This document is a Schedule of Items for Request for Proposal No. Contract No. for the Colorado River Sites-ADA Improvements project. The estimated start date is August 15, 2024, and the estimated completion date is December 15, 2024, with a performance time of 120 days.
The Schedule of Items lists 8 pay items, including Mobilization, Aggregate Base Course, Aggregate Surfacing, Cabana, Precast Concrete Tables and Benches, Riprap/Angular Rock, and Split Rail Cedar Fence. Estimated quantities and unit prices are provided for each item, with a total bid amount required on an "all or none" basis. The related federal contract opportunity is Solicitation Number 140L1724Q0032, issued by the Department of the Interior Bureau of Land Management Colorado Region for the CO RIVER SITES-ADA IMPROVEMENTS project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L1724Q0032_Amd_0002.pdf | ||
| Sol_140L1724Q0032_Amd_0001.pdf | ||
| B13_-Past_Performance_Questionnaire.doc | DOC document | |
| B03-Wage_Determination.pdf | ||
| A06-Locations_and_Details.pdf | ||
| Sol_140L1724Q0032.pdf | ||
| A04-SOW.pdf | ||
| A06-SOW_and_Misc.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF ITEMS
Request for Proposal No. Contract No.
Job Title: Colorado River Sites-ADA Improvements
Estimated Start Date: August 15, 2024 Estimated Completion Date: December 15, 2024 Performance Time: 120 days
Item Pay Est. Unit Unit Total No. Item Description Quantity Price Amount
1 01505(1) Mobilization 1 LS $ $
2 02730(1) Aggregate Base Course 75 Ton $ $
3 02730(2) Aggregate Surfacing 75 Ton $ $
4 10990(1) Cabana 1 EA $ $
5 10990(2) Precast Concrete Table 2 Ea $ $
6 10990(3) Precast Concrete Bench 1 EA $ $
7 10990(4) Riprap/Angular Rock 1 LS $ $
8 10990(5) Split Rail Cedar Fence 220 LF $ $
Total Bid: $ (all or none)