693JF719B000004_-_OHARA_HALL_POOL.pdf
PDF 974 KB Posted
- Attached to
- O'Hara Hall Pool Project Federal contract opportunity
- Solicitation number
- 693JF719B000004
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract_of_Offers_p.2.pdf | ||
| Abstract_of_Offers_p.1.pdf | ||
| Bid_Result.pdf | ||
| Responses_to_Questions.pdf | ||
| Amendment_2.pdf | ||
| Amendment_1.pdf | ||
| 19.05.01_USMMA_O'Hara_Hall_Pool_-_100__CD_Specifications.pdf | ||
| 19.05.01_USMMA_O'Hara_Hall_Pool_-_100__CD_Combined_Set.pdf | ||
| SOW_-_OHara_Hall_Pool_Upgrade_Construction.pdf | ||
| Picture_File.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
MMAPR520719000263
US DOTMARITIME ADMINISTRATION
1200 NEW JERSEY AVENUE SE
MAIL STOP W-28-201
WASHINGTON DC 20590-0001
MARAD-00091
MARITIME ADMINISTRATION
1200 NEW JERSEY AVENUE SE
MAIL STOP W-28-201
WASHINGTON DC 20590
NICOLE PRICE 202-366-7090
x
06/28/2019
693JF719B000004
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THE
ATTACHED STATEMENT OF WORK AND DRAWINGS.
READ ALL DOCUMENTS TO THIS SOLICITATION PRIOR TO COMPLETING AND
RETURNING ANY FORMS TO THIS OFFICE.
ENTER PRICE ON PAGE 2 IN BLACK INK OR TYPEWRITER AND FOR OPTIONS PAGE 3 BLOCK F.
A BID PACKAGE THAT FAILS TO CONTAIN THE FOLLOWING WILL RESULT IN THE BID BEING
CONSIDERED NONRESPONSIVE AND, THEREFORE, NOT BEING CONSIDERED FOR AWARD:
1. ALL REQUIRED ENTRIES IN BLOCKS 14 THRU 17, BID SCHEDULE;
2. SECTION K REPS, CERTS, & STATEMENT OF BIDDERS (UNLESS INCLUDED OR COMPLETED
ELECTRONICALLY THROUGH ONLINE REPRESENTATION AND CERTIFICATION AND AN ACTIVE SAM
REGISTRATION AT HTTPS://WWW.SAM.GOV/SAM/;
3. ALL ATTACHMENTS WHICH REQUIRE FILL-IN INFORMATION.
ENSURE THAT SF1442 IS COMPLETED, SIGNED & DATED.
ACKNOWLEDGE ALL AMENDMENTS IF APPLICABLE.
SEE SECTION L FOR SITE VISIT/PRE-BID CONFERENCE INFORMATION.
THE MAGNITUDE OF THE CONSTRUCTION IS $500,000 - $1,000,000.
THIS ACQUISITION IS RESTRICTED TO SMALL BUSINESS ONLY. APPLICABLE NAICS IS 236220.
SIZE STANDARD IS $36.5 MILLION. BIDS FROM THOSE FIRMS NOT CONSIDERED TO BE SMALL
BUSINESS WILL BE DEEMED NON-RESPONSIVE.
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 calendar days and complete it within ________________ ________________ calendar days after receiving
IAW FAR 52.111-10
07/29/2019
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
US DOTMARITIME ADMINISTRATION
OFFICE OF ACQUISITION
MAR-380
1200 NEW JERSEY AVENUE SE
MARAD-00091
MAIL STOP W-28-201
WASHINGTON DC 20590-0001
Judy Bowers
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 48
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
693JF719B000004
Delivery: 09/15/2019
Delivery Location Code: MARAD-00095
USMERCHANT MARINE ACADEMY PROCURE
US DOTMARITIME ADMINISTRATION
300 STEAMBOAT ROAD
KINGS POINT NY 11024-1699 USA
FOB: Destination
00001 Re-work of O'Hara indoor pool's mechanical room piping and equipment, ceiling repairs in accordance with all attached documents.
