About this file

This document contains a federal contract opportunity notice for roof replacement and site stabilization work at the Orlando Executive Airport VOR facility. The Federal Aviation Administration is seeking a firm-fixed price contract to provide all labor, materials and equipment to replace the roof and stabilize the site in accordance with the attached statement of work. Proposals are due by August 15, 2019. A pre-proposal site visit is encouraged and all questions must be submitted in writing by August 1st. Offerors must be registered in SAM and complete and return required forms by the closing date. The FAA will evaluate eligibility and technical aspects of proposals received and reserves the right to communicate with offerors during the solicitation process.

ORL VOR QA (pdf)

View the file

Other files for this federal contract opportunity

Other files attached to SCREENING INFORMATION REQUEST/REQUEST FOR OFFER ORL VOR Roof Replacement, Orlando, FL, newest first.
File Type Posted
Solicitation Amendment 6973GH-19-R-00216 0001.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
Performance Bond.pdf PDF
Payment Bond.pdf PDF
Roof Construction Drawings.pdf PDF
Experience Information Form.pdf PDF
Roof Specifications ORL-VOR-1201155.docx DOCX document
Statement of Work - Site Stabilization Services ORL VOR.pdf PDF
Solicitation Amendment 6973GH-19-R-00216 0002.pdf PDF
WAGE DETERMINATION FL20180263.pdf PDF
6973GH-19-R-00216 FINAL.pdf PDF
ORL Prebid Meeting Sign In Sheet.pdf PDF
Performance Bond.pdf PDF
Experience Information Form.pdf PDF
Solicitation Amendment 6973GH-19-R-00216 0001.pdf PDF
Roof Construction Drawings.pdf PDF
Statement of Work - Site Stabilization Services ORL VOR.pdf PDF
Payment Bond.pdf PDF
Roof Specifications ORL-VOR-1201155.docx DOCX document
WAGE DETERMINATION FL20180263.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
6973GH-19-R-00216 FINAL.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
WAGE DETERMINATION FL20180263.pdf PDF
Payment Bond.pdf PDF
Performance Bond.pdf PDF
6973GH-19-R-00216 FINAL.pdf PDF
Experience Information Form.pdf PDF
Roof Construction Drawings.pdf PDF
Roof Specifications ORL-VOR-1201155.docx DOCX document
Statement of Work - Site Stabilization Services ORL VOR.pdf PDF
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6973GH-19-R-00216, ORL site visit August 14, 2019 Questions & Answers

1. Who is responsible for the testing?

Arehna Engineering, Inc. or another Geotechnical Firm, retained on behalf of the FAA.

2. Can we directly contact the Geo-tech Firm who performed the initial geotechnical exploration?

Yes, it is encouraged. Their information can be found in the bid package provided.

3. Can the bid include alternates?

Bid as described in the Scope of Work. Alternate Bids may be submitted in addition to the Base Bid for technical evaluation from the FAA.

4. Is cold galvanizing spray acceptable to coat welds?

Yes, but welds should be kept to a minimum, and should be acid treated and neutralized prior to welding.