Questions Answers Pearland.docx
DOCX document 12 KB Posted
- Attached to
- Shelter Replacement Pearland TX Federal contract opportunity
- Solicitation number
- 6973GH-21-R-00014
About this file
This document contains questions and answers regarding a federal solicitation for construction services. The Federal Aviation Administration is seeking a contractor to construct a new RTR shelter located in Pearland, Texas as described in the scope of work and attachments. Questions addressed include the distance between the air traffic control tower and RTR site, manhole specifications, responsibility for cable installation between the transformer and meter, required conduit size and type, and bore requirements under Airfield Lane. Additional tower specifications are provided including platform size, wind load rating, and tower design standards. Offers are due by December 11, 2020 and are to be submitted electronically to the point of contact.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0001-Pearland.pdf | ||
| Performance Bond.pdf | ||
| Payment Bond.pdf | ||
| 6973GH-21-R-00014.pdf | ||
| Wage Determination.pdf | ||
| Contractor Release Form.doc | DOC document | |
| Experience Information Form.pdf | ||
| LVJ RTR Specifications.pdf | ||
| LVJ RTR Construction PDFs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6973GH-21-R-00014
Pearland, TX Questions & Answers
Specifications 1.01E: What is the distance between the ATCT building from the RTR site? I’m having difficulty finding it on my aerial pictures, so I’m going to contact the SSC to find this out. How many manholes? One manhole every 1,200 feet with a full loop in each manhole for cable slack
LVJ-D-RTR-C003 Note 1 vs Numbered Legend F&I 3: Who furnished and installs cables between transformer and meter? Depends on the electrical company. I will contacting the SSC to find out who the electric company, the account number, the location of the existing transformer and see what their policy is. But it will most likely be either the electric company or us will do the installation. What size and type of conduit is required?
LVJ-D-RTR-C003 Are we to bore under Airfield Lane? If so is HDPE acceptable? HDPE schedule 80 pipe is acceptable for under Airfield Lane
LVJ-D-RTR-G004 SOW Note 1: Where are the adjacent towers? There are no adjacent towers. The contractor will need to coordinate with FAA personnel to transfer Frequencies to new tower from existing tower.
Additional Tower Specifications:
Size of platform - 6 arm mount Wind Load - 140 MPH Tower Specifications - TIA-222-H