00002 Re-tiling of O'Hara pool's deck and pool's interior IAW attached documents.
(OPTION LINE ITEM)
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
NarineA Typewritten Text
NarineA Typewritten Text
NarineA Typewritten Text
NarineA Typewritten Text
NarineA Typewritten Text
NarineA Typewritten Text
NarineA Typewritten Text
NarineA Typewritten Text
NarineA Typewritten Text
NarineA Typewritten Text
693JF719B000004 Page 4 of 48
Table of Contents:
A. SOLICITATION/CONTRACT FORM
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2012)
52.236-5 Material and Workmanship. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.246-21 Warranty of Construction. (MAR 1994)
52.248-3 Value Engineering - Construction. (OCT 2010)
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
52.225-11 -- Buy American—Construction Materials under Trade Agreements
Buy American--Construction Materials Under Trade Agreements (May 2014)
52.236-1 Performance of Work by the Contractor (Apr 1984)
52.232-16 -- Progress Payments (Apr2012)
B. SUPPLIES OR SERVICES/PRICES
C. DESCRIPTION/SPECIFICATIONS
D. PACKAGING AND MARKING
E. INSPECTION AND ACCEPTANCE
52.223-3 Hazardous Material Identification and Material Safety Data. (JAN 1997)
52.246-12 Inspection of Construction. (AUG 1996)
F. DELIVERIES OR PERFORMANCE
52.211-13 Time Extensions. (SEP 2000)
52.247-34 F. O. B Destination. (Nov 1991)
G. CONTRACT ADMINISTRATION DATA
G.1 INVOICE REQUIREMENTS
G.2 ADDRESS OF CORRESPONDENCE
G.3 CONTRACTING OFFICER'S REPRESENTATIVE
H. SPECIAL CONTRACT REQUIREMENTS
52.225-25 Prohibition on Contracting with Entities Engaging in Sanctioned Activities Relating to
Iran--Representation and Certification. (DEC 2012)
52.242-15 -- Stop-Work Order (Aug. 1989)
52.242-14 Suspension of Work. (APR 1984)
I. CONTRACT CLAUSES
52.203-3 Gratuities. (APR 1984)
52.203-5 Covenant Against Contingent Fees. (MAY 2014)
52.203-7 Anti-Kickback Procedures. (MAY 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010)
52.203-13 Contractor Code of Business Ethics and Conduct. (APR 2010)
52.204-7 System for Award Management. ( JUL 2013)
52.204-9 Personal Identity Verification of Contractor Personnel. (JAN 2011)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUL 2013)
52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)
52.214-3 Amendments to Invitations for Bids
52.214-4 False Statements in Bids
52.214-5 Submission of Bids
52.214-6 Explanation to Prospective Bidders
693JF719B000004 Page 5 of 48
52.214-7 Late Submissions, Modifications, and Withdrawals of Bids
52.214-12 Preparation of Bids
52.214-15 Period for Acceptance of Bids
52.214-18 Preparation of Bids – Construction
52.214-19 Contract Award -- Sealed Bidding – Construction
52.215-2 Audit and Records - Negotiation. (OCT 2010)
52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997)
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011)
52.219-14 Limitations on Subcontracting (Nov 2011)
52.222-3 Convict Labor. (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation. (MAY 2014)
52.222-6 Construction Rate Requirements (MAY 2014)
52.222-7 Withholding of Funds. (MAY 2014)
52.222-8 Payrolls and Basic Records. (MAY2014)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (MAY 2014)
52.222-12 Contract Termination - Debarment. (MAY 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.
