Amendment 00002.pdf

PDF 151 KB Posted

Attached to
STEADFAST Dockside Repair FY20 Federal contract opportunity
Solicitation number
70Z080-20-Q-P4548400
Issued by
Department of Homeland Security US Coast Guard

About this file

This document contains an amendment to a solicitation for the dockside repair of the USCGC Steadfast. The amendment provides responses to vendor questions to clarify the scope of work items including the renewal of tile, deck plating repairs and measurements, replacement of an oily water separator, and accommodations for crew members during repairs. Equivalent valves and fire alarm panels to those specified will not be accepted. The contractor shall complete all repair work outlined in the specification within 56 calendar days during an availability period from April 27 to June 21, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to STEADFAST Dockside Repair FY20, newest first.
File Type Posted
STEADFAST DOCKSIDE REPAIRS FY20 AWARD NOTICE.pdf PDF
Specification Rev2.pdf PDF
Chart for Answer to Question 1.pdf PDF
627-WMEC_186_3_1_-_C.pdf PDF
Amendment 00001.pdf PDF
Specification Rev1.pdf PDF
70Z080-20-Q-P4548400_STEADFAST_Solicitation.pdf PDF
Specification_STEADFAST DS.pdf PDF
STEADFAST (WMEC 210B) DS FQ2 CMD 20ER0_BLANK.xls XLS spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES 1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4 REQUISITION/PURCHASE REQ NO. PROJECT NO. (If applicable) 00002 02/05/2020 N/A

6. ISSUED BY Code 7. ADMINISTERED BY (If other than item 6.) Code N/A Alissa Gavalian USCG Surface Forces Logistics Center 300 East Main Street, Suite 550 Norfolk, VA 23510 757-628-4597

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

70Z080-20-Q-P4548400

9B. DATED (SEE ITEM 11)

15 January 2020

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers _____ is extended __X__ is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

CGC STEADFAST DS FY20

The purpose of this Amendment is following:

1. Updated specification Rev. 2 attached.

2. See below vendors’ questions and answers.

Time for the questions is extended through 07 February 2020.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

FAR (49 CFR) 53.243

1. Can you provide NAVSEA Drawing 803-1385866, Rev E, Penetration that is referenced in WORK ITEM 16:

Forepeak Tank Vent/Gooseneck, Renew section of the spec?

1. Response: We do not provide the NAVSEA drawings, we don’t have access to them.

2. Work Item 12: Scullery Deck, Renew – Is the intention of Work Item 12 to remove and replace the entire tile floor in the Scullery? Does the entire work table come out? Can you provide more detail as to what interferences should come out in preparation to crop and renew 6 square feet of deck plating?

2. Response: It is not our intention to renew all of the tile in the scullery, only in the area where the deck has to be renewed. The area in need of renewal will have a bit of the tile in the way, and some piping that may need to be renewed because it goes through the deck.

3. Work Item 14: Scullery Drains – Note 3.2 calls for 100 UT measurements on the deck plating. How does the match up with the 50 UT measurements required in 3.1 of Work Item 12? Is the intention to have 150 UT measurements on the deck plating in the Scullery?

Response: Yes, we would like to have 150 UT shots total in the area of the scullery.

4. Request clarification on Work Item – 12, Para 3.1.4, the deck is covered with Quarry tile, is it the governments intent to remove and renew all of the Quarry tile in the scullery?

Response: We only intend to renew the tiles around what has to be removed as an interference, not the entire scullery.

5. Work Item 29: Oily Water Separator; Replace – On reference drawing (618 WMEC 529-011, Rev A) a bill of materials is shown for the OWS Piping Modifications. Some of the fittings called out are standard fittings such as those listed by manufacturer “BONNEY FORGE”. Are contractors to submit pricing of only fittings supplied by the respective manufacturer shown on the drawings or can contractors price and install fittings which meet the same industry standards?

Response: They can be equivalent valves. They don’t have to be Bonney Forge.

6. Work Items 2 through 7 directly affect the ship’s habitability. Conversations with ship’s personnel indicate a crew size of ~76 persons working during the daytime, and 10 persons staying on the ship round the clock. We have provided for two three stall shower/restroom trailers to be onsite for the duration of the ship’s work items 2 through

7. Is this sufficient size for the need?

Response: Yes those will work. Please refer to SFLC Standard Spec 0000 for this information.

7. Work Item 027: A request for supply of an “or equal” fire alarm panel (Ansul vs Monitor)

Response: We will not accept an equivalent panel. It must be the one we described in the spec.

8. Work Item 29: Oily Water Separator; Replace – On reference drawing (618 WMEC 529-011, Rev A) a bill of materials is shown for the OWS Piping Modifications. Some of the fittings called out are standard fittings such as those listed by manufacturer “BONNEY FORGE”. Are contractors to submit pricing of only fittings supplied by the respective manufacturer shown on the drawings or can contractors price and install fittings which meet the same industry standards?

Response: Equivalent valves will work.