A04_Scope_of_Work_Chickee_and_Echo.pdf

PDF 293 KB Posted

Attached to
REPLACE 3 CHICKEES AND ECHO POND DECK FOR EVERGLAD Federal contract opportunity
Solicitation number
140P5422R0001
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This scope of work document outlines the requirements for replacing three existing chickees, removing one abandoned chickee, and replacing an observation deck for Everglades National Park. The contractor will be responsible for demolishing and disposing of existing structures, installing new wood piles, aluminum deck structures, fiberglass decking, roofs, signage, benches, and other miscellaneous materials. Key locations include Hells Bay Chickee, Watson River Chickee, Shark River Chickee, removal of the Harney River Chickee, and replacing the Echo Pond observation deck. Submittals, permits, safety plans, and other pre-construction requirements are specified. The work must be done in accordance with threatened and endangered species protections and other environmental restrictions.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE 3 CHICKEES AND ECHO POND DECK FOR EVERGLAD, newest first.
File Type Posted
Sol_140P5422R0001_Amd_0001.pdf PDF
A06_2021_11_01_CHICKEE_DRAWINGS_0001.pdf PDF
Questions_0001.docx DOCX document
Site_Photos_to_Post.pdf PDF
B03_SOL_WAGE_RATES.pdf PDF
B09_QUESTIONNAIRE.pdf PDF
Sol_140P5422R0001.pdf PDF
Bid_Schedule.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-1

SCOPE OF WORK—REPLACE CHICKEES AND ECO POND DECK

PART 1 - GENERAL

1.1 SUMMARY

A. This work consists of providing all labor, materials, and equipment to remove and replace three existing chickees (Hells Bay, Watson River, Shark River), remove one abandoned-existing chickee (Harney River), and replace an observation deck (Echo Pond). Each chickee/deck is at a different location in Everglades National Park. Chickees are over-the-water pile supported structures used as campsites by visitors in the backcountry. Specific sites are:

1. Hells Bay Chickee: This work is to remove and replace an existing 500 square foot (sf) chickee. The work site is in the backcountry and only accessible by boat. Access is up the East River from Whitewater Bay. The East River has narrow (+/- 40’) and winding sections. GPS Coordinates of the site are North 25.2534° Latitude, West 80.8786° Longitude.

2. Watson River Chickee: This work is to remove and replace an existing 325 sf chickee. The work site is in the backcountry and only accessible by boat. The site is in the north end of Whitewater Bay. GPS Coordinates of the site are North 25.3326° Latitude, West 80.9807° Longitude.

3. Shark River Chickee: This work is to remove and replace an existing 325 sf chickee. The work site is in the backcountry and only accessible by boat. The work site is approximately 8 miles up the Shark River from the Gulf of Mexico. GPS Coordinates of the site are North 25.3687° Latitude, West 81.0451° Longitude.

4. Harney River Chickee: This work is to remove the remains of an old abandon 300 sf chickee.

No new chickee is to be built at this site. The work site is in the backcountry and only accessible by boat. The work site is approximately 5 miles up the Harney River from the Gulf of Mexico. GPS Coordinates of the site are North 25.4326° Latitude, West 81.0911° Longitude.

5. Echo Pond Observation Deck: This work is to remove and replace an existing 500 sf over-the-water observation deck on Echo Pond. This work site is in the Flamingo Area and is accessible by land. GPS Coordinates of the site are North 25.1401° Latitude, West -80.9366° Longitude.

B. All existing structures are visible on Google Earth.

C. NPS drawing number 160/175,278 is part of this scope of work.

1.2 DEFINITION OF BID ITEMS

A. Base Bid: The base bid shall include all work associated with replacing the chickees at Hells Bay, Watsons River, and Shark River.

B. Bid Additive: The bid additive shall include all work associated with removing the old Harney River Chickee and replacing the Eco Pond Deck.

1.3 PERMITS

A. The Government is securing permits for this project from the USACE and Florida DEP. Copies of these permits will be provided to the Contractor once available.

B. The Contractor shall follow all conditions required in these permits.

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-2

C. The Contractor shall prepare and submit all follow up paperwork required by the permits. This paperwork including but not limited to the USACE “Commencement Notification” form and the USACE “Self-Certification Statement of Compliance” form.

D. The paperwork shall be filed within the deadlines required in the permit. The Contractor shall provide the Contracting Officer copies of all paperwork at the time it is submitted to the agencies.

1.4 USE OF PREMISES AND WORK RESTRICTIONS

A. Use of Site: Limit use of the premises to the area immediately adjacent to the work site. Do not disturb the site beyond the work area.

B. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Appropriate erosion and siltation controls must be maintained during construction.

3. All equipment must be clean and free from visible debris (dirt, plant materials) prior to being brought into Everglades National Park.

4. Trimming of vegetation (Eco Pond) must be limited to the amount necessary to complete replacement of observation deck.