(MAY2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)
52.223-6 Drug-Free Workplace. (MAY 2001)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)
52.223-19 Compliance with Environmental Management Systems. (May 2011)
52.224-1 Privacy Act Notification. (APR 1984)
52.224-2 Privacy Act. (APR 1984)
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
52.227-1 Authorization and Consent. (DEC 2007)
52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007)
52.227-17 Rights in Data--Special Works. (DEC 2007)
52.228-3 Workers' Compensation Insurance (Defense Base Act). (JULY 2014)
52.228-5 Insurance - Work on a Government Installation. (JAN 1997)
52.228-14 Irrevocable Letter of Credit. (NOV 2014)
52.229-3 Federal, State, and Local Taxes. (FEB 2013)
52.229-4 Federal, State, and Local Taxes (State and Local Adjustments). (FEB 2013)
52.232-12 Advance Payments. (MAY 2001)
52.232-18 Availability of Funds. (APR 1984)
52.232-23 Assignment of Claims. (MAY 2014)
52.232-24 Prohibition of Assignment of Claims. (MAY 2014)
52.232-27 Prompt Payment For Construction Contracts. (MAY 2014)
52.232-33 Payment by Electronic Funds Transfer – System for Award Management. (JULY 2013)
52.232-36 Payment by Third Party. (MAY 2014)
52.232-37 Multiple Payment Arrangements. (MAY 1999)
52.232-40 Providing Accelerated Payment to Small Business Subcontractors (DEC 2013)
52.233-1 Disputes. (MAY 2014)
52.233-3 Protest after Award. (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)
52.236-2 Differing Site Conditions. (APR 1984)
693JF719B000004 Page 6 of 48
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR
1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-14 Availability and Use of Utility Services. (APR 1984)
52.236-15 Schedules for Construction Contracts. (APR 1984)
52.236-16 Quantity Surveys. (APR 1984)
52.236-17 Layout of Work. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.236-26 Preconstruction Conference. (FEB 1995)
52.242-1 Notice of Intent to Disallow Costs. (APR 1984)
52.242-13 Bankruptcy. (JUL 1995)
52.243-4 Changes. (JUN 2007)
52.243-5 Changes and Changed Conditions. (APR 1984)
52.245-1 Government Property. (APR 2012)
52.245-9 Use and Charges. (APR 2012)
52.247-64 Preference for Privately Owned U.S.-Flag Commercial Vessels. (FEB 2006)
52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012)
52.249-10 Default (Fixed-Price Construction). (APR 1984)
52.250-1 Indemnification Under Public Law 85-804. (APR 1984)
52.253-1 Computer Generated Forms. (JAN 1991)
52.209-11 – Representation by Corporations Regarding Delinquent Tax Liability or a Felony
Conviction under any Federal Law…………………………………………………………………………..28
52.244-2 Subcontracts (OCT 2010)
52.228-1 Bid Guarantee (Sep 1996)
52.228-15 Performance and Payment Bonds - Construction. (OCT 2010)
52.243-7 Notification of Changes. (APR 1984)
52.252-6 Authorized Deviations in Clauses. (APR 1984)
Insurance Limits (Local Clause)
J. LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
K. REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS
52.204-8 Annual Representations and Certifications (DEC 2014)
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for
Construction. (FEB 1999)
52.222-27 Affirmative Action Compliance Requirements for Construction. (APR2015)
52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014)
52.222-50 Combating Trafficking in Persons. (MARCH 2015)
52.222-54 Employment Eligibility Verification. (AUG 2013)
L. INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
52.214-34 Submission of Offers in the English Language. (APR 1991) 52.214-35 Submission of Offers in U.S.Currency. (APR 1991) 52.233-2 Service of Protest.(SEP 2006)
L.1 1NSTRUCTION TO OFFERORS
52.216-1--Type of Contract (Apr 1984)
M. EVALUATION FACTORS FOR AWARD
APPENDIX 1 (DOL Davis-Bacon Act for Wage Determination……………………………………………...36
693JF719B000004 Page 7 of 48
A. SOLICITATION/CONTRACT FORM
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://farsite.hill.af.mil
(End of clause)
52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2012)
52.236-5 Material and Workmanship. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.246-21 Warranty of Construction. (MAR 1994)
52.248-3 Value Engineering - Construction. (OCT 2010)
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than September 15, 2019 after receiving notice to proceed. The time stated for completion shall include final cleanup of the premises.
