Final_RFP_final.pdf

PDF 2 MB Posted

Attached to
Calibration and Metrology Laboratory Services Federal contract opportunity
Solicitation number
80GSFC19R0027
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

RFP

View the file

Other files for this federal contract opportunity

Other files attached to Calibration and Metrology Laboratory Services, newest first.
File Type Posted
Amendment_4_Final.pdf PDF
Exhibit__1_Core_Fixed_Price_List.pdf PDF
Attachment_J.pdf PDF
Amendment_3.pdf PDF
Attachment_I-Installation_Accountable_Government_Property.pdf PDF
Amendment_2.pdf PDF
Exhibit_5_-_Calibration_Historical_Data.pdf PDF
Attachment_H_-_IT_Security_Applicable_Documents_List.pdf PDF
SF1449.pdf PDF
Attachment_I_-_Installation_Accountable_Government_Property.pdf PDF
Amendment_1.pdf PDF
Attachment_H_Information_Technology_(IT)_Security_Applicable_Documents_List_final.pdf PDF
Attachment_G_IT_Security_Management_Plan_final.pdf PDF
Exhibit__3_Phase-In_Plan_Pricing_final.pdf PDF
Attachment_E_WD-CBA_final.pdf PDF
Exhibit__5_Calibration_Historical_Data_final.pdf PDF
Attachment_A_SOW_8-20_final.pdf PDF
Enclosure_2_QASP_Fixed_Price_Contract_final.pdf PDF
Attachment_C_Unit_Price_Rate_Matrix_final.pdf PDF
Attachment_B_Core_Equipment_List_final.pdf PDF
Exhibit__1_Core_Fixed_Price_List_final.pdf PDF
Attachment_F_Quality_Control_Plan_final.pdf PDF
Exhibit__4_ISO_9001-AS_9100_Requirements_final.pdf PDF
Exhibit__2_IDIQ_Representative_Task_Order_final.pdf PDF
Attachment_D_PIV_Requirements_final.pdf PDF
RFP_Cover_Letter_final.pdf PDF
SF1449_final.pdf PDF
enclosure_1_IT_Security_Management_Plan_final.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2.0 PART II - CONTINUATION OF SF 1449

2.1 GSFC 52.211-91 SCOPE OF WORK (FEB 2016)

The Contractor shall provide the personnel, materials, and facilities, except as otherwise specified in the contract, necessary to perform the work and to furnish the items specified in the

Supplies and/or Services To Be Provided clause of this contract in accordance with the Statement of Work, Attachment A, and task orders issued hereunder.

(End of Clause)

2.1.2 PRICE SCHEDULE

This is a hybrid contract with firm fixed price line items for Core services and Indefinite

Delivery Indefinite Quantity (IDIQ) type line items enabling Firm Fixed Price (FFP) task orders to be placed against the contract for services in addition to the core services. The base period and option periods, along with the applicable prices are in Attachment C- Unit Price Rate Matrix.

The Unit Price Rate Matrix (Attachment C) lists all of the equipment prices to perform services under the IDIQ portion of the SOW. The contractor shall use these item prices on the IDIQ portion of the contract.

(End of Text)

2.1.3 NFS 1852.216-78 FIRM FIXED PRICE (DEC 1988)

The total firm fixed price of this contract for core services is $ TBP

Contract Line

Item Number

(CLIN)

Core Services

Project Code and Name

Price

0001 Code 803 -- Safety Office $TBP

0002 Code 810 -- Sounding Rockets $TBP

0003 Code 820 -- Balloon Program Office $TBP

0004 Code 830 -- Aircraft Office $TBP

0005 Code 840 -- Range $TBP

0006 IDIQ (CLIN 0006-001 through 0006-2615) N/A - IDIQ

Total FFP $TBP

2.1.4 GSFC 52.216-92 MINIMUM/MAXIMUM AMOUNT OF SUPPLIES OR

SERVICES (FIXED PRICE) (APR 2008)

(a) The minimum amount of supplies or services that shall be ordered during the effective period of this contract is $500. The maximum amount of supplies or services that may be ordered during the effective period of this contract is $1.1M.

(b) All orders placed under this contract will be applied to the minimum and maximum specified above.