C. Preservation of Cultural Resources: No known archeological resources are in this area of this construction. If previously unknown archeological resources are discovered during the work of this project, the Contractor shall immediately stop work in the area of discovery and notify the Contracting Officer. An equitable adjustment will be made in accordance with the Changes clause of the contract.

D. Start of Work Notification: At least two weeks prior to the start of on-site work, the Contractor shall notify the Contracting Officer of the intended start date. This will allow Government personnel to conduct a final review the work site for any issues prior to the start of construction.

E. Threatened, Endangered and Species of Concern: The following threatened, endangered, and species of concern could be encountered in the project area: Crocodiles, Sawfish, Manatees, and Sea Turtles.

1. To avoid potential impacts to crocodiles and their nests, ground disturbing work at Eco Pond will not be carried out at this site between March and September.

2. All work shall be done in daylight hours.

3. All sightings of these species shall be reported to the Contracting Officer.

4. When a threatened or endangered species is present or observed on the work site, work shall be postponed until the individuals leave the area.

5. The Contractor shall comply with the “Standard Manatee Conditions for In-Water Work –

2011”.

6. The Contractor shall comply with National Marine Fisheries Service's “Sea Turtle and

Smalltooth Sawfish Construction Conditions,” dated March 23, 2006.

7. At the start of the project, all on-site employees shall receive training to identify threatened and endangered species which maybe encountered on the site.

F. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday. Requests for any work outside those hours, including weekends and holidays, must be submitted for approval at least 48 hours in advance. No night work shall be performed.

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-3

G. Hurricanes: The Government requires closing of operations between 48 and 72 hours of anticipated landfall of a tropical storm or hurricane as determined by the National Park Service. All project materials shall be adequately secured or removed from the site before the closure.

1.5 PRECONSTRUCTION CONFERENCE:

A. Before start of construction, the Contracting Officer will arrange a meeting with the Contractor. The meeting agenda will include the following as a minimum: correspondence procedures, designation of responsible personnel, payments to the Contractor, park rules and regulations, construction schedule, submittals, and project closeout requirements.

1.6 SUBMITTALS

A. All submittals shall be transmitted electronically in PDF or MS Word format.

B. Pre-Construction Submittals:

1. Submit a Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each phase of the work.

2. Submit a Schedule of Values showing the breakdown of the Contract. This breakdown shall include administrative costs, general condition costs, overhead, and profit in the work breakdown items and not as separate items. The Schedule of Values will also form the basis for progress payments.

3. Submit a safety plan per the accident prevention paragraph of this section. The safety plan shall include methods to follow the CDC guidelines to minimize exposure to COVID-19 for workers and the public.

C. Material Submittals:

1. Submittals are required for the following items:

a. Manufactures Literature:

1) Fiberglass Decking

2) Wood Piles

3) Composite Wood

4) Metal Roofing

5) Echo Pond Benches

b. Warranty: Provide manufacture's written warranty for:

1) Fiberglass Decking.

2) Aluminum Dock Structure.

c. Shop Drawings:

1) Aluminum deck structures and decking.

2. All material submittals shall be transmitted using National Park Service form DSC-1(CS). No action will be taken on a submittal item unless accompanied by the transmittal form.

3. Provide submittals to the Contracting Officer at least 21 days before need for approval.

4. The Government will return the submittals either approved, approved with notations, or disapproved.

D. Periodic Submittals:

1. Provide quality assurance reports per the quality assurance paragraph of this section.

2. On a weekly basis, provide the Contracting Officer with a two-week look ahead schedule of his intended activities. This schedule can be an informal handwritten paper copy.

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-4

E. Post Construction Submittals:

1. Project Record Drawings: Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue.

1.7 ACCIDENT PREVENTION

A. Before on-site work begins, submit a written accident prevention plan containing the following:

1. Identification of personnel responsible for safety at both corporate and project level including on-site personnel.

2. Emergency Response Plan including site specific emergency contact information and location of the nearest emergency room.

3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.

B. The Contractor shall follow all federal, state, and local safety and health requirements

C. The Contractor shall report all accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

D. First Aid Facilities: Provide adequate facilities for the number of employees and the type of construction at the site.