52.225-11 -- Buy American—Construction Materials under Trade Agreements.
Buy American--Construction Materials Under Trade Agreements (May 2014)
(a) Definitions. As used in this clause--
“Caribbean Basin country construction material” means a construction material that--
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is— http://farsite.hill.af.mil/
693JF719B000004 Page 8 of 48
(i) A commercial item (as defined in paragraph (1) of the definition at FAR
2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.
However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material
(whether or not such costs are paid to a domestic firm), and any applicable duty
(whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit.
Cost of components does not include any costs associated with the manufacture of the construction material.
“Designated country” means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement country
(Armenia, Aruba, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech
Republic, Denmark. Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Netherlands, Norway, Poland, Portugal, 693JF719B000004 Page 9 of 48
Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, or United Kingdom);
(2) A Free Trade Agreement country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the
Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
“Designated country construction material” means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United
States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic: or
(ii) The construction material is a COTS item.
“Free Trade Agreement country construction material means” a construction material that--
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
693JF719B000004 Page 10 of 48
“Foreign construction material” means a construction material other than a domestic construction material.
“Least developed country construction material” means a construction material that--
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
“United States” means the 50 States, the District of Columbia, and outlying areas.
“WTO GPA country construction material” means a construction material that--
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.50-5(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.
(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:_____none_______________ (4) The Contracting
Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that--
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the
693JF719B000004 Page 11 of 48
Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the
United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for
Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph
(d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such
693JF719B000004 Page 12 of 48 determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the
Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy
American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of measure Quantity Price (dollars) *
Item 1
Foreign construction material
Domestic construction material
Item 2
Foreign construction material
Domestic construction material
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information. ]
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
693JF719B000004 Page 13 of 48
52.236-1 Performance of Work by the Contractor (Apr 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least fifty-one (51) percent of the total amount of work to be performed under the contract.
This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
(End of Clause)
52.232-16 -- Progress Payments (APR 2012)
The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly in amounts of $2,500 or more approved by the Contracting Officer, under the following conditions:
(a) Computation of amounts.
(1) Unless the Contractor requests a smaller amount, the Government will compute each progress payment as 80 percent of the Contractor’s total costs incurred under this contract whether or not actually paid, plus financing payments to subcontractors (see paragraph (j) of this clause), less the sum of all previous progress payments made by the Government under this contract. The Contracting Officer will consider cost of money that would be allowable under FAR 31.205-10 as an incurred cost for progress payment purposes.
(2) The amount of financing and other payments for supplies and services purchased directly for the contract are limited to the amounts that have been paid by cash, check, or other forms of payment, or that are determined due will be paid to subcontractors--
(i) In accordance with the terms and conditions of a subcontract or invoice; and
(ii) Ordinarily within 30 days of the submission of the Contractor’s payment request to the Government.
(3) The Government will exclude accrued costs of Contractor contributions under employee pension plans until actually paid unless--
(i) The Contractor’s practice is to make contributions to the retirement fund quarterly or more frequently; and
(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor’s total costs for progress payments until paid).
693JF719B000004 Page 14 of 48
(4) The Contractor shall not include the following in total costs for progress payment purposes in paragraph (a)(1) of this clause:
(i) Costs that are not reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices.
(ii) Costs incurred by subcontractors or suppliers.
(iii) Costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.
(iv) Payments made or amounts payable to the subcontractors or suppliers, except for--
(A) completed work, including partial deliveries, to which the
Contractor has acquired title; and
(B) Work under cost-reimbursement or time-and-material subcontracts to which the Contractor has acquired title.
(5) The amount of unliquidated progress payments may exceed neither (i) the progress payments made against incomplete work (including allowable unliquidated progress payments to subcontractors) nor (ii) the value, for progress payment purposes, of the incomplete work. Incomplete work shall be considered to be the supplies and services required by this contract, for which delivery and invoicing by the Contractor and acceptance by the Government are incomplete.
(6) The total amount of progress payments shall not exceed 80 percent of the total contract price.