(c) The maximum amount may be adjusted unilaterally by the Government on an as needed basis. Historic, current, and/or projected workload requirements will be used to determine the amount of upward adjustment. In no event will the adjusted maximum amount exceed 20% of the original maximum amount.

NOTE: The above clause applies to the IDIQ portion of the contract.

3.0 PART III - CONTRACT CLAUSES

3.1 52.212-4 CONTRACT TERMS AND CONDITIONS -- COMMERCIAL ITEMS

(OCT 2018)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights --

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31

U.S.C.3727). However, when a third party makes payment (e.g., use of the Government wide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The

Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the

Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting

Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer— System for Award Management, or 52.232-34, Payment by

Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and

Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt Payment. The Government will make payment in accordance with the Prompt

Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-

5(b)/ALT I for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i) (6) (v) of this clause, and then at the rate applicable for each six-month period at fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the

Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the

Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the

Contractor shall be liable to the Government for any and all rights and remedies provided by law.

If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with

31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain

Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and

41 U.S.C. chapter 21 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws

Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause.

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments.

(9) The specification.

(t) Reserved

(u) Unauthorized Obligations.

(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End Use License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (u) (1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

3.2 ADDENDUM TO 52.212-4 – OTHER CONTRACT CLAUSES

3.2.1 FAR 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POST

CONSUMER FIBER CONTENT PAPER (MAY 2011)

3.2.2 RESERVED

3.2.3 FAR 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER

SUBCONTRACT AWARDS (OCT 2018)

3.2.4 FAR 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE

(OCT 2018)

3.2.5 FAR 52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW

INFORMATION (MAY 2011) – ALT I (MAY 2011) AND ALT II (MAY 2011)

3.2.6 FAR 52.223-10 WASTE REDUCTION PROGRAM (MAY 2011)

3.2.7 FAR 52.223-15 – ENERGY EFFICIENCY IN ENERGY-CONSUMING

PRODUCTS (DEC 2007)

3.2.8 FAR 52.228-5 INSURANCE—WORK ON A GOVERNMENT INSTALLATION

(JAN 1997)

3.2.9 FAR 52.232-18 AVAILABILITY OF FUNDS (APR 1984)

3.2.10 FAR 52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL

BUSINESS SUBCONTRACTORS (DEC 2013)

3.2.11 FAR 52.236-13 ACCIDENT PREVENTION (NOV 1991)

3.2.12 FAR 52.237-2 PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT,

AND VEGETATION (APR 1984)

3.2.13 FAR 52.237-3 CONTINUITY OF SERVICES (JAN 1991)

3.2.14 FAR 52.245-1 GOVERNMENT PROPERTY (JAN 2017)

3.2.15 FAR 52.245-9 USE AND CHARGES (APR 2012)

3.2.16 NFS 1852.203-71 REQUIREMENT TO INFORM EMPLOYEES OF

WHISTLEBLOWER RIGHTS (AUG 2014)

3.2.17 NFS 1852.223-70 SAFETY AND HEALTH (DEC 2015)

3.2.18 NFS 1852.223-72 SAFETY AND HEALTH (SHORT FORM) (JUL 2015)

3.2.19 NFS 1852.223-75 MAJOR BREACH OF SAFETY OR SECURITY (FEB 2002) - -

ALT I (FEB 2006)

3.2.20 NFS 1852.228-75 MINIMUM INSURANCE COVERAGE (OCT 1988)

3.2.21 NFS 1852.237-70 EMERGENCY EVACUATION PROCEDURES (DEC 1988)

3.2.22 NFS 1852.237-72 ACCESS TO SENSITIVE INFORMATION (JUN 2005)

3.2.23 NFS 1852.237-73 RELEASE OF SENSITIVE INFORMATION (JUN 2005)

3.2.24 NFS 1852.242-72 DENIED ACCESS TO NASA FACILITIES (OCT 2015)

3.2.25 NFS 1852.245-75 PROPERTY MANAGEMENT CHANGES (JAN 2011)

3.2.26 NFS 1852.245-78 PHYSICAL INVENTORY OF CAPITAL PERSONAL PROPERTY

(AUG 2015)

3.2.27 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

For Federal Acquisition Regulation (FAR) clauses: http://www.acquisition.gov/far

For NASA FAR Supplement (NFS) clauses:

http://www.hq.nasa.gov/office/procurement/regs/NFS.pdf

3.2.28 FAR 52.216-18 ORDERING (OCT 1995)

(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued in accordance with the Period of Performance/Effective Ordering Period specified in Clause GSFC 52.217-92.