E. Personnel protective equipment: Meet requirements of NIOSH and ANSI.

1.8 QUALITY ASSURANCE

A. The Contractor shall keep daily reports of the construction activity. The form of the report is up to the Contractor, but the report shall include the following information:

1. Date

2. Project Title and Contract Number

3. Contractor’s name and On-site Superintendent’s name

4. General description of weather and ground conditions

5. Number of employees (including sub-contractors) working on-site. Employees shall be listed by job categories.

6. List of major equipment working on-site.

7. Description of work performed

8. Any issues arising including disputes, unforeseen circumstances, differing site conditions, delays, accidents, etc.

B. Reports shall be e-mailed to the Contracting Officer on a weekly basis.

1.9 CONSTRUCTION MATERIALS:

A. All materials shall be Contractor furnished from outside the park.

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-5

1.10 DISPOSAL

A. All removed material becomes the property of the Contractor and shall be disposed of outside the park, in accordance with all Federal, State, and local regulatory guidelines

1.11 FIELD VERIFICATION:

A. Field verify all new and existing dimensions affecting the work of this contract before ordering materials. Any discrepancies between construction drawings, construction specifications, and field conditions shall be brought to the attention of the Contracting Officer before work is to be performed. Any work that is performed without notifying the Contracting Officer shall be done at the Contractor's own expense.

PART 2 - PRODUCTS

2.1 WOOD PILE AND PILE WRAP

A. ASTM D25, natural taper. Sizes given are based on tip diameter.

B. Treatment: Chromated Copper Arsenate (2.50 pcf).

C. Sheeting Wrap: 60 mil polyethylene.

D. Pile Cap for Wood Piles: PVC cap, size to fit piles.

E. Nails: 316 stainless steel roofing nails.

2.2 ALUMINUM CHICKEE/DECK STRUCTURES

A. The Contractor shall provide the structure, including aluminum pile caps, to the dimensions shown on the plans and designed to meet the following criteria:

1. Deck Live Load: 100 psf (pounds per square foot)

2. Roof Live Load: 10 psf (pounds per square foot)

3. Dead Load: Per Contractors Design.

4. Winds Loads:

a. Lateral pressure applied to the side of structure: 90 psf. This load only applies to parts of the structure above the top of the deck.

b. Uplift of deck: 60 psf

c. Downward on deck: 60 psf

5. Lateral Wave Load to side of structure: 230 psf. This load only applies to parts of the structure below the top of the deck.

6. The Contractor shall be responsible for the design of the connection to the piles.

7. The Contractor deck structure shall not cause loadings on the piles that exceeds the limits of the

Government provided design as listed in these specifications.

8. The structure shall support the grating so under the live design load, the maximum deflection of the grating is less than the Span Length divided by 180.

B. Design of the piles is provided by the Government. When installed as shown and specified, the dock designer can assume each pile can be loaded to the following limits:

1. Vertical Pile Load: 20,000 pounds

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-6

2. Vertical Pile Uplift: 10,000 pounds

3. Horizontal lateral load at the top of the pile: 3,000 pounds

C. Materials: 6061 T6 Marine Grade Aluminum and 316 Stainless Fasteners.

D. Fabrication: The aluminum structure shall be manufactured by welders certified by the American Welding Association and fabricated under strict guidelines set forth by ISO 9001.

E. Warranty: The Manufacturer/Fabricator shall provide a 10-year limited warranty against defects in the dock structure.

F. Details:

1. The exterior frame of the aluminum structure shall be made with rectangular sections or c-channels with the flat side facing out so the side of the structure has a flat vertical face.

2. The aluminum frame shall have a lip approximately the height of the grating depth to cover the outer edge of the grading.

G. The manufacture of the deck structure shall be Golden Marine Systems, LLC, North Fort Myers, Florida or approved equal.

2.3 FIBERGLASS DECKING

A. Fiberglass grating with a minimum 60% open area for light transmittance. Open area calculation must include both load and cross bars.

B. Must be ADA compliant with a maximum open space between load bars of 1/2 inch.

C. Gating shall be manufactured with a barefoot friendly aqua-grit (sugar grit) to the top surface of each bar providing slip resistance.

D. Load/Deflection: Maximum deflection of 0.167 inches with a uniform distributed load of 100 pounds per square foot at 30-inch clear span.

E. All finished surfaces of fiberglass items shall be smooth, resin-rich, free of voids and without dry spots, cracks, crazes or unreinforced areas. All glass fibers shall be well covered with resin to protect against their exposure due to wear or weathering.

F. All mechanical grating clips shall be manufactured of Type 316SS (stainless steel).

G. Manufacturer’s 3-year limited warranty against defects in materials and workmanship.

H. Manufacturer shall be certified to the ISO 9001 standard.

I. Ecograte 62 Molded Grating as manufactured by Fibergrate Composite Structures or approved equal.

2.4 COMPOSITE WOOD

A. Used for facial on the aluminum structure and for fender piles.

B. Reclaimed wood and polyethylene plastic with additives for coloring and inhibiting fungal/algal growth; free from toxic chemicals.

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-7

C. Surface texture: Wood grain embossed finish

D. Moisture Shield Composite Decking or approved equal.

2.5 MISCELLANEOUS WOOD

A. Used for roofing sub deck

B. PS-20.

1. Moisture Content: 19 percent maximum (dry) at time of manufacture for lumber 2 inches or less in thickness.

2. Surfacing: S4S, unless otherwise specified.

3. Dimensions: All dimensions are nominal.

4. Species: Southern Pine.

5. Structural: No 2 Grade or better.

6. Treatment: AWPA Use category for saltwater splash (Category UC4B). Waterborne

Preservatives Alkaline Copper Quaternary or Copper Azole.