(7) If a progress payment or the unliquidated progress payments exceed the amounts permitted by subparagraphs (a)(4) or (a)(5) above, the Contractor shall repay the amount of such excess to the Government on demand.
(8) Notwithstanding any other terms of the contract, the Contractor agrees not to request progress payments in dollar amounts of less than $2,500. The Contracting
Officer may make exceptions.
(9) The costs applicable to items delivered, invoiced, and accepted shall not include costs in excess of the contract price of the items.
(b) Liquidation. Except as provided in the Termination for Convenience of the Government clause, all progress payments shall be liquidated by deducting from any payment under this contract, other than advance or progress payments, the unliquidated progress payments, or 80 percent of the amount invoiced, whichever is less. The Contractor shall repay to the
Government any amounts required by a retroactive price reduction, after computing
693JF719B000004 Page 15 of 48 liquidation’s and payments on past invoices at the reduced prices and adjusting the unliquidated progress payments accordingly. The Government reserves the right to unilaterally change from the ordinary liquidation rate to an alternate rate when deemed appropriate for proper contract financing.
(c) Reduction or suspension. The Contracting Officer may reduce or suspend progress payments, increase the rate of liquidation, or take a combination of these actions, after finding on substantial evidence any of the following conditions:
(1) The Contractor failed to comply with any material requirement of this contract
(which includes paragraphs (f) and (g) below).
(2) Performance of this contract is endangered by the Contractor’s --
(i) Failure to make progress; or
(ii) Unsatisfactory financial condition.
(3) Inventory allocated to this contract substantially exceeds reasonable requirements.
(4) The Contractor is delinquent in payment of the costs of performing this contract in the ordinary course of business.
(5) The fair value of the undelivered work is less than the amount of unliquidated progress payments for that work.
(6) The Contractor is realizing less profit than that reflected in the establishment of any alternate liquidation rate in paragraph (b) above, and that rate is less than the progress payment rate stated in subparagraph (a)(1) above.
(d) Title.
(1) Title to the property described in this paragraph (d) shall vest in the Government.
Vestiture shall be immediately upon the date of this contract, for property acquired or produced before that date. Otherwise, vestiture shall occur when the property is or should have been allocable or properly chargeable to this contract.
(2) “Property,” as used in this clause, includes all of the below-described items acquired or produced by the Contractor that are or should be allocable or properly chargeable to this contract under sound and generally accepted accounting principles and practices.
(i) Parts, materials, inventories, and work in process;
(ii) Special tooling and special test equipment to which the Government is to acquire title;
693JF719B000004 Page 16 of 48
(iii) Nondurable (i.e., noncapital) tools, jigs, dies, fixtures, molds, patterns, taps, gauges, test equipment, and other similar manufacturing aids, title to which would not be obtained as special tooling under subparagraph (ii) above;
and
(iv) Drawings and technical data, to the extent the Contractor or subcontractors are required to deliver them to the Government by other clauses of this contract.
(3) Although title to property is in the Government under this clause, other applicable clauses of this contract; e.g., the termination clauses, shall determine the handling and disposition of the property.
(4) The Contractor may sell any scrap resulting from production under this contract without requesting the Contracting Officer’s approval, but the proceeds shall be credited against the costs of performance.
(5) To acquire for its own use or dispose of property to which title is vested in the
Government under this clause, the Contractor must obtain the Contracting Officer’s advance approval of the action and the terms. The Contractor shall
(i) exclude the allocable costs of the property from the costs of contract performance, and
(ii) repay to the Government any amount of unliquidated progress payments allocable to the property. Repayment may be by cash or credit memorandum.
(6) When the Contractor completes all of the obligations under this contract, including liquidation of all progress payments, title shall vest in the Contractor for all property
(or the proceeds thereof) not --
(i) Delivered to, and accepted by, the Government under this contract; or
(ii) Incorporated in supplies delivered to, and accepted by, the Government under this contract and to which title is vested in the Government under this clause.
