Amendment_0001.pdf

PDF 2 MB Posted

Attached to
Closed Circuit Video (CCV) System Federal contract opportunity
Solicitation number
70RFP319QEH000010
Issued by
Department of Homeland Security Office of Procurement Operations

About this file

Amendment 0001 to 70RFP319QEH000010

View the file

Other files for this federal contract opportunity

Other files attached to Closed Circuit Video (CCV) System, newest first.
File Type Posted
Response_to_Questions_Received_from_Industry.pdf PDF
Redacted_Brand_Name_Justification.pdf PDF
70RFP319QEH000010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

70RFP319QEH000010

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Philadelphia PA 19106 701 Market Street, Suite 3200

OPO/FPS/EACCG/HQ/NC

Office of Procurement Operations Federal Protective Service U.S. Dept. of Homeland Security NPPD/FPS/East CCG/HQ-Natl Contracts

06/03/20190001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/03/2019

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Requirement: CCV Project for 800 North Capital Street, Washington, DC

A. The purpose of Amendment 0001 is to make changes and corrections to the solicitation as a result of questions and answers received from industry.

1. Solicitation page 28, Section C.8.1, CCV Locations is deleted in its entirety and replaced with Attachment A.

2. Solicitation page 29, Section C.9, Equipment List is deleted in its entirety and replaced with Attachment B.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Peter J. Andrews

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 7

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

70RFP319QEH000010/0001

3. Incorporates three (3) floor plans for 800

North Capital Street as Attachments C,D and E.

4. Solicitation page 72, Submission of Electronic

Quotations, Second Paragraph. The first sentence is hereby corrected to read as follows:

"Quotes are due no later than 1:00 PM, Eastern

Time on June 28, 2019."

5. Contractor questions and answers are for information purposes only and do not in themselves constitute a change. Any changes to the terms and conditions of the solicitation are expressly and separately indicated as such.

6. All other terms and conditions remain unchanged.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Amendment 0001 Page 3 of 7

Attachment A

REVISED C.8.1 CCV LOCATIONS

C.8.1 CCV Locations: The contractor and FPS shall verify all camera installation locations to provide the optimal view prior to any installation. Replacement and new cameras are located as follows:

Camera 1. Panoramic on the NE comer of N Capitol (4 sensors)

Camera 2. Panoramic on the SE comer of N Capitol (4 sensors)

Camera 3. Panoramic on H St near N Capitol (4 sensors)

Camera 4. Panoramic on H St near loading dock (4 sensors)

Camera 5. Fixed camera inside loading dock (3 sensors)

Camera 6. Fixed camera at rear emergency exit and corridor for PSO OPS Center (3 sensors)

Camera 7. Panoramic at H St Parking Garage (3 sensors)

Camera 8. Panoramic at Parking Garage space 174 (3 sensors)

Camera 9. Panoramic at Parking Garage space 194 (3 sensors)

Camera 10. Panoramic at Parking Garage space 97 (3 sensors)

Camera 11. Panoramic at Parking Garage space 124 (3 sensors)

Camera 12. Panoramic at parking Garage space 22 (3 sensors)

Camera 13. Panoramic at Parking Garage space 51 (3 sensors)

Camera 14. Fixed camera at stairway# 3, P-1 level (bullet)

Camera 15. Fixed camera at stairway# 4, P-1 level (bullet)

Camera 16. Fixed camera at stairway# 3, P-2 level (bullet)

Camera 17. Fixed camera at stairway# 4, P-2 level (bullet)

Camera 18. Fixed camera at stairway# 3, street level (bullet)

Camera 19. Fixed camera at stairway# 3, P-3 level (bullet)

Camera 20. Fixed camera at stairway# 4, P-3 level (bullet)

Camera 21. Fixed camera at the loading dock platform near dumpster (bullet)

Camera 22. Fixed camera at the lower level fitness center – hallway approach (bullet)

Camera 23. Fixed camera at the lower level health unit entrance Room L80 (3 sensors) (dome)

Camera 24. Fixed camera at the lower level elevator lobby (dome)

A (3) means the 3 headed panoramic, 3 mp per camera, camera (Avigilon 9W-H3-

3MH-DP1-B - 3x 3 Megapixel WDR Day/Night, 2.8-8mm f/1.3, Pendant Dome)

A (4) means the 4 headed panoramic, 4 mp per camera, camera (Avigilon 12W-

H3- 4MH-DP1-B - 4x 3 Megapixel WDR Day/Night, 2.8-8mm f/1.3, Pendant

Dome)

The 8MP bullet includes the IR lighting onboard. (Avigilon 8.0-H4A-BO1-IR 4K

UHD 8.0MP, H4 HD Bullet, 4.3-8mm) exterior camera

Amendment 0001 Page 4 of 7

Attachment B

REVISED C.9 EQUIPMENT LIST

C.9 Equipment List – Not Comprehensive. This list is provided for reference.

Description of Work Per

Unit Measure

Avigilon HD-NVR3-PRM-84TB-NA - HD NVR3 PRM 84TB NA 2U Rack

Mnt WS2012R2

EA

Avigilon 24C-ACC6-ENT - Enterprise license for up to 45 cameras and unlimited client connections

Avigilon 8.0-H4A-BO1-IR 4K UHD 8.0MP, H4 HD Bullet, 4.3-8mm 11 EA

Avigilon H4-BO-JBOX1 Junction box for the H4A-BO-IR HD Bullet Cameras 11 EA

Avigilon 9W-H3-3MH-DP1-B - 3x 3 Megapixel WDR Day/Night, 2.8-8mm f/1.3, Pendant Dome

Avigilon 12W-H3-4MH-DP1-B - 4x 3 Megapixel WDR Day/Night, 2.8-8mm f/1.3, Pendant Dome

Avigilon CM-MT-WALL1 - Compact wall bracket for use with H3PTZ-DP and and H3-DP Pendant Dome Camera

Avigilon H4-MT-CRNR1 - Corner mount adapter for use with H4A-MT-

WALL1, H4-BO-JBOX1, H4SL, H4F, and H4 PTZ cameras

Avigilon HD-RMWS3-2MN-NA - REMOTE MONITORING WRKSTN, NA, 2 Monitor

32" 4K or better, HD monitors for NVR and workstations, must have HDMI, DVI, VGA inputs

Switch, 1 Gigabit POE 24 Port 4 EA

Switch, 10 Gigabit POE/POE+ 24 Port 1 EA

Avigilon HD-NVR3-SFPPLUS-DA SFP+ 10GbE Transceiver at each end of

Twinaxial Direct Attach Copper Cable, 3m

Wire, Cable, etc. 1 Lot

Scissors lift 1 Lot

System Programming/Paperwork/Testing/Training 1 Lot