(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.

(c) If mailed, a delivery order or task order is considered "issued" when the Government deposits the order in the mail. Orders may be issued orally, by facsimile, or by electronic commerce methods only if authorized in the Schedule.

3.2.29 FAR 52.216-19 ORDER LIMITATIONS (OCT 1995)

(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $500, the Government is not obligated to purchase, nor is the

Contractor obligated to furnish, those supplies or services under the contract.

(b) Maximum order. The Contractor is not obligated to honor -

(1) Any order for a single item in excess of $250,000;

(2) Any order for a combination of items in excess of $500,000; or

(3) A series of orders from the same ordering office within 14 days that together call for quantities exceeding the limitation in subparagraph (b) (1) or (2) of this section.

(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-

21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.

(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within fourteen (14) days after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.

3.2.30 FAR 52.216-22 INDEFINITE QUANTITY (OCT 1995)

(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the

Schedule are estimates only and are not purchased by this contract.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the “maximum.” The Government shall order at least the quantity of supplies or services designated in the Schedule as the “minimum.”

(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period;

provided, that the Contractor shall not be required to make any deliveries under this contract after one year after the contract’s effective ordering period.

NOTE: The above clause applies to the IDIQ portion of the contract.

3.2.31 FAR 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The

Contracting Officer may exercise the option by written notice to the Contractor within 30 days.

3.2.32 FAR 52.217-9 OPTION TO EXTEND THE TERM OF THE

CONTRACT (MAR 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within any time during the term of the contract; provided that the Government gives the

Contractor a preliminary written notice of its intent to extend at least 30 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 60 months.

3.2.33 NFS 1852.204-76 SECURITY REQUIREMENTS FOR UNCLASSIFIED

INFORMATION TECHNOLOGY RESOURCES (JAN 2011)

(a) The contractor shall protect the confidentiality, integrity, and availability of NASA Electronic

Information and IT resources and protect NASA Electronic Information from unauthorized disclosure.

(b) This clause is applicable to all NASA contractors and sub-contractors that process, manage, access, or store unclassified electronic information, to include Sensitive But Unclassified (SBU) information, for NASA in support of NASA's missions, programs, projects and/or institutional requirements. Applicable requirements, regulations, policies, and guidelines are identified in the

Applicable Documents List (ADL) provided as an attachment to the contract. The documents listed in the ADL can be found at: http://www.nasa.gov/offices/ocio/itsecurity/index.html. For policy information considered sensitive, the documents will be identified as such in the ADL and made available through the Contracting Officer.

(c) Definitions. (1) IT resources means any hardware or software or interconnected system or subsystem of equipment, that is used to process, manage, access, or store electronic information.

(2) NASA Electronic Information is any data (as defined in the Rights in Data clause of this contract) or information (including information incidental to contract administration, such as financial, administrative, cost or pricing, or management information) that is processed, managed, accessed or stored on an IT system(s) in the performance of a

NASA contract.

(3) IT Security Management Plan—This plan shall describe the processes and procedures that will be followed to ensure appropriate security of IT resources that are developed, processed, or used under this contract. Unlike the IT security plan, which addresses the

IT system, the IT Security Management Plan addresses how the contractor will manage personnel and processes associated with IT Security on the instant contract.

(4) IT Security Plan—this is a FISMA requirement; see the ADL for applicable requirements. The IT Security Plan is specific to the IT System and not the contract.

Within 30 days after award, the contractor shall develop and deliver an IT Security

Management Plan to the Contracting Officer; the approval authority will be included in the ADL. All contractor personnel requiring physical or logical access to NASA IT resources must complete NASA's annual IT Security Awareness training. Refer to the IT

Training policy located in the IT Security Web site at https://itsecurity.nasa.gov/policies/index.html.

(d) The contractor shall afford Government access to the Contractor's and subcontractors' facilities, installations, operations, documentation, databases, and personnel used in performance of the contract. Access shall be provided to the extent required to carry out a program of IT inspection (to include vulnerability testing), investigation and audit to safeguard against threats and hazards to the integrity, availability, and confidentiality of NASA Electronic Information or to the function of IT systems operated on behalf of NASA, and to preserve evidence of computer crime.

