0002 page 2 WAESCHE DS FY22.pdf

PDF 200 KB Posted

Attached to
Dock- Side: USCGC WAESCHE FY22 DS Federal contract opportunity
Solicitation number
70Z080-22-Q-MECP0013
Issued by
Department of Homeland Security US Coast Guard

About this file

This document provides clarification questions and answers related to solicitation number 70Z080-22-Q-MECP0013 for dockside repairs of USCGC WAESCHE (WMSL-751) from September 20 to November 15, 2022. The solicitation seeks contractor estimates to perform work items including replacement of circuit breakers according to specifications provided, and conducting a ship service diesel generator engine overhaul while mooring the cutter pier side to limit cable requirements to 250 feet as specified in the statement of work. Bidders are instructed to provide all required technical documents, a completed price schedule, signed amendments, and notes that incomplete quotes missing these documents may not be considered.

View the file

Other files for this federal contract opportunity

Other files attached to Dock- Side: USCGC WAESCHE FY22 DS, newest first.
File Type Posted
0003 page 2 WAESCHE DS FY22.pdf PDF
SF30 Amendment 0003 08JUNE2022.pdf PDF
SF30 Amendment 0002 02JUNE2022.pdf PDF
0001 page 2 WAESCHE DS FY22.pdf PDF
SF30 Amendment 0001 19 MAY 2022.pdf PDF
Attachment 1SOSS BLANK.xls XLS spreadsheet
RFQ Ship Repair Combined Synopis WAESCHE DS.pdf PDF
Attachment 2 SPECS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

70Z080-22-Q-MECP0013

WAESCHE DOCKSIDE REPAIRS FY22

AMENDMENT 0002

Response to Questions/Requests for Clarification:

1. Work item 3, paragraph 3.5.1; Can you please provide details for the circuit breakers, OEM and model, listed in Table 1 so that replacement units could be sourced as an option?

Details for the circuit breaker are:

Manufacturer Model Rating Quantity

Siemens 15A L-5538 E82813, 3 Pole 120 V 10

Siemens 40A L-5538 E82615, 3 Pole 120 V 2

2. Work Item 2 Ship Service Diesel Generator, Engine Major Overhaul PARA NO 3.12.4

Will the cutter be able to moor ‘rescue door’ pier side in order to limit the amount of

Cable that will be needed to conduct 3.12.4?

The contractor shall create estimates based on the 250 feet of cable as per paragraph 3.12.4. For contractor’s work coordination purposes, the cutter will be moored starboard side (rescue door side) to the pier.