C. Plywood used for Chickee Roofing: Exterior Grade, RTD sheathing. 19/32 minimum thickness or as required by the roofing product NOA. Treatment: AWPA Use category for saltwater splash (Category UC4B).

2.6 CHICKEE ROOFING

A. 5V-crimp style metal roof panels. 26 gauge. Finish: G90 per ASTM A653 for Galvanized. Include matching peak, rake, and eave trim.

B. Underlayment: Self-adhering polymer-modified bitumen underlayment complying with ASTM D1970.

C. Flashing: 24-gage galvanized steel sheet, meeting requirements of ASTM A653 with minimum zinc coating of 1.25 ounces per square foot and 0.2 percent copper bearing, and mill phosphatized for maximum paint adherence.

2.7 CHICKEE WOODEN SIGNS

A. Sign with routed lettering approximately ¼ inch deep.

1. Materials: Wood or High Density Urethane.

2. Size: Three-inch lettering with 1-inch minimum margin between lettering and sign edges.

3. Colors: White lettering with NPS Brown (Pantone PMS 1615) background.

4. Type Style shall be NPS Rawlinson. NPS Rawlinson is a font licensed by the National Park

Service. NPS Rawlinson Font Files will be provided to the Contractor for use on this project.

The font files provided shall not be used for any other purpose.

2.8 CRUSHED LIMEROCK FILL

A. FDOT Standard Specification 911 for lime rock stabilized base (at least 97% passing the 1-1/2 inch sieve).

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-8

2.9 HARDWARE

A. Hardware including bolts, nuts, anchors, washers, screws, and nails shall be 316 stainless steel.

2.10 BENCHES FOR ECHO POND DECK

A. Bench with back, and length as shown on the drawings. Made from recycled polyethylene plastic or composite material of reclaimed wood and polyethylene plastic. Features: 2” thick solid planks, 900-pound capacity, stainless steel hardware, no arm rests, UV protected, and solid color molded through. Monarque bench or approved equal.

2.11 CHICKEE LADDER

A. Welded marine grade aluminum construction, U-shaped railings that extends above the deck, 4 steps, 2” deep flat rungs with nonslip surface. 18” minimum width, and 500 lbs. minimum load rating.

2.12 CHICKEE PORTABLE TOILET

A. Government Provided. Salvage and Store the existing portable toilet. Reinstall on the new chickee.

PART 3 - EXECUTION

3.1 DEMOLITION

A. The existing structure shall be cut up into removable pieces and transported for disposal as required in the disposal section of this scope. The existing piles shall be pulled and removed.

B. Piping and Utilities: Remove all pipe and utility structures to 2 feet below grade. Abandon in place pipe or utility structures greater than 2 feet below grade. Plug ends of abandoned utilities left in place.

C. Any holes left in the ground above water shall be filled with crushed lime rock fill to grade.

Compact fill to 90% per ASTM D698 density (Standard Proctor).

3.2 WOOD PILES AND PILE WRAP

A. Install piles to the depth shown on the drawings.

B. Piles shall be installed plumb to within 1 inch in 10'.

C. Piles shall be installed without splices.

D. In rock, the pile shall be installed in a pre-drilled hole not greater that the pile diameter.

E. Attached a cap to protect the top of each pile. Attachment shall be with a minimum of (4) #10 x 3/4” stainless steel screws or stainless steel roofing nails. The cap shall fit the piling naturally without having to modify the pile cap in any fashion to forcefully fit the pile diameter (e.g. splitting a cap to fit a larger diameter piling than the pile cap was designed to fit).

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-9

F. Install pile wrap from the mud line to 1’ above MHHW. Overlap seams a minimum of 6 inches.

Connect to the pile with stainless steel roofing nails spaced at 2-inch on center along all edges and seams.

3.3 ALUMINUM STRUCTURE

A. Install the aluminum structure per the dock suppliers approved submittal and shop drawings.

B. At all points where the aluminum structure and the treated piles touch, install 60 mil polyethylene sheeting between the two materials to prevent direct contact.

3.4 BOLTS

A. Bolt holes shall be a minimum of 1/32" to a maximum of 1/16" larger that the diameter of the bolt.

B. When installed and tightened, at least 2 full threads shall be exposed beyond the nut.

C. Washers not less than standard cut shall be placed between the wood and bolt head and between the wood and nut.

D. Minimum edge distance (edge of board to center of bolt) shall be:

1. 1.5 times the diameter of the bolt (Loading Parallel to Grain)

2. 4 times the diameter of the bolt (Loading Perpendicular to Grain)

E. Minimum end distance (end of board to center of bolt)

1. 4 times the diameter of the bolt (Loading Perpendicular to Grain)

2. 4 times the diameter of the bolt (Compression Loading Parallel to Grain)

3. 7 times the diameter of the bolt (Tension Loading Parallel to Grain)

3.5 DECKING

A. Install decking in accordance with manufacturer's instructions.

B. All field fabricated grating cuts shall be coated by the contractor in accordance with the manufacturer's instructions and approved sealers.