(e) At the completion of the contract, the contractor shall return all NASA information and IT resources provided to the contractor during the performance of the contract in accordance with retention documentation available in the ADL. The contractor shall provide a listing of all NASA

Electronic information and IT resources generated in performance of the contract. At that time, the contractor shall request disposition instructions from the Contracting Officer. The

Contracting Officer will provide disposition instructions within 30 calendar days of the contractor's request. Parts of the clause and referenced ADL may be waived by the contracting officer, if the contractor's ongoing IT security program meets or exceeds the requirements of

NASA Procedural Requirements (NPR) 2810.1 in effect at time of award. The current version of

NPR 2810.1 is referenced in the ADL. The contractor shall submit a written waiver request to the

Contracting Officer within 30 days of award. The waiver request will be reviewed by the Center

IT Security Manager. If approved, the Contractor Officer will notify the contractor, by contract modification, which parts of the clause or provisions of the ADL are waived.

(f) The contractor shall insert this clause, including this paragraph in all subcontracts that process, manage, access or store NASA Electronic Information in support of the mission of the

Agency.

3.2.34 NFS 1852.215-84 OMBUDSMAN (NOV 2011) – ALT I (JUN 2000)

(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and contractors during the preaward and postaward phases of this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman is not to diminish the authority of the contracting officer, the Source Evaluation Board, or the selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of formal contract disputes. Therefore, before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution.

(b) If resolution cannot be made by the contracting officer, interested parties may contact the installation ombudsman, whose name, address, telephone number, facsimile numbers, and e-mail address may be found at: http://prod.nais.nasa.gov/pub/pub library/Omb.html. Concerns, issues, disagreements, and recommendations which cannot be resolved at the installation may be referred to the Agency ombudsman identified at the above URL. Please do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the Contracting Officer or as specified in this document.

(c) If this is a task or delivery order contract, the ombudsman shall review complaints from contractors and ensure they are afforded a fair opportunity to be considered, consistent with the procedures of the contract.

3.2.35 NFS 1852.216-80 TASK ORDERING PROCEDURE (OCT 1996) ALT II (APR

2018)

(a) Only the Contracting Officer may issue task orders to the Contractor, providing specific authorization or direction to perform work within the scope of the contract and as specified in the schedule. The Contractor may incur costs under this contract in performance of task orders and task order modifications issued in accordance with this clause. No other costs are authorized unless otherwise specified in the contract or expressly authorized by the Contracting Officer.

(b) Prior to issuing a task order, the Contracting Officer shall provide the Contractor with the following data:

(1) A functional description of the work identifying the objectives or results desired from the contemplated task order.

(2) Proposed performance standards to be used as criteria for determining whether the work requirements have been met.

(3) A request for a task plan from the Contractor to include the technical approach, period of performance, appropriate cost information, and any other information required to determine the reasonableness of the Contractor's proposal.

(c) Within three (3) calendar days after receipt of the Contracting Officer's request, the

Contractor shall submit a task plan conforming to the request.

(d) After review and any necessary discussions, the Contracting Officer may issue a task order to the Contractor containing, as a minimum, the following:

(1) Date of the order.

(2) Contract number and order number.

(3) Functional description of the work identifying the objectives or results desired from the task order, including special instructions or other information necessary for performance of the task.

(4) Performance standards, and where appropriate, quality assurance standards.

(5) Maximum dollar amount authorized (cost and fee or price). This includes allocation of award fee among award fee periods, if applicable.

(6) Any other resources (travel, materials, equipment, facilities, etc.) authorized.

(7) Delivery/performance schedule including start and end dates.

(8) If contract funding is by individual task order, accounting and appropriation data.

(e) The Contractor shall provide acknowledgment of receipt to the Contracting Officer within three (3) calendar days after receipt of the task order.

(f) If time constraints do not permit issuance of a fully defined task order in accordance with the procedures described in paragraphs (a) through (d), a task order which includes a ceiling price may be issued.

(g) The Contracting Officer may amend tasks in the same manner in which they were issued.

(h) In the event of a conflict between the requirements of the task order and the Contractor's approved task plan, the task order shall prevail.

