ATTACHMENT-3_Technical_Evaluation_Factors.pdf
PDF 177 KB Posted
- Attached to
- DOCKSIDE USCGC ROLLIN FRITCH Federal contract opportunity
- Solicitation number
- 70Z080-19-Q-P4529600
About this file
Attachment-3 Technical Evaluation Factors
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ATTACHMENT-1_SCHEDULE_ROLLIN_FRITCH_DS.xls | XLS spreadsheet | |
| ATTACHMENT-2_SPEC_ROLLIN_FRITCH_REV0_103118.pdf | ||
| SOLICITATION_USCGC_ROLLIN_FRITCH_013119_nmb.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment-3 Technical Evaluation Factors
USCGC ROLLIN FITCH DS2 FY19 Contract
General Ref: SFLC Standard Specification 0000, 3.2.5 Planning Document
Technical Approach
Submit a brief overview planning document using any means (computer generated, hand written, etc.) that outlines the strategy for ensuring that this requirement is completed on or before the contract completion date. The planning document shall include at least:
1) Proposed schedule, resources, completion-dates, float, and major milestones for the various tasks required to complete this contract and
2) Identify a list of items that may pose the most contract schedule risk and approach to mitigate or eliminate each risk.
Welding Ref: SFLC Standard Specification 0740, 3.1.2 Welding Documentation
Welding Certifications/Procedures
Submit welding documentation (e.g. WPSs, welder certs, etc.) in accordance with
SFLC Standard Specification 0740, specific to your internal or subcontracted staff for the weld joints that will be installed.
Preservation Applicable for critical-coated surfaces (IAW SFLC STD SPEC 0000):
Freeboard, superstructure, masts, and stacks.
All weather decks, including buoy and helicopter (flight) decks.
Bilges.
Or otherwise stated as a critical-coated surface in the work item.
Ref: SFLC Standard Specification 0000, 3.2.4 QC/QA Program
Coatings Certification Requirements
Submit a description of how you intend to meet SFLC Standard Specification
0000 coatings QC/QA requirements for this contract. Submit a plan for containment, preparation, spill response, and clean up. This plan must include the names of any subcontractors and resumes for any proposed QP1 certified painters and/or independent NACE CIP Level 3 inspectors.