ATTACHMENT-3_Technical_Evaluation_Factors.pdf

PDF 177 KB Posted

Attached to
DOCKSIDE USCGC ROLLIN FRITCH Federal contract opportunity
Solicitation number
70Z080-19-Q-P4529600
Issued by
Department of Homeland Security US Coast Guard

About this file

Attachment-3 Technical Evaluation Factors

View the file

Other files for this federal contract opportunity

Other files attached to DOCKSIDE USCGC ROLLIN FRITCH, newest first.
File Type Posted
ATTACHMENT-1_SCHEDULE_ROLLIN_FRITCH_DS.xls XLS spreadsheet
ATTACHMENT-2_SPEC_ROLLIN_FRITCH_REV0_103118.pdf PDF
SOLICITATION_USCGC_ROLLIN_FRITCH_013119_nmb.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment-3 Technical Evaluation Factors

USCGC ROLLIN FITCH DS2 FY19 Contract

General Ref: SFLC Standard Specification 0000, 3.2.5 Planning Document

Technical Approach

Submit a brief overview planning document using any means (computer generated, hand written, etc.) that outlines the strategy for ensuring that this requirement is completed on or before the contract completion date. The planning document shall include at least:

1) Proposed schedule, resources, completion-dates, float, and major milestones for the various tasks required to complete this contract and

2) Identify a list of items that may pose the most contract schedule risk and approach to mitigate or eliminate each risk.

Welding Ref: SFLC Standard Specification 0740, 3.1.2 Welding Documentation

Welding Certifications/Procedures

Submit welding documentation (e.g. WPSs, welder certs, etc.) in accordance with

SFLC Standard Specification 0740, specific to your internal or subcontracted staff for the weld joints that will be installed.

Preservation Applicable for critical-coated surfaces (IAW SFLC STD SPEC 0000):

Freeboard, superstructure, masts, and stacks.

All weather decks, including buoy and helicopter (flight) decks.

Bilges.

Or otherwise stated as a critical-coated surface in the work item.

Ref: SFLC Standard Specification 0000, 3.2.4 QC/QA Program

Coatings Certification Requirements

Submit a description of how you intend to meet SFLC Standard Specification

0000 coatings QC/QA requirements for this contract. Submit a plan for containment, preparation, spill response, and clean up. This plan must include the names of any subcontractors and resumes for any proposed QP1 certified painters and/or independent NACE CIP Level 3 inspectors.

File details come from the government source that posted it.