(i) Contractor shall submit progress reports, as required. When required, the reports shall contain, at a minimum, the following information:

(1) Contract number, task order number, and date of the order.

(2) Price and billed amounts to date for each task order.

(3) Significant issues/problems associated with the task order.

(4) Status of all task orders issued under the contract.

(5) Invoice number.

3.2.36 NFS 1852.225-70 EXPORT LICENSES (FEB 2000)

(a) The Contractor shall comply with all U.S. export control laws and regulations, including the

International Traffic in Arms Regulations (ITAR), 22 CFR Parts 120 through 130, and the Export

Administration Regulations (EAR), 15 CFR Parts 730 through 799, in the performance of this contract. In the absence of available license exemptions/exceptions, the Contractor shall be responsible for obtaining the appropriate licenses or other approvals, if required, for exports of hardware, technical data, and software, or for the provision of technical assistance.

(b) The Contractor shall be responsible for obtaining export licenses, if required, before utilizing foreign persons in the performance of this contract, including instances where the work is to be performed on-site at the Wallops Flight Facility, where the foreign person will have access to export-controlled technical data or software.

(c) The Contractor shall be responsible for all regulatory record keeping requirements associated with the use of licenses and license exemptions/exceptions.

(d) The Contractor shall be responsible for ensuring that the provisions of this clause apply to its subcontractors.

3.2.37 NFS 1852.232-77 LIMITATION OF FUNDS (Fixed Price Contract) (MAR 1989)

(a) Of the total price of items for this contract, the sum of $ TBD (core services) and $ TBD

(IDIQ) is presently available for payment and allotted to this contract. It is anticipated that from time to time additional funds will be allocated to the contract in accordance with the following schedule, until the total price of said items is allotted:

SCHEDULE FOR ALLOTMENT OF FUNDS

Date: TBD

Amount: $ TBD

Funding Total: $ TBD

(b) The Contractor agrees to perform or have performed work on the items specified in paragraph (a) of this clause up to the point at which, if this contract is terminated pursuant to the Termination for Convenience of the Government clause of this contract, the total amount payable by the Government (including amounts payable for subcontracts and settlement costs) pursuant to paragraphs (f) and (g) of that clause would, in the exercise of reasonable judgment by the Contractor, approximate the total amount at the time allotted to the contract. The

Contractor is not obligated to continue performance of the work beyond that point. The

Government is not obligated in any event to pay or reimburse the Contractor more than the amount from time to time allotted to the contract, anything to the contrary in the Termination for Convenience of the Government clause notwithstanding.

(c) (1) It is contemplated that funds presently allotted to this contract will cover the work to be performed until TBD.

(2) If funds allotted are considered by the Contractor to be inadequate to cover the work to be performed until that date, or an agreed date substituted for it, the Contractor shall notify the Contracting Officer in writing when within the next 60 days the work will reach a point at which, if the contract is terminated pursuant to the Termination for

Convenience of the Government clause of this contract, the total amount payable by the

Government (including amounts payable for subcontracts and settlement costs) pursuant to paragraphs (f) and (g) of that clause will approximate 75 percent of the total amount then allotted to the contract.

(3) (i) The notice shall state the estimate when the point referred to in paragraph (c)(2) of this clause will be reached and the estimated amount of additional funds required to continue performance to the date specified in paragraph (c)(1) of this clause, or an agreed date substituted for it.

(ii) The Contractor shall, 60 days in advance of the date specified in paragraph (c) (1) of this clause, or an agreed date substituted for it, advise the Contracting Officer in writing as to the estimated amount of additional funds required for the timely performance of the contract for a further period as may be specified in the contract or otherwise agreed to by the parties.

(4) If, after the notification referred to in paragraph (c) (3) (ii) of this clause, additional funds are not allotted by the date specified in paragraph (c) (1) of this clause, or an agreed date substituted for it, the Contracting Officer shall, upon the Contractor's written request, terminate this contract on that date or on the date set forth in the request, whichever is later, pursuant to the Termination for Convenience of the Government clause.

(d) When additional funds are allotted from time to time for continued performance of the work under this contract, the parties shall agree on the applicable period of contract performance to be covered by these funds. The provisions of paragraphs (b) and (c) of this clause shall apply to these additional allotted funds and the substituted date pertaining to them, and the contract shall be modified accordingly.