C. Field cut and drill fiberglass reinforced plastic products with carbide or diamond tipped bits and blades. Panels shall be installed in as large of pieces as available to minimize seams.

D. Panels shall be attached to the structure with a minimum of two clips at each end. If the panel is more than 4 feet long, intermediate rows shall be added so the spacing between rows is less than 4 feet.

3.6 ROOFING

A. Follow manufacture’s recommendations and the product NOA including installation of eave, rake and, peak trim. Roof panels shall cover the full roof length without splices. Roof nails/screws shall be a minimum 1.5 inches long.

REPLACE CHICKEES AND ECO POND DECK SCOPE OF WORK-10

3.7 LIMEROCK FILL

A. Install in 6-inch lifts. Compact fill to 90% density per ASTM D698 (Standard Proctor).

3.8 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish.

At the time of final inspection, project shall be thoroughly clean and ready for use.

B. Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.

C. If the project is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.

D. After all deficiencies have been corrected, a Letter of Acceptance will be issued.

PART 1 - GENERAL
1.1 SUMMARY
A. This work consists of providing all labor, materials, and equipment to remove and replace three existing chickees (Hells Bay, Watson River, Shark River), remove one abandoned-existing chickee (Harney River), and replace an observation deck (Echo Po...
1. Hells Bay Chickee: This work is to remove and replace an existing 500 square foot (sf) chickee. The work site is in the backcountry and only accessible by boat. Access is up the East River from Whitewater Bay. The East River has narrow (+/- 40’...
2. Watson River Chickee: This work is to remove and replace an existing 325 sf chickee. The work site is in the backcountry and only accessible by boat. The site is in the north end of Whitewater Bay. GPS Coordinates of the site are North 25.3326 ...
3. Shark River Chickee: This work is to remove and replace an existing 325 sf chickee. The work site is in the backcountry and only accessible by boat. The work site is approximately 8 miles up the Shark River from the Gulf of Mexico. GPS Coordina...
4. Harney River Chickee: This work is to remove the remains of an old abandon 300 sf chickee. No new chickee is to be built at this site. The work site is in the backcountry and only accessible by boat. The work site is approximately 5 miles up t...
5. Echo Pond Observation Deck: This work is to remove and replace an existing 500 sf over-the-water observation deck on Echo Pond. This work site is in the Flamingo Area and is accessible by land. GPS Coordinates of the site are North 25.1401 Lati...
B. All existing structures are visible on Google Earth.
C. NPS drawing number 160/175,278 is part of this scope of work.
1.2 DEFINITION OF BID ITEMS
A. Base Bid: The base bid shall include all work associated with replacing the chickees at Hells Bay, Watsons River, and Shark River.
B. Bid Option: The bid option shall include all work associated with removing the old Harney River Chickee and replacing the Eco Pond Deck.
1.3 PERMITS
A. The Government is securing permits for this project from the USACE and Florida DEP. Copies of these permits will be provided to the Contractor once available.
B. The Contractor shall follow all conditions required in these permits.
C. The Contractor shall prepare and submit all follow up paperwork required by the permits. This paperwork including but not limited to the USACE “Commencement Notification” form and the USACE “Self-Certification Statement of Compliance” form.
D. The paperwork shall be filed within the deadlines required in the permit. The Contractor shall provide the Contracting Officer copies of all paperwork at the time it is submitted to the agencies.
1.4 USE OF PREMISES AND WORK RESTRICTIONS
A. Use of Site: Limit use of the premises to the area immediately adjacent to the work site. Do not disturb the site beyond the work area.
B. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Appropriate erosion and siltation controls must be maintained during construction.
3. All equipment must be clean and free from visible debris (dirt, plant materials) prior to being brought into Everglades National Park.
4. Trimming of vegetation (Eco Pond) must be limited to the amount necessary to complete replacement of observation deck.
C. Preservation of Cultural Resources: No known archeological resources are in this area of this construction. If previously unknown archeological resources are discovered during the work of this project, the Contractor shall immediately stop work i...
D. Start of Work Notification: At least two weeks prior to the start of on-site work, the Contractor shall notify the Contracting Officer of the intended start date. This will allow Government personnel to conduct a final review the work site for an...
