This statement of work outlines requirements for asphalt paving services at Canyonlands National Park in Utah. The contractor will supply and install a three-inch layer of hot mix asphalt pavement in the Murphy Point parking area to match the grade of existing surfaces. Work must be completed during a one-week window from August 14th to September 22nd, 2023, excluding Labor Day weekend, requiring full closure of the parking lot. The contractor must provide asphalt mix cut sheets, a traffic control plan, and safety plan addressing on-site supervision, emergency equipment, hazardous work phases and materials, and required personal protective equipment. Work hours are daily from 6:00am to 6:00pm Monday through Thursday. The contractor must stage from the Murphy parking lot and Green River storage area, keeping vehicles off roadway pullouts during closure. The contractor must protect vegetation and structures, and promptly address spills or leaks.

View the file

Other files for this federal contract opportunity

Other files attached to CANY-MURPHY POINT ASPHALT PAVING, newest first.
File Type Posted
Wage_Determination.pdf PDF
B08_Bid_Schedule.docx DOCX document
Sol_140P1223Q0095.pdf PDF
B08_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work: Murphy Trailhead Paving

Work Location: Canyonlands National Park, Island in the Sky District

May 2023

PROJECT SPECIFICATIONS

PART 1GENERAL
PART 1GENERAL

1.1 DESCRIPTION

A. Synopsis. Supply and install hot mix asphalt pavement for the Murphy Point parking area located at the Island in the Sky District of Canyonlands National Park. The required pavement installation includes the associated regrading and compaction of the base coarse material. A three-inch finished layer of asphalt pavement is to be installed in the areas designated in the Attachment A - plan sheet C2. The Contractor’s pavement installation is to seamlessly match the existing pavement finished grade at all asphalt cuts and to ensure the stormwater drainage slopes as indicated in the plan sheet. The Murphy Trailhead parking lot will be closed to the public for one week in order for the grading and pavement installation work to be completed in total. The road closure is a significant impact to the Park; therefore, it is imperative that the Contractor meet the scheduling requirements agreed upon.

B. Location. The Island in the Sky District is located in Canyonlands National Park by traveling 10 miles North of Moab, Utah on U.S. Highway 191, then by traveling 22 miles south along State Highway 211. The Murphy Point parking lot is accessed by traveling south an additional 9 miles along the Grand View Point Drive from the Visitor Center.

C. Period of Performance: The period of performance for this project is a one week window from 8/14/2023 to 9/22/2023, excluding the Labor Day weekend. Arrange the performance dates with COR approval.

D. Warranty: The Contractor shall warranty the materials and workmanship for one year and shall replace or repair any defective work. Defective work that is the result of the Park’s roadway bench, such as inadequate compaction or improper drainage, is not covered under this warranty.

E. Site Visit. The Park encourages potential Contractors to visit the site to determine the extent of the pavement installation in the roadways that are included in the statement of work.

F. Submittals. Provide electronic cut sheets (in PDF format) that document the hot asphalt mix salient features, and provide the trade name, name and address of the manufacturer, recommended application temperature and methods. If more than one product type is listed on the cut sheet, the product to be supplied must be noted on the cut sheet or called out on a separate sheet. This information must be included with the quote, even if an approved product is being supplied.

1. Provide cut sheets for the hot mix asphalt

2. Provide a temporary traffic control plan (TTC) for review by the Park safety officer. The traffic control plan is to be developed in accordance with Part 6, Temporary Controls of the FHWA Manual on Uniform Traffic Control Devices (MUTCD).

3. Provide a safety plan that addresses the following:

a) Name of responsible on-site supervisor to carry out the safety program.

b) Emergency Equipment. Provide a list of Contractor first aid kit locations. At a minimum the Contractor shall have at least one first aid kit on site. Provide a list of Contractor fire extinguisher locations and type. At a minimum the Contractor shall have at least one 20 pound class C fire extinguisher on site.

c) Hazardous work phases and materials. Briefly outline each phase of the work, and identify any hazardous materials, associated hazards, and the methods proposed to ensure protection of property and safety of the public, Park personnel, and the Contractor's employees.

d) Personal Protective Equipment (PPE). Provide a list of required PPE and a statement requiring PPE be worn by employees.

e) Address site and job specific safety hazards (i.e., traffic control, hot asphalt hazards, etc.).

1.2 PROJECT CONDITIONS

A. Work days and hours. The Contractor shall perform the services required under this contract from Monday through Thursday from 6:00 am until 6:00 am (during daylight hours). No work is to be performed on weekends or Federal Holidays. Any work requested outside of the designated times and dates shall first be approved by Brad Larsen, (435) 719-2152, prior to work commencing. The Contractor shall pay overtime for any employees working over 40 hours in a week as required by the Davis Bacon Act and this contract.

B. Services. Power – The Contractor shall provide for all their power needs. Cell phone coverage is spotty or non-existent within the Park. NPS Phones are not available to the Contractor. Restrooms are available for Contractor use at the Murphy Trailhead and at various locations within the Park. Food and Lodging. Commercial Lodging and Restaurants and Groceries are available in Moab at several locations. Motels can typically be fully booked in the spring and fall seasons.

C. Staging Areas. The staging areas are located at the Murphy parking lot and at the Green River storage area. No vehicles or equipment are to be parked overnight along the pull outs along the roadway during the road closure period. The Grand View Point Road shall be kept accessible to emergency vehicle traffic at all times.

D. Limits of Disturbance. The Contractor shall keep all vehicles and equipment on the roadway surface. Vegetation, structures and natural features are to be protected from work related impacts at all times. The Contractor is to keep vehicles and equipment properly maintained and to address fluid leaks and material spills promptly.

E. Existing Utilities: There are no utilities in the construction zone.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the State of Utah load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage that may result from moving of equipment.

1.3 FIELD VERIFICATION: The Contractor shall field verify all new and existing dimensions affecting the work of this contract before beginning construction or ordering products.

END OF SECTION

MURPHY ASPHALT PAVING011000-1
CANYONLANDS NATIONAL PARKSUMMARY OF WORK