(e) If, solely by reason of the Government's failure to allot additional funds in amounts sufficient for the timely performance of this contract, the Contractor incurs additional costs or is delayed in the performance of the work under this contract, and if additional funds are allotted, an equitable adjustment shall be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of the items to be delivered, or in the time of delivery, or both.

(f) The Government may at any time before termination, and, with the consent of the

Contractor, after notice of termination, allot additional funds for this contract.

(g) The provisions of this clause with respect to termination shall in no way be deemed to limit the rights of the Government under the default clause of this contract. The provisions of this Limitation of Funds clause are limited to the work on and allotment of funds for the items set forth in paragraph (a) of this clause. This clause shall become inoperative upon the allotment of funds for the total price of said work except for rights and obligations then existing under this clause.

(h) Nothing in this clause shall affect the right of the Government to terminate this contract pursuant to the Termination for Convenience of the Government clause of this contract.

3.2.38 NFS 1852.245-71 INSTALLATION-ACCOUNTABLE GOVERNMENT

PROPERTY (JUN 2018)

(a) The Government property described in paragraph (c) of this clause may be made available to the Contractor on a no-charge basis for use in performance of this contract. This property shall be utilized only within the physical confines of the NASA installation that provided the property unless authorized by the Contracting Officer under (b)(1)(iv). Under this clause, the Government retains accountability for, and title to, the property, and the Contractor shall comply with the following:

NASA Procedural Requirements (NPR) 4100.1, NASA Materials Inventory Management

Manual;

NASA Procedural Requirements (NPR) 4200.1, NASA Equipment Management Procedural

Requirements;

NASA Procedural Requirement (NPR) 4300.1, NASA Personal Property Disposal Procedural

Requirements;

Property not recorded in NASA property systems must be managed in accordance with the requirements of the clause at FAR 52.245-1, as incorporated in this contract.

The Contractor shall establish and adhere to a system of written procedures to assure continued, effective management control and compliance with these user responsibilities. In accordance with FAR 52.245-1(h)(1) the contractor shall be liable for property lost, damaged, destroyed or stolen by the contractor or their employees when determined responsible by a NASA Property

Survey Board, in accordance with the NASA guidance in this clause.

(b)(1) The official accountable recordkeeping, financial control, and reporting of the property subject to this clause shall be retained by the Government and accomplished within NASA management information systems prescribed by the installation Supply and Equipment

Management Officer (SEMO) and Financial Management Officer. If this contract provides for the Contractor to acquire property, title to which will vest in the Government, the following additional procedures apply:

(i) The Contractor's purchase order shall require the vendor to deliver the property to the installation central receiving area.

(ii) The Contractor shall furnish a copy of each purchase order, prior to delivery by the vendor, to the installation central receiving area.

(iii) The Contractor shall establish a record for Government titled property as required by

FAR 52.245-1, as incorporated in this contract, and shall maintain that record until accountability is accepted by the Government.

(iv) Contractor use of Government property at an off-site location and off-site subcontractor use requires advance approval of the Contracting Officer and notification of the Industrial

Property Officer. The property shall be considered Government furnished and the Contractor shall assume accountability and financial reporting responsibility. The Contractor shall establish records and property control procedures and maintain the property in accordance with the requirements of FAR 52.245-1, Government Property (as incorporated in this contract), until its return to the installation. NASA Procedural Requirements related to property loans shall not apply to offsite use of property by contractors.

(2) After transfer of accountability to the Government, the Contractor shall continue to maintain such internal records as are necessary to execute the user responsibilities identified in paragraph

(a) of this clause and document the acquisition, billing, and disposition of the property. These records and supporting documentation shall be made available, upon request, to the SEMO and any other authorized representatives of the Contracting Officer.

(c) The following property and services are provided if checked:

X (1) Office space, work area space, and utilities. Government telephones are available for official purposes only.

X (2) Office furniture.

X (3) Property listed in Attachment C.

(i) If the Contractor acquires property, title to which vests in the Government pursuant to other provisions of this contract, this property also shall become accountable to the

Government upon its entry into Government records.

(ii) The Contractor shall not bring to the installation for use under this contract any property owned or leased by the Contractor, or other property that the Contractor is accountable for under any other Government contract, without the Contracting Officer's prior written approval.

