation.

7” by 9” by 8 foot grade AA reclaimed railroad ties in good condition – straight with at least three good sound sides, minimal plate wear and end splits.

1” diameter, 6 x 19 EIPS Steel Core Cable.

1” galvanized wire rope clips with saddle and nuts.

1” steel washers.

3 ¼” circular reflector, white base color.

3 ¼” circular reflector, yellow base color.

6” wide type-3 reflective tape, yellow.

30D galvanized nails (to attach reflectors).

1” by 16” galvanized All-Thread.

1” galvanized hex nut.

RAINBOW GARDENS POST AND CABLE FENCE – JUNE 2022 Page 5 of 8

B6.7 Material and Equipment - Storage, Delivery, Handling, Security

Contractor shall protect all fence material incorporated into the work from damage while in transit to the site. Contractor shall load and unload the product in such a manner that protects them from damage until installation on the project.

Contractor shall maintain all materials free of damage until final project acceptance. The Contractor is responsible for the security and maintenance of all equipment and materials used on the project.

SECTION C - PERFORMANCE OF WORK

C1.0 Equipment

All equipment must be steam cleaned or pressure washed off-site prior to arrival at the site.

All vehicles/equipment being used on this project shall be steam cleaned or pressure washed off-site (car wash or other similar site) property prior to starting the project.

C2.0 Sensitive Vegetation

Sensitive vegetation will be identified and flagged by BLM pre-construction – flagged areas will be diligently avoided by the contractor to minimize damage to sensitive vegetation.

C3.0 Ground Surface Repair

Access roads shall not be constructed along fence lines or to the job sites but travel along the fence line is permitted. No blading or scraping of the ground outside of clearly defined road limits is permitted.

Contractor will repair all ruts and scarred ground created by construction activities upon completion of fencing installation. Excess dirt from post hole digging shall be spread on road.

Course gran gravels, cobbles and boulders shall be moved to the back of the road to the backside of the fence line.

C4.0 Cleanup

All on-site trash will be contained in raven-proof containers and removed daily. All excess materials (i.e. topped railroad ties) must be removed.

All on-site trash will be kept in raven-proof containers and will be removed daily. Fencing supplies are not considered trash. Excess materials and any trash must be removed from the project site on completion of construction and disposed of in a manner, and at a location, approved by the Bureau of Land Management.

RAINBOW GARDENS POST AND CABLE FENCE – JUNE 2022 Page 6 of 8

C5.0 Excessive Heat

Excessive heat (temperatures above 90 degrees) may affect work hours; however, any changes to the schedule shall be coordinated with the Government at least one day prior to any changes to the schedule.

C6.0 Inspection and Acceptance

Regular construction inspections will be performed by a qualified Government inspector to ensure compliance with approved design drawings, specifications, and this statement of work.

The Contractor will assume liability for all work not performed per the approved design drawings and specifications. The contractor will remove, replace, or repair any work that is not in conformance with the approved drawings, specifications, and this statement of work at no additional cost to the Government.

C7.0 Project Period of Performance

The performance period of this Contract shall be 90 calendar days following the date the Government issues project Notice To Proceed:

Construction shall occur between 5:00 am to 4:30 pm, Monday through Friday, excluding Federal observed holidays.

SECTION D - ADDITIONAL TERMS AND CONDITIONS

D1.0 Environmental Training

All Contractor and Sub-Contractor personnel must complete environmental training including desert tortoise and sensitive plant awareness.

Contractor will ensure that all on-site personnel have environmental training including desert tortoise and sensitive plant awareness.

D2.0 Camping

No Camping is allowed within the Rainbow Gardens Area of Critical Environmental Concern

(ACEC).

D3.0 Hazardous Materials

No hazardous materials shall be stored or disposed of on-site. Fuel, oil, and grease needed for equipment maintenance during the working period may be stored on site where no leakage or spillage will contaminate the ground. The Contractor will be responsible for cleanup of any spilled materials. No equipment maintenance will be performed within, or near, any stream channel or waters where petroleum products or other pollutants from equipment may enter these waters.

RAINBOW GARDENS POST AND CABLE FENCE – JUNE 2022 Page 7 of 8

D4.0 Cultural Considerations

Because fragile and irreplaceable culture resources may be present in the area, project activities and any other action which causes disturbance of the earth's surface shall be limited to those areas approved by the Bureau of Land Management.

Deviations from routes flagged or shown on the drawings are not allowable without prior approval of the Bureau of Land Management. Contractor shall insure that he, his employees, or his representatives do not collect archaeological artifacts.

Should the condition of the cultural resources in the area be altered during construction due to unauthorized activity by Contractor, Contractor shall be responsible for all costs of mitigating the cultural resources involved.

If deterioration of the archaeological sites is found to be occurring during the construction phase, work on the project shall be terminated until a data recovery plan is prepared and completed in accordance with the National Historic Preservation Act.

Contractor shall immediately bring to the attention of the Bureau of Land Management all cultural resources including, but not limited to, historic and pre-historic sites or artifacts, buried artifacts, and buried features such as fire pits, burials, and house floors discovered as a result of construction operations. Contractor shall immediately suspend all activities that might harm the object(s) and shall leave such discoveries intact until instructed to proceed by the Bureau of Land Management.

Pursuant to 43 CFR 10.4(g) the Contractor must notify the Bureau of Land Management by telephone, with written confirmation, immediately upon the discovery of human remains, funerary items, sacred objects, or objects of cultural patrimony. Further, pursuant to 43 CFR 10.4(c) and (d), the Contractor must stop activities in the immediate vicinity of the discovery and protect it from construction activities for 30 days or until notified to proceed by the Bureau of Land Management.

SECTION E – SITE SAFETY

E1.0 Fire Safety

The work sites are in a dry rural desert environment. Prior to construction, the Contractor shall coordinate with the BLM Southern Nevada District Fire Management Officer at 4701 N. Torrey Pines Drive, Las Vegas, NV 89130; phone 702-515-5135, to outline fire safety requirements at the work site.

The Contractor shall take all reasonable precautions to prevent and suppress fires. In case of a fire, the Contractor shall immediately notify the nearest emergency response center (911) and the Las Vegas Interagency Communication Center at 702-515-5300. If needed, the Contractor shall require his/her employees and those of any subcontractor to work under BLM Fire Management Officials in fire-control and suppression efforts.

RAINBOW GARDENS POST AND CABLE FENCE – JUNE 2022 Page 8 of 8

Contractor shall be required to verify all materials are within specifications before placing. The contractor shall be responsible for any damages or spills resulting from the delivery of materials to the site. Surplus materials delivered to the site but not used shall not be permitted to be dumped or temporarily stored onsite, unless a container specifically designated for that purpose is in place prior to delivery and approved by the Contracting Officer.

Contractor will be responsible for the cleanup and restoration of any areas damaged as the result of improper waste disposal, including damage caused by material suppliers.

E2.0 BLM Law Enforcement

BLM Law Enforcement Emergency: 702-293-8932.

BLM Law Enforcement Non-Emergency: 702-293-8998.

ATTACHMENTS

SOW_June 2022_Rainbow Gardens Post and Cable - revised
ATTACHMENTS
Ex 1
Ex 2
Ex 3