E. Threatened, Endangered and Species of Concern: The following threatened, endangered, and species of concern could be encountered in the project area: Crocodiles, Sawfish, Manatees, and Sea Turtles.
1. To avoid potential impacts to crocodiles and their nests, ground disturbing work at Eco Pond will not be carried out at this site between March and September.
2. All work shall be done in daylight hours.
3. All sightings of these species shall be reported to the Contracting Officer.
4. When a threatened or endangered species is present or observed on the work site, work shall be postponed until the individuals leave the area.
5. The Contractor shall comply with the “Standard Manatee Conditions for In-Water Work – 2011”.
6. The Contractor shall comply with National Marine Fisheries Service's “Sea Turtle and Smalltooth Sawfish Construction Conditions,” dated March 23, 2006.
7. At the start of the project, all on-site employees shall receive training to identify threatened and endangered species which maybe encountered on the site.
F. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday. Requests for any work outside those hours, including weekends and holidays, must be submitted for approva...
G. Hurricanes: The Government requires closing of operations between 48 and 72 hours of anticipated landfall of a tropical storm or hurricane as determined by the National Park Service. All project materials shall be adequately secured or removed fro...
1.5 PRECONSTRUCTION CONFERENCE:
A. Before start of construction, the Contracting Officer will arrange a meeting with the Contractor. The meeting agenda will include the following as a minimum: correspondence procedures, designation of responsible personnel, payments to the Contrac...
1.6 SUBMITTALS
A. All submittals shall be transmitted electronically in PDF or MS Word format.
B. Pre-Construction Submittals:
1. Submit a Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each phase of the work.
2. Submit a Schedule of Values showing the breakdown of the Contract. This breakdown shall include administrative costs, general condition costs, overhead, and profit in the work breakdown items and not as separate items. The Schedule of Values will ...
3. Submit a safety plan per the accident prevention paragraph of this section. The safety plan shall include methods to follow the CDC guidelines to minimize exposure to COVID-19 for workers and the public.
C. Material Submittals:
1. Submittals are required for the following items:
a. Manufactures Literature:
1) Fiberglass Decking
2) Wood Piles
3) Composite Wood
4) Metal Roofing
5) Echo Pond Benches
b. Warranty: Provide manufacture's written warranty for:
1) Fiberglass Decking.
2) Aluminum Dock Structure.
c. Shop Drawings:
1) Aluminum deck structures and decking.
2. All material submittals shall be transmitted using National Park Service form DSC-1(CS). No action will be taken on a submittal item unless accompanied by the transmittal form.
3. Provide submittals to the Contracting Officer at least 21 days before need for approval.
4. The Government will return the submittals either approved, approved with notations, or disapproved.
D. Periodic Submittals:
1. Provide quality assurance reports per the quality assurance paragraph of this section.
2. On a weekly basis, provide the Contracting Officer with a two-week look ahead schedule of his intended activities. This schedule can be an informal handwritten paper copy.
E. Post Construction Submittals:
1. Project Record Drawings: Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue.
1.7 ACCIDENT PREVENTION
A. Before on-site work begins, submit a written accident prevention plan containing the following:
1. Identification of personnel responsible for safety at both corporate and project level including on-site personnel.
2. Emergency Response Plan including site specific emergency contact information and location of the nearest emergency room.
3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.
B. The Contractor shall follow all federal, state, and local safety and health requirements
C. The Contractor shall report all accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
D. First Aid Facilities: Provide adequate facilities for the number of employees and the type of construction at the site.
E. Personnel protective equipment: Meet requirements of NIOSH and ANSI.
1.8 QUALITY ASSURANCE
A. The Contractor shall keep daily reports of the construction activity. The form of the report is up to the Contractor, but the report shall include the following information:
1. Date
2. Project Title and Contract Number
3. Contractor’s name and On-site Superintendent’s name
4. General description of weather and ground conditions
5. Number of employees (including sub-contractors) working on-site. Employees shall be listed by job categories.
6. List of major equipment working on-site.
7. Description of work performed
8. Any issues arising including disputes, unforeseen circumstances, differing site conditions, delays, accidents, etc.

