0001 page 2 WAESCHE DS FY22.pdf
PDF 220 KB Posted
- Attached to
- Dock- Side: USCGC WAESCHE FY22 DS Federal contract opportunity
- Solicitation number
- 70Z080-22-Q-MECP0013
About this file
This document contains an amendment to a solicitation for dock-side repairs to the USCGC WAESCHE (WMSL-751). The amendment provides responses to questions from potential offerors. It specifies that the ship's crew will only pump sewage and gray water holding tanks to low suction prior to work beginning, and will not perform double rinses of the tanks. Serial numbers are provided for two ship service diesel generators that require an engine major overhaul as part of the work items. Offerors are advised that quotes must follow instructions and include all required documents to be considered, such as a completed price schedule, statement of work, and signed amendments. The solicitation is issued by the US Coast Guard for dock-side repairs to the cutter from September 2022 to November 2022.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 0003 page 2 WAESCHE DS FY22.pdf | ||
| SF30 Amendment 0003 08JUNE2022.pdf | ||
| 0002 page 2 WAESCHE DS FY22.pdf | ||
| SF30 Amendment 0002 02JUNE2022.pdf | ||
| SF30 Amendment 0001 19 MAY 2022.pdf | ||
| Attachment 1SOSS BLANK.xls | XLS spreadsheet | |
| RFQ Ship Repair Combined Synopis WAESCHE DS.pdf | ||
| Attachment 2 SPECS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
70Z080-22-Q-MECP0013
WAESCHE DOCKSIDE REPAIRS FY22
AMENDMENT 0001
Response to Questions/Requests for Clarification:
1. WORK ITEM 2: Ship Service Diesel Generator, Engine Major Overhaul, Perform
Please provide the serial numbers for the NR1 and NR2 SSDG’s below
From WAESCHE Main Prop division:
Serial number for NR1 SSDG for WAE: NSC 00004
Serial number for NR2 SSDG for WAE: NSC 00006
2. DEFINITE ITEM NO. 7 PARA NO. 3.5 Sewage Holding Tank(s) Clean & Inspect
May Contractor(s) assume that the Ship's Crew will accomplish a double rinse of the tank prior to pumping it to low suction?
No. The Ship’s Crew will only pump the tank to low suction prior to the commencement of contractor work. A double rinse of the tank by Ship’s force will not be performed.
3. DEFINITE ITEM NO. 6 PARA NO. 3.4 Gray Water Holding Tank(s) and Lift Stations, Clean and Inspect. May Contractor(s) assume that the Ship's Crew will accomplish a double rinse of the tank(s) prior to pumping them to low suction?
Concerning Work Item No. 5, no, the Ship’s Crew will only pump the tank(s) to low suction prior to the commencement of contractor work. A double rinse of the tank(s) by Ship’s force will not be performed.