(7) The terms of this contract concerning liability for Government-furnished property shall not apply to property to which the Government acquired title solely under this clause.
(e) Risk of loss. Before delivery to and acceptance by the Government, the Contractor shall bear the risk of loss for property, the title to which vests in the Government under this clause, except to the extent the Government expressly assumes the risk. The Contractor shall repay the Government an amount equal to the unliquidated progress payments that are based on costs allocable to property that is lost (see 45.101).
693JF719B000004 Page 17 of 48
(f) Control of costs and property. The Contractor shall maintain an accounting system and controls adequate for the proper administration of this clause.
(g) Reports and access to records.
(1) The Contractor shall promptly furnish reports, certificates, financial statements, and other pertinent information (including estimates to complete) reasonably requested by the Contracting Officer for the administration of this clause. Also, the Contractor shall give the Government reasonable opportunity to examine and verify the
Contractor’s books, records, and accounts.
(2) The Contractor shall furnish estimates to complete that have been developed or updated within six months of the date of the progress payment request. The estimates to complete shall represent the Contractor’s best estimate of total costs to complete all remaining contract work required under the contract. The estimates shall include sufficient detail to permit Government verification.
(3) Each Contractor request for progress payment shall:
(i) Be submitted on Standard Form 1443, Contractor’s Request for Progress
Payment, or the electronic equivalent as required by agency regulations, in accordance with the form instructions and the contract terms; and
(ii) Include any additional supporting documentation requested by the
Contracting Officer.
(h) Special terms regarding default. If this contract is terminated under the Default clause,
(i) the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments and
(ii) title shall vest in the Contractor, on full liquidation of progress payments, for all property for which the Government elects not to require delivery under the Default clause. The Government shall be liable for no payment except as provided by the Default clause.
(i) Reservations of rights.
(1) No payment or vesting of title under this clause shall—
(i) Excuse the Contractor from performance of obligations under this contract;
or
(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.
693JF719B000004 Page 18 of 48
(2) The Government’s rights and remedies under this clause—
(i) Shall not be exclusive but rather shall be in addition to any other rights and remedies provided by law or this contract; and
(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.
(j) Financing payments to subcontractors. The financing payments to subcontractors mentioned in paragraphs (a)(1) and (a)(2) of this clause shall be all financing payments to subcontractors or divisions, if the following conditions are met:
(1) The amounts included are limited to—
(i) The unliquidated remainder of financing payments made; plus
(ii) Any unpaid subcontractor requests for financing payments.
(2) The subcontract or interdivisional order is expected to involve a minimum of approximately 6 months between the beginning of work and the first delivery, or, if the subcontractor is a small business concern, 4 months.
(3) If the financing payments are in the form or progress payments, the terms of the subcontract or interdivisional order concerning progress payments --
(i) Are substantially similar to the terms of the clause for any subcontractor that is a large business concern, or that clause with its Alternate I for any subcontractor that is a small business concern;
(ii) Are at least as favorable to the Government as the terms of this clause;
(iii) Are not more favorable to the subcontractor or division than the terms of this clause are to the Contractor;
(iv) Are in conformance with the requirements of FAR 32.504(e); and
(v) Subordinate all subcontractor rights concerning property to which the
Government has title under the subcontract to the Government’s right to require delivery of the property to the Government if --
(A) The Contractor defaults; or
(B) The subcontractor becomes bankrupt or insolvent.
693JF719B000004 Page 19 of 48
(4) If the financing payments are in the form of performance-based payments, the terms of the subcontract or interdivisional order concerning payments—
(i) Are substantially similar to the Performance-Based Payments clause at FAR
52.232-32 and meet the criteria for, and definition of, performance-based payments in FAR Part 32;
(ii) Are in conformance with the requirements of FAR 32.504(f); and
(iii) Subordinate all subcontractor rights concerning property to which the
Government has title under the subcontract to the Government’s right to require delivery of the property to the Government if—
(A) The Contractor defaults; or
(B) The subcontractor becomes bankrupt or insolvent.