B. Reports shall be e-mailed to the Contracting Officer on a weekly basis.

1.9 CONSTRUCTION MATERIALS:
A. All materials shall be Contractor furnished from outside the park.
1.10 DISPOSAL
A. All removed material becomes the property of the Contractor and shall be disposed of outside the park, in accordance with all Federal, State, and local regulatory guidelines
1.11 FIELD VERIFICATION:
A. Field verify all new and existing dimensions affecting the work of this contract before ordering materials. Any discrepancies between construction drawings, construction specifications, and field conditions shall be brought to the attention of the ...
PART 2 - PRODUCTS
2.1 WOOD PILE AND PILE WRAP
A. ASTM D25, natural taper. Sizes given are based on tip diameter.
B. Treatment: Chromated Copper Arsenate (2.50 pcf).
C. Sheeting Wrap: 60 mil polyethylene.
D. Pile Cap for Wood Piles: PVC cap, size to fit piles.
E. Nails: 316 stainless steel roofing nails.
2.2 ALUMINUM CHICKEE/DECK STRUCTURES
A. The Contractor shall provide the structure, including aluminum pile caps, to the dimensions shown on the plans and designed to meet the following criteria:
1. Deck Live Load: 100 psf (pounds per square foot)
2. Roof Live Load: 10 psf (pounds per square foot)
3. Dead Load: Per Contractors Design.
4. Winds Loads:
a. Lateral pressure applied to the side of structure: 90 psf. This load only applies to parts of the structure above the top of the deck.
b. Uplift of deck: 60 psf
c. Downward on deck: 60 psf
5. Lateral Wave Load to side of structure: 230 psf. This load only applies to parts of the structure below the top of the deck.
6. The Contractor shall be responsible for the design of the connection to the piles.
7. The Contractor deck structure shall not cause loadings on the piles that exceeds the limits of the Government provided design as listed in these specifications.
8. The structure shall support the grating so under the live design load, the maximum deflection of the grating is less than the Span Length divided by 180.
B. Design of the piles is provided by the Government. When installed as shown and specified, the dock designer can assume each pile can be loaded to the following limits:
1. Vertical Pile Load: 20,000 pounds
2. Vertical Pile Uplift: 10,000 pounds
3. Horizontal lateral load at the top of the pile: 3,000 pounds
C. Materials: 6061 T6 Marine Grade Aluminum and 316 Stainless Fasteners.
D. Fabrication: The aluminum structure shall be manufactured by welders certified by the American Welding Association and fabricated under strict guidelines set forth by ISO 9001.
E. Warranty: The Manufacturer/Fabricator shall provide a 10-year limited warranty against defects in the dock structure.
F. Details:
1. The exterior frame of the aluminum structure shall be made with rectangular sections or c-channels with the flat side facing out so the side of the structure has a flat vertical face.
2. The aluminum frame shall have a lip approximately the height of the grating depth to cover the outer edge of the grading.

G. The manufacture of the deck structure shall be Golden Marine Systems, LLC, North Fort Myers, Florida or approved equal.

2.3 FIBERGLASS DECKING
A. Fiberglass grating with a minimum 60% open area for light transmittance. Open area calculation must include both load and cross bars.
B. Must be ADA compliant with a maximum open space between load bars of 1/2 inch.
C. Gating shall be manufactured with a barefoot friendly aqua-grit (sugar grit) to the top surface of each bar providing slip resistance.
D. Load/Deflection: Maximum deflection of 0.167 inches with a uniform distributed load of 100 pounds per square foot at 30-inch clear span.
E. All finished surfaces of fiberglass items shall be smooth, resin-rich, free of voids and without dry spots, cracks, crazes or unreinforced areas. All glass fibers shall be well covered with resin to protect against their exposure due to wear or wea...
F. All mechanical grating clips shall be manufactured of Type 316SS (stainless steel).
G. Manufacturer’s 3-year limited warranty against defects in materials and workmanship.
H. Manufacturer shall be certified to the ISO 9001 standard.
I. Ecograte 62 Molded Grating as manufactured by Fibergrate Composite Structures or approved equal.
2.4 COMPOSITE WOOD
A. Used for facial on the aluminum structure and for fender piles.
B. Reclaimed wood and polyethylene plastic with additives for coloring and inhibiting fungal/algal growth; free from toxic chemicals.
C. Surface texture: Wood grain embossed finish
D. Moisture Shield Composite Decking or approved equal.
2.5 MISCELLANEOUS WOOD
A. Used for roofing sub deck
B. PS-20.
1. Moisture Content: 19 percent maximum (dry) at time of manufacture for lumber 2 inches or less in thickness.
2. Surfacing: S4S, unless otherwise specified.
3. Dimensions: All dimensions are nominal.
4. Species: Southern Pine.
5. Structural: No 2 Grade or better.
6. Treatment: AWPA Use category for saltwater splash (Category UC4B). Waterborne Preservatives Alkaline Copper Quaternary or Copper Azole.

C. Plywood used for Chickee Roofing: Exterior Grade, RTD sheathing. 19/32 minimum thickness or as required by the roofing product NOA. Treatment: AWPA Use category for saltwater splash (Category UC4B).

