ROBO_-_NP-WHHO_Lafayette_Park.pdf
PDF 25 KB Posted
- Attached to
- White House - Lafayette Park Federal contract opportunity
- Solicitation number
- 693C73-18-B-000009
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0002_-_NP-WHHO_Lafayette_Park.pdf | ||
| IFB_Solicitation_-_NP-WHHO_Lafayette_Park.pdf | ||
| VETS-4212_Form.pdf | ||
| Supplemental_Specifications_SOD.pdf | ||
| Categorical_Exclusion_Form_(NEPA).pdf | ||
| Plans_NP_WHHO_Lafayette_Park.pdf | ||
| FP14_Eng.pdf | ||
| Synopsis_-_NP-WHHO_Lafayette_Park.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration Eastern Federal Lands Highway Division
Bid Opening for
White House / Lafayette Park
PROJECT: NP-WHHO_Lafayette_Park
SOLICITATION NO. 693C73-18-B-000009
December 5, 2017 at 2:00 p.m.
Sterling, VA
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-18-B-000009 PROJECT NUMBER: NP-WHHO_Lafayette_Park
December 5, 2017, 2:00 p.m. local time
BIDDER BID TOTAL DAYS TOTAL PRICE
M&F Concrete Schedule A $223,626.90
75 Calendar Days Schedule A $223,626.90
Firvida Construction Corp. Schedule A $253,628.00
75 Calendar Days Schedule A $253,628.00
Knight Solutions Schedule A $762,769.09
75 Calendar Days Schedule A $762,769.09
Encon Corporation Schedule A $264,640.75
75 Calendar Days Schedule A $264,640.75
Garcete Construction Schedule A $242,996.00
75 Calendar Days Schedule A $242,996.00
The performance period for the completion of Schedule A is 75 calendar days.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-18-B-000009 PROJECT NUMBER: NP-WHHO_Lafayette_Park
December 5, 2017, 2:00 p.m. local time
BIDDER BID TOTAL DAYS TOTAL PRICE
AllGreen Landscape Co. Schedule A $158,429.00
75 Calendar Days Schedule A $158,429.00
PWC Builders Schedule A $210,000.00
75 Calendar Days Schedule A $210,000.00
Pavkov Contracting Schedule A $351,040.00
75 Calendar Days Schedule A $351,040.00
Schedule A
75 Calendar Days Schedule A
Engineer’s Estimate Schedule A $225,000.00
75 Calendar Days Schedule A $225,000.00
The performance period for the completion of Schedule A is 75 calendar days.
File details come from the government source that posted it.