(5) If the financing payments are in the form of commercial item financing payments, the terms of the subcontract or interdivisional order concerning payments—
(i) Are constructed in accordance with FAR 32.206(c) and included in a subcontract for a commercial item purchase that meets the definition and standards for acquisition of commercial items in FAR Part 2 and 12;
(ii) Are in conformance with the requirements of FAR 32.504(g); and
(iii) Subordinate all subcontractor rights concerning property to which the
Government has title under the subcontract to the Government’s right to require delivery of the property to the Government if—
(A) The Contractor defaults; or
(B) The subcontractor becomes bankrupt or insolvent.
(6) If financing is in the form of progress payments, the progress payment rate in the subcontract is the customary rate used by the contracting agency, depending on whether the subcontractor is or is not a small business concern.
(7) Concerning any proceeds received by the Government for property to which title has vested in the Government under the subcontract terms, the parties agree that the proceeds shall be applied to reducing any unliquidated financing payments by the
Government to the Contractor under this contract.
(8) If no unliquidated financing payments to the Contractor remain, but there are unliquidated financing payments that the Contractor has made to any subcontractor, the Contractor shall be subrogated to all the rights the Government obtained through
693JF719B000004 Page 20 of 48 the terms required by this clause to be in any subcontract, as if all such rights had been assigned and transferred to the Contractor.
(9) To facilitate small business participation in subcontracting under this contract, the
Contractor shall provide financing payments to small business concerns, in conformity with the standards for customary contract financing payments stated in Subpart 32.113.
The Contractor shall not consider the need for such financing payments as a handicap or adverse factor in the award of subcontracts.
(k) Limitations on undefinitized contract actions. Notwithstanding any other progress payment provisions in this contract, progress payments may not exceed 80 percent of costs incurred on work accomplished under undefinitized contract actions. A “contract action” is any action resulting in a contract, as defined in Subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes. This limitation shall apply to the costs incurred, as computed in accordance with paragraph (a) of this clause, and shall remain in effect until the contract action is definitized. Costs incurred which are subject to this limitation shall be segregated on Contractor progress payment requests and invoices from those costs eligible for higher progress payment rates. For purposes of progress payment liquidation, as described in paragraph (b) of this clause, progress payments for undefinitized contract actions shall be liquidated at 80 percent of the amount invoiced for work performed under the undefinitized contract action as long as the contract action remains undefinitized.
The amount of unliquidated progress payments for undefinitized contract actions shall not exceed 80 percent of the maximum liability of the Government under the undefinitized contract action or such lower limit specified elsewhere in the contract. Separate limits may be specified for separate actions.
(l) Due date. The designated payment office will make progress payments on the _30th_____ day after the designated billing office receives a proper progress payment request. In the event that the Government requires an audit or other review of a specific progress payment request to ensure compliance with the terms and conditions of the contract, the designated payment office is not compelled to make a payment by the specified due date. Progress payments are considered contract financing and are not subject to the interest penalty provisions of the
Prompt Payment Act.
(m) Progress payments under indefinite-delivery contracts. The Contractor shall account for and submit progress payment requests under individual orders as if the order constituted a separate contract, unless otherwise specified in this contract.
693JF719B000004 Page 21 of 48
B. SUPPLIES OR SERVICES/PRICES
Bid in accordance with the requirement of the solicitation, as a lump sum.
C. DESCRIPTION/SPECIFICATIONS
Specification & Drawings posted with solicitation notice on website www.fbo.gov.
D. PACKAGING AND MARKING
There are no packaging and marking requirements.
E. INSPECTION AND ACCEPTANCE
52.223-3 Hazardous Material Identification and Material Safety Data. (JAN 1997)
52.246-12 Inspection of Construction. (AUG 1996)
F. DELIVERIES OR PERFORMANCE
52.211-13 Time Extensions. (SEP 2000)
52.247-34 F. O. B Destination. (Nov 1991) http://www.fbo.gov/
693JF719B000004 Page 22 of 48
G. CONTRACT ADMINISTRATION DATA
G.1 INVOICE REQUIREMENTS
All vendors have the option to send invoices electronically.