2.6 CHICKEE ROOFING
A. 5V-crimp style metal roof panels. 26 gauge. Finish: G90 per ASTM A653 for Galvanized. Include matching peak, rake, and eave trim.
B. Underlayment: Self-adhering polymer-modified bitumen underlayment complying with ASTM D1970.
C. Flashing: 24-gage galvanized steel sheet, meeting requirements of ASTM A653 with minimum zinc coating of 1.25 ounces per square foot and 0.2 percent copper bearing, and mill phosphatized for maximum paint adherence.
2.7 CHICKEE WOODEN SIGNS
A. Sign with routed lettering approximately ¼ inch deep.
1. Materials: Wood or High Density Urethane.
2. Size: Three-inch lettering with 1-inch minimum margin between lettering and sign edges.
3. Colors: White lettering with NPS Brown (Pantone PMS 1615) background.
4. Type Style shall be NPS Rawlinson. NPS Rawlinson is a font licensed by the National Park Service. NPS Rawlinson Font Files will be provided to the Contractor for use on this project. The font files provided shall not be used for any other purpose.
2.8 CRUSHED LIMEROCK FILL
A. FDOT Standard Specification 911 for lime rock stabilized base (at least 97% passing the 1-1/2 inch sieve).
2.9 HARDWARE
A. Hardware including bolts, nuts, anchors, washers, screws, and nails shall be 316 stainless steel.
2.10 BENCHES FOR ECHO POND DECK
A. Bench with back, and length as shown on the drawings. Made from recycled polyethylene plastic or composite material of reclaimed wood and polyethylene plastic. Features: 2” thick solid planks, 900-pound capacity, stainless steel hardware, no arm...
2.11 CHICKEE LADDER
A. Welded marine grade aluminum construction, U-shaped railings that extends above the deck, 4 steps, 2” deep flat rungs with nonslip surface. 18” minimum width, and 500 lbs. minimum load rating.
2.12 CHICKEE PORTABLE TOILET
A. Government Provided. Salvage and Store the existing portable toilet. Reinstall on the new chickee.
PART 3 - EXECUTION
3.1 DEMOLITION
A. The existing structure shall be cut up into removable pieces and transported for disposal as required in the disposal section of this scope. The existing piles shall be pulled and removed.
B. Piping and Utilities: Remove all pipe and utility structures to 2 feet below grade. Abandon in place pipe or utility structures greater than 2 feet below grade. Plug ends of abandoned utilities left in place.
C. Any holes left in the ground above water shall be filled with crushed lime rock fill to grade. Compact fill to 90% per ASTM D698 density (Standard Proctor).
3.2 WOOD PILES AND PILE WRAP
A. Install piles to the depth shown on the drawings.
B. Piles shall be installed plumb to within 1 inch in 10'.
C. Piles shall be installed without splices.
D. In rock, the pile shall be installed in a pre-drilled hole not greater that the pile diameter.
E. Attached a cap to protect the top of each pile. Attachment shall be with a minimum of (4) #10 x 3/4” stainless steel screws or stainless steel roofing nails. The cap shall fit the piling naturally without having to modify the pile cap in any fash...
F. Install pile wrap from the mud line to 1’ above MHHW. Overlap seams a minimum of 6 inches. Connect to the pile with stainless steel roofing nails spaced at 2-inch on center along all edges and seams.
3.3 ALUMINUM STRUCTURE
A. Install the aluminum structure per the dock suppliers approved submittal and shop drawings.
B. At all points where the aluminum structure and the treated piles touch, install 60 mil polyethylene sheeting between the two materials to prevent direct contact.
3.4 BOLTS
A. Bolt holes shall be a minimum of 1/32" to a maximum of 1/16" larger that the diameter of the bolt.
B. When installed and tightened, at least 2 full threads shall be exposed beyond the nut.
C. Washers not less than standard cut shall be placed between the wood and bolt head and between the wood and nut.
D. Minimum edge distance (edge of board to center of bolt) shall be:
1. 1.5 times the diameter of the bolt (Loading Parallel to Grain)
2. 4 times the diameter of the bolt (Loading Perpendicular to Grain)
E. Minimum end distance (end of board to center of bolt)
1. 4 times the diameter of the bolt (Loading Perpendicular to Grain)
2. 4 times the diameter of the bolt (Compression Loading Parallel to Grain)
3. 7 times the diameter of the bolt (Tension Loading Parallel to Grain)
3.5 DECKING
A. Install decking in accordance with manufacturer's instructions.
B. All field fabricated grating cuts shall be coated by the contractor in accordance with the manufacturer's instructions and approved sealers.
C. Field cut and drill fiberglass reinforced plastic products with carbide or diamond tipped bits and blades. Panels shall be installed in as large of pieces as available to minimize seams.
D. Panels shall be attached to the structure with a minimum of two clips at each end. If the panel is more than 4 feet long, intermediate rows shall be added so the spacing between rows is less than 4 feet.
3.6 ROOFING
A. Follow manufacture’s recommendations and the product NOA including installation of eave, rake and, peak trim. Roof panels shall cover the full roof length without splices. Roof nails/screws shall be a minimum 1.5 inches long.
3.7 LIMEROCK FILL
A. Install in 6-inch lifts. Compact fill to 90% density per ASTM D698 (Standard Proctor).
3.8 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. At the time of final inspection, project shall be thoroughly clean and ready for use.
B. Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.
C. If the project is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.
D. After all deficiencies have been corrected, a Letter of Acceptance will be issued.