X (4) Supplies from stores stock.

X (5) Publications and blank forms stocked by the installation.

X (6) Safety and fire protection for Contractor personnel and facilities.

X (7) Installation service facilities: [IT services through NASA Goddard Space Flight Center, Agency Consolidated End-user Services (ACES) contract].

X (8) Medical treatment of a first-aid nature for Contractor personnel injuries or illnesses sustained during on-site duty.

X (9) Cafeteria privileges for Contractor employees during normal operating hours.

X (10) Building maintenance for facilities occupied by Contractor personnel.

X (11) Moving and hauling for office moves, movement of large equipment, and delivery of supplies. Moving services may be provided on-site, as approved by the Contracting Officer.

3.2.39 NFS 1852.245-72 LIABILITY FOR GOVERNMENT PROPERTY FURNISHED

FOR REPAIR OR OTHER SERVICES (JAN 2011)

(a) This clause shall govern with respect to any Government property furnished to the Contractor for repair or other services that is to be returned to the Government. Such property, hereinafter referred to as “Government property furnished for servicing,” shall not be subject to FAR

52.245-1, Government Property.

(b) The official accountable recordkeeping and financial control and reporting of the property subject to this clause shall be retained by the Government. The Contractor shall maintain adequate records and procedures to ensure that the Government property furnished for servicing can be readily accounted for and identified at all times while in its custody or possession or in the custody or possession of any subcontractor.

(c) The Contractor shall be liable for any loss, damage, or destruction of the Government property furnished for servicing when caused by the Contractor's failure to exercise such care and diligence as a reasonable prudent owner of similar property would exercise under similar circumstances. The Contractor shall not be liable for loss, damage, or destruction of Government property furnished for servicing resulting from any other cause except to the extent that the loss, damage, or destruction is covered by insurance (including self-insurance funds or reserves).

(d) The Contractor shall hold the Government harmless and shall indemnify the Government against all claims for injury to persons or damage to property of the Contractor or others arising from the Contractor's possession or use of the Government property furnished for servicing or arising from the presence of that property on the Contractor's premises or property.

3.2.40 NFS 1852.245-73 FINANCIAL REPORTING OF NASA PROPERTY IN THE

CUSTODY OF CONTRACTORS (JAN 2017)

(a) The Contractor shall submit annually a NASA Form (NF) 1018, NASA Property in the

Custody of Contractors, in accordance with this clause, the instructions on the form and NFS subpart 1845.71, and any supplemental instructions for the current reporting period issued by

NASA.

(b)(1) Subcontractor use of NF 1018 is not required by this clause; however, the Contractor shall include data on property in the possession of subcontractors in the annual NF 1018.

(2) The Contractor shall mail the original signed NF 1018 directly to the cognizant NASA Center

Industrial Property Officer and a copy to the cognizant NASA Center Deputy Chief Financial

Officer, Finance, unless the Contractor uses the NF 1018 Electronic Submission System (NESS) for report preparation and submission.

(3) One copy shall be submitted (through the Department of Defense (DOD) Property

Administrator if contract administration has been delegated to DOD) to the following address:

[Insert name and address of appropriate NASA Center office.], unless the Contractor uses the NF

1018 Electronic Submission System (NESS) for report preparation and submission.

(c)(1) The annual reporting period shall be from October 1 of each year through September 30 of the following year. The report shall be submitted in time to be received by October 31st. The information contained in these reports is entered into the NASA accounting system to reflect current asset values for agency financial statement purposes. Therefore, it is essential that required reports be received no later than October 31st.

(2) Some activity may be estimated for the month in which the report is submitted, if necessary, to ensure the NF 1018 is received when due. However, contractors' procedures must document the process for developing these estimates based on planned activity such as planned purchases or NASA Form 533 (NF 533) Contractor Financial Management Report cost estimates. It should be supported and documented by historical experience or other corroborating evidence, and be retained in accordance with FAR Subpart 4.7, Contractor Records Retention. Contractors shall validate the reasonableness of the estimates and associated methodology by comparing them to the actual activity once that data is available, and adjust them accordingly. In addition, differences between the estimated cost and actual cost must be adjusted during the next reporting period. Contractors shall have formal policies and procedures, which address the validation of

NF 1018 data, including data from subcontractors, and the…