Invoices MUST be in PDF format and submitted to: MARADInvoices@FAA.GOV
Invoices can be mailed or submitted to the following Address: U.S. Mail
MARAD, A/P Branch AMZ316
P.O. Box 25710 Oklahoma, OK 73125
Commercial Mail
MARAD A/P Branch, AMZ316
6500 S. MACARTHUR BLVD.
Oklahoma, City, OK 73169
a. Invoices shall be submitted through Electronic Invoice System (EIS) and inform MARAD of the submittal to EIS
b. To constitute a proper invoice, the invoice must include the following information and/or documentation
(1) Name of the business concern (Note this name much match the name on the contract document exactly. If another name is used on the invoice such as a Doing
Business As (DBA) the name on the contract document must also be listed on the invoice document). Invoices that does not contain the name on the contract will be rejected.
(2) Invoice Number and date
(3) Contract Number, or other authorization for supplies delivered or services performed (4) Description price and quantity of supplies and services actual delivered or rendered (5) Shipping and payment terms
(6) Name (where practicable), title, phone number, and complete mailing address of responsible official to whom payment is to be sent.
(7) Other substantiating documentation or information as required by the contract.
Upon completion of the web-based system, invoices shall be available on-line.
The on-line version of the invoice shall provide the ACO with the capability of approving in full or partial payments or rejecting invoices in total.
mailto:MARADInvoices@FAA.GOV
693JF719B000004 Page 23 of 48
ELECTRONIC FUNDS TRANSFER (EFT) PAYMENT REQUIREMENTS
FAR 52.223-33 Payment by Electronic Funds Transfer System for Award
Management registration is included in this solicitation/contract. All Contractor payments will be made by EFT unless accepted or otherwise determined by the paying office designated in the contract.
POINTS OF CONTACT
a. PROCURING CONTRACTING OFFICER (PCO)
DOT/Maritime Administration
Judy Bowers, Contracting Officer
1200 New Jersey AVE SE
Washington, DC 20590
Email: Judy.Bowers@dot.gov
b. LOCAL CONTRACT ADMINISTRATION
All post award Correspondence shall be directed to the Administrative (ACO) Contracting
Officer except as otherwise specified at the following address:
U.S. Merchant Marine Academy
Maxmillian Diah, Chief of Procurement
300 Steamboat Road
Kings Point, NY 11024
Email: diahm@usmma.edu
G.2 ADDRESS OF CORRESPONDENCE
All correspondence except as otherwise specified, shall be directed to the Contract Specialist at the following address:
DOT/Maritime Administration
Nicole A. Price, Contracting Specialist
1200 New Jersey AVE SE W28-201
Washington, DC 20590
Email: Nicole.Price@dot.gov mailto:Judy.Bowers@dot.gov mailto:diahm@usmma.edu mailto:Nicole.Price@dot.gov
693JF719B000004 Page 24 of 48
G.3 CONTRACTING OFFICER'S REPRESENTATIVE
a. The Contacting Officer's Representative (COR) is responsible for the technical aspects of the project and technical liaison with the Contractor. The COR is also responsible for the final inspection and acceptance of all reports and such other responsibilities as may be specified in the contract.
b. The COR is not authorized to make any commitments or otherwise obligate the
Government or authorize any changes which affect the contract price, terms or conditions. Any Contractor request for changes shall be referred to the Contracting
Officer directly or through the COR. No such changes shall be made without the expressed prior authorization of the Contracting Officer. The COR may designate assistant (COR(s) to act for him/her by naming such assistant in writing and transmitting a copy of such designation through the Contracting Officer to the
Contractor.
c. The COR for this contract will be:
U.S. Merchant Marine Academy
Richard Ronde, Jr.
Planner/Estimator
300 Steamboat Road
Kings Point, NY 11024
Office: (516) 726-5606
Email: ronder@usmma.edu
d. The COR may be changed by the Government at any time, but notification of the change, including the name and address of…